January 21, 2010
The Federal Contaminated Sites Action Plan (FCSAP) is a collaborative effort by federal departments, agencies, and consolidated Crown corporations ("custodians") to identify, assess and prioritize the remediation or risk management of federal contaminated sites based on the level of risk posed to human health and the environment.
Originally developed in response to the 2004 federal budget commitment of $3.5 billion in multi-year funding, the FCSAP is a 15-year cost-shared program that provides a mechanism to accelerate the remediation or risk management of priority federal contaminated sites. The FCSAP expands on the previous Federal Contaminated Sites Accelerated Action Plan (FCSAAP) (which ran during 2003-04 and 2004-05), prior to which the majority of departments and agencies collectively reallocated up to $100 million per year1 from other priorities to risk-manage and/or remediate their federal contaminated sites.
In its third year of operation (2007-08), expenditures were reported nationally by 15 custodians for 276 remediation / risk management projects (consisting of 519 sites where activity was undertaken) and 590 assessment projects (consisting of 2269 sites where activity was undertaken). These projects included the cleanup of sites where the environmental consequences of past practices were not fully understood, including such sites as: harbours and ports, military bases, former Distant Early Warning (DEW) line sites, light stations, and abandoned mines.
FY 2007-08 at a glance:
$188.4 million in total FCSAP expenditures, including federal contaminated sites projects, program management, secretariat/expert support services, and PWGSC accommodation costs
$146.9 million in FCSAP funds spent on remediation/risk management projects
$19.2 million in federal custodian funds spent on remediation/risk management projects funded under FCSAP
$18.5 million in FCSAP funds spent on assessment projects
$6.1 million in custodian funds spent on assessment projects
276 priority remediation/risk management projects funded
2269 assessment sites funded (on 590 projects)
In 2007-08, $188.4 million of FCSAP funds were spent on federal contaminated sites projects, program management, secretariat/expert support services, and Public Works and Government Services Canada (PWGSC) accommodation costs. In addition to the FCSAP funds, and in adherence to the Government of Canada's "polluter pays" principle, custodians contributed $25.3 million in cost-share. Of the total amount spent ($213.7 million), the greatest proportion of the funds ($190.7 million) went towards the actual assessment and remediation / risk management of federal contaminated sites.
As of March 31, 2008, a liability of $3.332 billion was recorded for approximately 2360 contaminated sites, compared with a liability of $3.014 billion for 2630 sites in 20072. This increase in federal environmental liability is primarily attributed to changes recorded to planned cost estimates for remediation activities of large projects. It is also attributed to the fact that increased spending on assessment activities results in a more accurate estimate of liability, often leading to an increase. Continued work on all types of FCSAP projects will result in further refinement of liability estimates, and total liability is expected to decline as sites are remediated. If you have questions or comments on this report, or wish to obtain additional copies of this report, please contact:
FCSAP Secretariat
Contaminated Sites Division
Environmental Protection Operations Directorate
Environment Canada
351 St. Joseph Boulevard, 15th Floor
Gatineau QC K1A 0H3
Tel: 819-934-2155 / Fax: 819-994-0502
Email: fcsap.pascf@ec.gc.ca
The Federal Contaminated Sites Action Plan (FCSAP) is a collaborative effort by federal departments, agencies, and consolidated Crown corporations ("custodians") to identify, assess and prioritize the management of federal contaminated sites based on the level of risk they pose to human health and the environment. The Program has a number of key objectives:
Contaminated Site
A site at which substances occur at concentrations (1) above background levels (background is defined as an area not influenced by chemicals released from the site under evaluation) and posing or likely to pose an immediate or long-term hazard to human health or the environment, or (2) exceeding levels specified in policies and regulations.
From A Federal Approach to Contaminated Sites, developed by the Contaminated Sites Management Working Group, November 1999The FCSAP was established as a 15-year cost-shared program, developed in response to the 2004 federal budget commitment of $3.5 billion in multi-year funding for priority federal contaminated sites.
The number of custodians that participate in FCSAP varies annually, as do the number and type of projects that receive funding under FCSAP. In the fiscal year 2007-08, 15 custodians received funding through FCSAP. Projects included sites where the environmental consequences of past practices were not fully understood, including such sites as: harbours and ports, military bases, former DEW line sites, light stations, and abandoned mines.
The FCSAP builds on the previous two-year Federal Contaminated Sites Accelerated Action Plan (FCSAAP), which was in place from fiscal year 2003-2004 to fiscal year 2004-2005. Before FCSAAP, the majority of departments and agencies collectively reallocated up to $100 million per year3 from other priorities in order to remediate or to manage the risks associated with their contaminated sites. The majority of the spending was concentrated in a small number of departments that were responsible for the highest proportion of federal contaminated sites.
Environment Canada (EC) and the Treasury Board Secretariat (TBS) jointly administer FCSAP. Within EC, the FCSAP Secretariat provides program oversight and administers the non-financial aspects of the program. EC manages the project selection process, maintains a secure website, develops communication materials, and monitors and reports on progress. TBS ensures the Program's adherence to Treasury Board (TB) policies on the management of federal real property, reviews the financial aspects of proposals, assesses custodians' reallocation capacity, administers the fund, and advises the FCSAP Secretariat on the monitoring of Government-wide progress.
The FCSAP helps custodians address priority contaminated sites where the nature and mobility of contaminants represent the highest risk to human health and the environment. The responsibility and accountability for managing contaminated sites rests with custodians. Custodians are the project champions and are responsible for program delivery: identifying and prioritizing sites of concern; conducting risk assessments; developing remediation / risk management plans and project funding proposals consistent with their contaminated sites management plans; implementing approved projects; and achieving the contaminated sites management objectives set out in the contaminated sites management plans and project proposals. Custodians are also expected to incorporate linkages with other government of Canada initiatives such as Aboriginal training and employment, innovative technology usage, and federal brownfields, where possible.
EC, Health Canada (HC), Fisheries and Oceans Canada (DFO), and Public Works and Government Services Canada (PWGSC) are FCSAP expert support departments. The role of the expert support departments is to assist the Secretariat with development and promotion of best practices, and to ensure that custodians adopt a consistent approach to the assessment to human health and ecological risk across the program. EC, HC and DFO also:
EC, HC, and DFO also carry out their mandates related to regulatory compliance. EC and HC focus on improving and promoting environmental and health risk assessments as a key part of the project selection process, while DFO ensures that site remediation or risk management activities do not further compromise any fish or fish habitat resources.
PWGSC provides project management tools and related training, and acts as the lead department for liaison with industry. PWGSC also works closely with Industry Canada (IC), which supports the Program by working to optimize the participation of the Canadian environmental industry in the remediation of federal contaminated sites, and to facilitate the introduction and use of innovative remediation technologies at these sites. PWGSC is responsible for disseminating information on innovative technologies so that custodian departments, other levels of government, and industry can benefit from technological advances and strategies.
In addition, three interdepartmental groups provide strategic direction:
FCSAP was developed in 2005 as a comprehensive 15-year program intended to support custodians in reducing risks to human health and the environment and decreasing federal financial liabilities associated with priority federal contaminated sites. Although any site that has been identified as potentially contaminated based on past (prior to July 1, 2002) activities on or near the site is entitled to assessment funding, only those sites classified as Class 1 or 2 under the Canadian Council of Ministers of the Environment (CCME) National Classification System4 are eligible for remediation / risk management funding. It is expected that the existing list of Class 1 and Class 2 priority sites that will seek funding under FCSAP will change in future years as remediation / risk management projects progress, newly assessed sites are considered, and remediation / risk management plans are fine-tuned.
In recognition of the "polluter pays" principle underlying the program, FCSAP operates on a cost-shared basis with custodians. To assist custodians in classifying their contaminated sites, assessment funding is available through FCSAP at an 80/20 (FCSAP/custodian) cost-share, up to a program maximum of $25 million per year. For remediation / risk management projects with total estimated project costs of $10 million or less, the cost-share is also 80/20 (FCSAP/custodian). Once estimated project costs for remediation / risk management projects exceed $10 million, the custodian's share is reduced to 10% on the amount exceeding $10 million. Certain exceptionally large projects with total costs in excess of $90 million may be eligible for full funding of project costs.
In order to give custodians the flexibility to better manage their contaminated sites programs, FCSAP allows custodians to internally reallocate FCSAP funds in-year among projects. In so doing, FCSAP is providing custodians with the flexibility to respond to unforeseen circumstances within a given fiscal year, while continuing to make progress and meet the requirements of the Program.
In 2007-08, funding was approved for assessment and remediation / risk management projects, program management activities, and program support activities for expert support departments, the FCSAP Secretariat, and TBS. Of the $280 million that was available in the fiscal framework to be allocated to remediation / risk management and assessment projects in 2007-08, $217.7 million was allocated to the custodian departments, with no more than $25 million of this amount to be used to conduct assessment projects. Actual FCSAP project expenditures for 2007-08 totalled $165.4 million-approximately $52 million less than was requested. Available FCSAP funding for 2007-08 included the funds allocated ($217.7 million) and the annual in-year adjustments (including funds carried forward from 2006-07) of $8.5 million, giving a total of $226 million. Hence, the total variance between available funding and spent funds was $61 million.
In addition to federal contaminated sites expenditures, program management funds were spent by custodians on salaries to support the implementation of the custodian's contaminated sites management program through FCSAP, and to fund various operational costs related to program planning, implementation and reporting (i.e. travel, training, etc.).
In 2007-08, $8,023,752 of program management funding was available to 12 custodians. Of the total amount available, $471,152 was transferred from previous fiscal years and $7,552,600 was approved in Treasury Board submissions. Overall, $6,711,316 was spent.
The breakdown of program management expenditures and variance for 2007-08 is outlined in Table 1.
| Program Management | ||||
|---|---|---|---|---|
| Planned FCSAP Expenditures ($) |
Adjustments ($) |
Actual FCSAP Expenditures ($) |
Variance ($) (approved + adjustment - expenditure) |
|
| 1 Funding brought forward from the previous fiscal year | ||||
| 2 Funds received from the FCSAP Secretariat or Expert Support | ||||
| Agriculture and Agri-Food Canada | 150,000 | 30,0001 | 120,000 | 60,000 |
| Correctional Service Canada | 67,670 | 67,670 | 0 | |
| Environment Canada | 467,958 | 467,958 | 0 | |
| Fisheries and Oceans Canada | 1,033,315 | 22,7312 | 894,046 | 162,000 |
| Health Canada | 121 429 | 121 429 | 0 | |
| Indian and Northern Affairs Canada | ||||
| Indian and Inuit Affairs Business Line | 735,035 | 735,035 | 0 | |
| Northern Affairs Organizations | 2,213,980 | 2,293,652 | -79,672 | |
| Department of National Defense | 150,000 | 0 | 150,000 | |
| National Resources Canada | 150,000 | 0 | 150,000 | |
| Parks Canada Agency | 366,713 | 418,4211 | 367,414 | 417,720 |
| Public Works and Government Services Canada | 200,000 | 191,829 | 8,171 | |
| Royal Canadian Mounted Police | 395,500 | 340,434 | 55,066 | |
| Transport Canada | 451,000 | 451,000 | 0 | |
| Total Expenditures | 7,552,600 | 471,152 | 6,711,316 | 1,312,436 |
FCSAP funded two types of projects in 2007-08: assessment and remediation / risk management. In the past, there were also several care and maintenance projects funded under FCSAP5 , however, given that the majority of activities on these previously-identified care and maintenance projects are now remediation activities, these projects have been converted to remediation / risk management projects. Some remediation / risk management projects may still have one or more care and maintenance activities.
Assessment Projects - Funding assessment work is an important part of FCSAP. By assessing sites suspected of being contaminated, the federal government is able to more accurately estimate human health and environmental risk, and the level of financial liability for historically contaminated federal sites.
A full-scale assessment of the severity of contamination at a site can be a lengthy and complex process (see steps 1 to 6 in the Ten Step Process in section 2.0). An FCSAP assessment project is considered completed once all sites within the project have a status of either "Assessment Completed: Requires no Further Action" or "Assessment Completed: Requires Remediation / Risk Management."
Following assessment, many sites are determined not to pose a risk to human health and/or the environment-these sites are considered closed.
Remediation / Risk Management Projects - After a site is assessed and the need for contamination to be addressed is confirmed, a remediation / risk management plan is used to explore the various alternatives and to identify the preferred option to reduce the risk to human health and the environment. The remediation / risk management method that is chosen is designed to address the unique conditions of the site. Common remediation activities involve reducing exposure to contaminants by removing, destroying or containing them.
Under FCSAP, a site is considered completed once Step 9 (confirmatory sampling and final reporting) has been finished following site remediation, or once Step 10 (long-term monitoring) is finished at risk managed sites. A completed site is not eligible for FCSAP funds in the future unless it is reactivated by the custodian based on the discovery of new information.
An FCSAP remediation / risk management project is considered completed once all sites within the project have been completed.
Federal Approach for Addressing Contaminated Sites-Ten Step Process
Step 1 - Identify Suspect Sites: Identify potentially contaminated sites based on activities (past or current) on or near the site.
Step 2 - Historical Review: Assemble and review all historical information pertaining to the site.
Step 3 - Initial Testing Program: Provide a preliminary characterization of contamination and site conditions.
Step 4 - Classify Contaminated Site using the CCME National Classification System: Prioritize the site for future investigations and/or remediation / risk management actions.
Step 5 - Detailed Testing Program: Focus on specific areas of concern identified in Step 3 and provide further in-depth investigations and analysis.
Step 6 - Reclassify the Site using CCME National Classification System: Update the ranking based on the results of the detailed investigations.
Step 7 - Develop Remediation / Risk Management Strategy: Develop a site-specific plan to address contamination issues.
Step 8 - Implement Remediation / Risk Management Strategy: Implement the site-specific plan that addresses contamination issues.
Step 9 - Confirmatory Sampling and Final Reporting: Verify and document the success of the remediation/risk management strategy.
Step 10 - Long-Term Monitoring: If required, long term-monitoring ensures that remediation and long-term risk management goals are achieved.
Source: A Federal Approach to Contaminated Sites (CSMWG, 1999)
Note: The steps indicate the stage of each site and not the effort associated with each step. Significantly more time and energy are required to complete Step 8 than any other step.
Progress in managing FCSAP projects is tracked according to the 10 steps of the CSMWG Federal Approach to Contaminated Sites (see box). However, managing a contaminated site is a complex and multi faceted undertaking, particularly at large and/or highly contaminated sites. Because contaminated sites may contain various types of contaminants in different media (e.g. soil, sediment, groundwater), different remediation activities may be required at different times throughout the project life cycle. This variability can affect how progress is described. Also, activities on contaminated sites do not necessarily progress in the linear manner described by the Ten Step Process. At times, it may be necessary to carry out urgent activities that would normally be undertaken in later steps in order to prevent a severe environmental event from occurring.
In 2007-08, 15 custodians reported activity at 276 remediation / risk management projects, and 590 assessment projects. Total expenditures under FCSAP by custodian and project category are summarized in Table 2.
Custodian |
Assessment |
Remediation/risk management |
||||||||
|---|---|---|---|---|---|---|---|---|---|---|
Number of projects with activity |
Number of sites with activity |
FCSAP funding available*($) |
FCSAP funds spent ($) |
Custodian share spent |
Number of projects with activity |
Number of sites with activity |
FCSAP funding available*($) |
FCSAP funds spent ($) |
Custodian share spent |
|
Total |
590 |
2269 |
27,886,247 |
18,483,725 |
6,142,690 |
276 |
519 |
198,322,521 |
146,879,259 |
19,182,048 |
Total FCSAP funds spent on assessment and remediation/risk management projects |
162,362,984 |
|||||||||
Agriculture and Agri-Food Canada (AAFC) |
21 |
36 |
796,000 |
445,897 |
111,474 |
1 |
1 |
500,000 |
562,503 |
140,626 |
Canada Border Services Agency |
- |
- |
- |
- |
- |
2 |
2 |
341,360 |
327,098 |
82,346 |
Correctional Service of Canada |
- |
- |
27,921 |
- |
- |
1 |
1 |
1,062,086 |
1,349 |
337 |
Environment Canada (EC) |
15 |
203 |
3,976,350 |
634,652 |
158,663 |
4 |
140 |
5,364,209 |
2,696,354 |
473,169 |
Fisheries and Oceans Canada (DFO) |
71 |
605 |
6,357,929 |
3,819,994 |
954,998 |
103 |
103 |
10,514,184 |
3,877,973 |
969,474 |
Health Canada (HC) |
10 |
10 |
136,000 |
136,000 |
262,381 |
7 |
7 |
1,174,366 |
442,585 |
136,383 |
Indian and Northern Affairs Canada (Indian and Inuit Affairs Business Line) |
47 |
580 |
3,232,003 |
2,310,115 |
567,679 |
31 |
45 |
10,515,480 |
7,607,531 |
1,901,810 |
Indian and Northern Affairs Canada (Northern Affairs Program) |
118 |
118 |
1,559,122 |
898,806 |
224,706 |
26 |
29 |
99,231,835 |
75,569,559 |
5,927,381 |
The Jacques Cartier and Champlain Bridges Inc. (JCCBI) |
- |
- |
- |
- |
- |
- |
- |
92,000 |
- |
- |
National Defence (DND) |
43 |
167 |
5,310,337 |
5,310,337 |
2,347,114 |
52 |
103 |
51,004,136 |
42,824,283 |
6,323,902 |
National Capital Commission (NCC) |
23 |
66 |
609,670 |
566,633 |
141,658 |
2 |
2 |
192,000 |
192,000 |
113,139 |
Natural Resources Canada (NRCan) |
4 |
4 |
175,810 |
35,428 |
8,857 |
- |
- |
- |
- |
- |
Parks Canada Agency (PC) |
34 |
50 |
1,406,341 |
1,343,122 |
391,705 |
9 |
11 |
1,530,856 |
1,004,774 |
303,013 |
Public Works and Government Services Canada (PWGSC) |
34 |
50 |
1,406,341 |
1,343,122 |
391,705 |
9 |
11 |
1,530,856 |
1,004,774 |
303,013 |
Royal Canadian Mounted Police (RCMP) |
188 |
397 |
2,820,000 |
2,020,622 |
519,515 |
9 |
9 |
2,213,600 |
912,112 |
228,027 |
Transport Canada (TC) |
5 |
7 |
520,000 |
111,000 |
103,000 |
14 |
17 |
11,548,948 |
8,733,435 |
1,996,978 |
* Total FCSAP funding available = 2007–08 allocated amount + brought forward amounts from 2006–07.
Table 3 provides a summary of the approved FCSAP funding, actual FCSAP expenditures and the corresponding custodian expenditures.
As described in Section 1.2, custodians are required to meet cost shares on an annual basis. In fiscal year 2007-08, four custodians (Department of National Defence [DND], Indian and Northern Affairs Canada-Northern Affairs Organization [INAC-NAO], EC and Transport Canada [TC]) had projects that produced adjusted FCSAP cost shares6. All other federal custodians were required to respect the typical 80/20 (FCSAP/custodian) cost share requirement.
In 2007-08, all but two custodians (INAC (including both NAO and Indian and Inuit Affairs Business Line [IIABL]) and EC) either met or surpassed their annual cost share requirement. The shortfalls were calculated as follows: $837,179 for INAC-NAO (which represents 14% of their total custodian expenditures); $85,713 for EC (14% of their total custodian expenditures); and $9,923 for INAC-IIABL (less than 1% of their total custodian expenditures).
Project type |
FCSAP funding allocated (millions) |
Project work undertaken in fiscal year 2007–08 |
|||
|---|---|---|---|---|---|
Number of projects with activity |
Number of sites with activity |
FCSAP Fund expenditures (millions) |
Custodian expenditures (millions) |
||
Total |
$217.697 |
866 |
2788 |
$165.36 |
$25.32 |
Remediation/risk management |
$192.69 |
276 |
519 |
$146.88 |
$19.18 |
Assessment |
$25.0 |
590 |
2269 |
$18.48 |
$6.14 |
Funding of assessment projects is an important part of FCSAP. The results of assessments facilitate the identification of risks to human health and the environment, and the accurate estimation of federal financial liability for contaminated sites. In assessment Steps 1 to 4 (initial) and 5 to 6 (detailed) of the Ten Step Process, scientifically defensible work is undertaken to identify the presence, nature and extent of site contamination.
In 2007-08, $18,483,725 of the available FCSAP assessment funds ($27,886,247) were spent by 12 different custodians at 2269 sites, grouped into 590 projects. The available amount included $25,000,000 that was allocated in 2007-08, and $2,886,247 of unused FCSAP assessment funds that were transferred from the previous fiscal year. Assessment activities were most prominent in Manitoba (567 sites), Atlantic Canada (482 sites), and Quebec (228 sites), as a result of large scale assessment initiatives undertaken by DFO and the Royal Canadian Mounted Police (RCMP) in Atlantic Canada, and Quebec and INAC-IIABL in Manitoba. Overall, the number of sites assessed in 2007-08 (2269) was almost double the number of assessments in fiscal year 2006-07 (1252) and more than three times the number of sites assessed in 2005-06 (660). A summary of 2007-08 assessment projects, sites and FCSAP expenditures is presented by province/territory in Table 4 and by custodian in Table 5.
Province/territory |
Number of projects with activity |
Number of sites with activity |
Estimated FCSAP funds spent ($)8 |
|---|---|---|---|
Total |
590 |
2269 |
18,483,7259 |
Alberta |
44 |
142 |
1,479,860 |
British Columbia |
52 |
163 |
1,268,335 |
Manitoba |
27 |
567 |
2,553,448 |
New Brunswick |
56 |
106 |
718,102 |
Newfoundland and Labrador |
20 |
218 |
1,185,452 |
Northwest Territories |
51 |
311 |
2,246,400 |
Nova Scotia |
26 |
25 |
219,687 |
Nunavut |
111 |
148 |
2,070,820 |
Ontario |
53 |
150 |
1,820,041 |
Prince Edward Island |
11 |
30 |
196,418 |
Quebec |
62 |
228 |
3,403,393 |
Saskatchewan |
35 |
183 |
901,028 |
Yukon Territory |
6 |
6 |
84,851 |
Federal custodian |
Number of projects |
Number of sites |
FCSAP funds spent ($) |
|---|---|---|---|
Total |
590 |
2269 |
18,483,725 |
Agriculture and Agri-Food Canada |
21 |
36 |
445,897 |
Environment Canada |
15 |
203 |
634,652 |
Fisheries and Oceans Canada |
17 |
605 |
3,819,994 |
Health Canada |
10 |
10 |
136,000 |
Indian and Northern Affairs Canada |
|
|
|
Indian and Inuit Affairs Business Line |
47 |
580 |
2,310,115 |
Northern Affairs Organization |
118 |
118 |
898,806 |
National Capital Commission |
23 |
66 |
566,633 |
Department of National Defence |
43 |
167 |
5,310,337 |
Natural Resources Canada |
4 |
4 |
35,428 |
Parks Canada Agency |
34 |
50 |
1,343,122 |
Public Works and Government Services Canada |
11 |
26 |
851,119 |
Royal Canadian Mounted Police |
188 |
397 |
2,020,622 |
Transport Canada |
5 |
7 |
111,000 |
A total of $25,000,000 was approved for assessment activities in 2007-08. As shown in Table 3, custodians contributed funds amounting to $6,142,690 and FCSAP provided $18,483,725 in funding for assessment activities. As indicated in the financial table in Appendix 3b, the difference between planned and actual expenditures for assessment projects was $9,402,522, after adjusting for the funds transferred from the previous fiscal year and funds transferred from Expert Support ($2,886,24710). The variance is due to the following factors:
Variance between planned and actual expenditures for individual assessment projects can be attributed to a variety of factors, including the reallocation of funding from previously approved sites to more urgent assessment requirements, shifting custodian demands or priorities, and the difficulty in initial estimation of the projected costs of assessments because the nature and extent of contamination is unknown at the outset of the project.
The Fisheries and Oceans Canada (DFO) is the custodian of a diverse array of urban, rural (mostly coastal) and remote properties. DFO is one of the largest custodians of real property within the federal government, with interest in more than 8200 properties across the country. The Department is a program manager, regulator and facilitator; a building owner; an operator; and a manager of assets such as buildings, vehicles, aircraft, vessels and harbours.
Minor Shore Lights have served as navigational aids to vessels for centuries. Of DFO's entire property portfolio, approximately 2200 properties are classified as Minor Shore Lights. There are a variety of different types of Minor Shore Lights under the custodianship of DFO, including those with an aluminum/steel skeleton tower, a wooden structure, or a fibreglass cylindrical structure, among others. These aids are fixed in place, equipped with a light, and can also include former light stations. Historically, the use of mercury baths, compressed gas, batteries and lead-based paint were common to these sites and have subsequently resulted in high levels of heavy metals, hydrocarbons and other pollutants at many of these locations.
The assessment of these properties is risk-based and takes into account the likelihood of contamination based on past and/or present operations, and the potential for risks to human health and the environment. The anticipated future use of the site is taken into account during the assessment and management of these sites, including whether or not the Department intends to retain the site or the site is being actively marketed for divestiture.
In 2007-08, assessment activity-resulting in one of the following four outcomes-was reported for 2269 sites. Figure 1 presents the distribution of the 2007-08 assessment outcomes on these sites.
There were an additional 1063 sites, which were reported as not assessed with no further action planned. These had generally been divested in-year or were the result of multiple Federal Contaminated Sites Inventory numbers that had been consolidated into one site. There were an additional 3263 active assessment sites that were not assessed in 2007-08.
Figure 1: FCSAP Assessment Results (2007-08)

(Description of the above image)
Referring to Figure 1 above, approximately 20% of the sites indicated the need for additional investigation and 16% of sites confirmed contamination in need of remediation / risk management. The remaining 65% of sites (for which assessment was either partially [23%] or fully [42%] completed) indicated that no further assessment activities would be undertaken in future fiscal years.
For the 2269 sites where assessment activity occurred, Figure 2 presents the last step completed in 2007-08. Seventy-six percent (76%) of sites were in the process of completing or had completed initial assessment work, which is delivered as steps 1 to 4 (identification of a suspect site, historical review, initial testing, and classification). Eleven percent (11%) of sites reported activity in the final stages of and/or the completion of a full site assessment, the second stage of assessment work which is undertaken in steps 5 and 6 (intrusive testing and site reclassification). The remaining 13% of sites had completed activities in Step 7 or higher (or were archived); and while Step 6 is normally considered the end point for the funding of assessments, occasionally-if the contamination is minimal-it is often more efficient and cost effective to undertake site remediation concurrent with assessment activities.
Figure 2: Status of FCSAP Assessment Projects by Step (2007-08)

(Description of the above image)
FCSAP supports federal custodians responsible for contaminated sites in all parts of Canada. In 2007-08, remediation / risk management accounted for 87% of total expenditure under the FCSAP and activity was reported throughout Canada at 276 remediation / risk management projects consisting of 519 sites. Within these 276 projects, 35% of projects (96 projects) reported delays or project setbacks, such as weather (12% of projects), industry capacity issues (8% of projects), the identification of new contamination (7% of projects), legal issues (3% of projects), and lack of custodian financial resources (1%).
A contaminated site is an area in which substances occur at concentrations above normally occurring background levels and pose, or are likely to pose, an immediate or long-term hazard to human health or the environment. Determining the risk posed by the presence of these substances involves identifying the potential receptors, determining potential exposure pathways, and estimating the level of risk based on the pathways. Refer to Appendix 1 for more information on how human health and ecological risks are evaluated under FCSAP.
Contamination of sites is primarily a result of past practices and activities whose environmental consequences were not fully understood at the time. The size and scope of federal contaminated sites vary greatly. Common examples include abandoned mines on federal Crown land in the North, airports, government laboratories, harbours, lighthouse stations, national parks, military bases and training facilities, former DEW line sites, and Aboriginal communities (Figure 3).
In 2007-08, the greatest proportion of remediation / risk management activity was reported for DFO light station projects (32% of all remediation / risk management projects) comprising 2% of total remediation / risk management FCSAP expenditures. The most significant proportion of expenditures was reported by INAC-NAO and DND (67% of all remediation / risk management expenditures) for activities undertaken at abandoned mines (6% of all remediation / risk management projects) and former DEW line sites (7% of all remediation / risk management projects) in the Canadian North.
Figure 3: Remediation / Risk Management Project Categories (2007-08)
A) Distribution of Projects by Project Category

(Description of the above image)
B) Distribution of Expenditures by Project Category

Remediation / risk management sites targeted for FCSAP funding have multiple types of affected media (Figure 4) that are contaminated by a wide variety of substances (Figure 5) resulting from one or more historic activities (Table 6). In 2007-08, soil contamination (86% of projects) and groundwater contamination (31% of projects) was most often related to the presence of metals (71% of projects), petroleum hydrocarbons (68% of projects), and polycyclic aromatic hydrocarbons (PAHs) (42% of projects). The main sources of contamination were fuelling activities/spilling (33% of projects), the presence of above ground storage tanks (AST)/piping (20% of projects with above-ground storage tank capacity of less than 2500 litres [AST< 2500L]; 21% of projects with AST>= 2500L), lead/metal/PCB containing paints (28% of projects), and batteries (24% of projects) on site.
Contaminant Soources |
Number of projects |
Percentage of projects |
|---|---|---|
Above-ground Storage Tank(s)/Piping (<2500L) |
56 |
20% |
Above-ground Storage Tank(s)/Piping (>=2500L)) |
57 |
21% |
Active Waste Disposal Site |
40 |
14% |
Adjacent Property |
3 |
1% |
Batteries |
66 |
24% |
Burn Pit |
21 |
8% |
Chemical Storage / Spill |
11 |
4% |
Creosote / Chromated Copper Arsenate Materials |
2 |
1% |
Dredging Materials |
1 |
0.3% |
Fill Materials |
13 |
5% |
Fire Fighting Training Area |
5 |
2% |
Fuelling Activities / Spill |
90 |
33% |
Galvanized Steel |
5 |
2% |
Golf Course Maintenance / Landscaping Activities |
0 |
0% |
Hazardous Construction Materials |
9 |
3% |
Historical Vessel Activities |
7 |
3% |
Inactive Waste Disposal Site |
35 |
13% |
Lead/Metal/PCB-Containing Paint |
78 |
28% |
Mercury Bath |
23 |
8% |
Mining and/or Milling Industries |
15 |
5% |
Miscellaneous On-Shore Harbour/Port Activities |
6 |
2% |
Oil and Gas Extraction Activities |
0 |
0% |
Other |
55 |
20% |
Other Waste Materials |
9 |
3% |
PCB Storage |
2 |
1% |
Pesticide / Herbicide Dump |
2 |
1% |
Petroleum Products Storage Area |
11 |
4% |
Road Salt Storage / Application |
9 |
3% |
Sewage / Liquid or Sewage Effluent |
5 |
2% |
Snow Disposal |
0 |
0% |
Tires |
1 |
0.3% |
Underground Storage Tank(s)/Piping |
28 |
10% |
Unknown/Unsure |
4 |
1% |
Waste Storage |
17 |
6% |
Figure 4: Contaminated Media at Remediation / Risk Management Sites (2007-08)

(Description of the above image)
Figure 5: Types of Contamination at Remediation / Risk Management Sites (2007-08)

(Description of the above image)
Due to the large number of remediation / risk management projects funded by FCSAP in 2007-08, for the purpose of distribution analyses the projects have been categorized based on their total expected completion costs. The estimated completion costs serve two functions: (1) to determine whether the project approval submission follows the streamlined or regular risk evaluation process12 and (2) to provide the FCSAP Secretariat with information useful for work-planning and estimating future demands on the program.
Total expected completion costs are structured as follows:
A detailed summary of the provincial/territorial distribution of remediation / risk management projects funded in 2007-08 is provided in Appendix 2, and the national distribution is mapped in Figure 6. The map identifies the number and location of projects with expected completion costs less than or equal to $10 million and projects with expected completion costs greater than $10 million. A large number of small projects that fall under DFO are distributed along the coastlines. High-cost projects (with total estimated expenditures of greater than $10 million) managed by INAC-NAO and by DND are concentrated in northern Canada.
Figure 6: National Distribution of FCSAP Remediation / Risk Management Projects (2007-08)

(Description of the above image)
The distribution of remediation / risk management projects is greatest in British Columbia (26% of projects), Atlantic Canada13 (21% of projects), and Quebec (17% of projects). However, when the location and expenditure data are compared, it becomes clear that the number of projects is not directly related to the overall project expenditures. Together, British Columbia, Quebec, and Atlantic Canada account for 64% of the number of projects but less than one quarter (<23%) of the associated expenditures. Similarly, northern Canada-Nunavut, Yukon, and the Northwest Territories-has only 18% of the projects but accounts for nearly three quarters (72%) of the FCSAP expenditures. The remaining 18% of projects and >5% of expenditures are distributed among the Prairies. (Figure 7)
Figure 7: National Distribution of Remediation / Risk Management Projects (2007-08)
A) Distribution of Projects by Province/Territory

B) Distribution of Expenditures by Province/Territory

(Description of the above images)
The relatively large concentration of remediation / risk management projects being undertaken in Quebec, Atlantic Canada, and British Columbia (Figure 7) is the direct result of many smaller scale projects (such as light stations and small craft harbours) that are being managed by DFO. As an overall percentage, in 2007-08 DFO was responsible for 37% of projects but only received 3% of the FCSAP annual funding allocated to remediation / risk management projects.
Unlike DFO, DND and INAC have fewer projects but they tend to be larger-primarily abandoned mines and former DEW line sites in the Canadian North. Located in Nunavut, the Yukon, and the Northwest Territories, these projects are associated with significant costs for logistics. In 2007-08 alone, DND and INAC-NAO combined spent $118,393,842 (80%) of the FCSAP funds allocated to remediation / risk management on 78 (28%) projects.
Refer to Figures 8A/B for details of the 2007-08 distribution of projects and expenditures by custodian.
Figure 8: Distribution of Remediation / Risk Management Projects by Custodian (2007-08)


(Description of the above images)
As indicated in Table 3, the total funding approved in 2007-2008 for FCSAP remediation / risk management projects was $192,689,953. Over the course of the year, custodians contributed funds amounting to $19,182,048, and spent $146,879,259 of FCSAP funding. The variance between allocated FCSAP funding and actual expenditures is $51,443,262, after adjusting for the funds transferred from the previous fiscal year ($5,632,568 14). This variance is due to several factors:
Under normal conditions, the implementation of the remediation / risk management plan falls under Step 8 of the Ten Step Process. Step 8 is composed of a wide variety of activities, which include evaluating the available remediation / risk management technology, performing cost-benefit analyses, selecting a contractor, and obtaining the necessary permits (i.e., water licence, land use permit, or approval under the Canadian Environmental Assessment Act). Because of the large number and variety of activities that can be undertaken under Step 8, it is often many years before a project is ready to proceed to Step 9. In Step 9 of the Ten Step Process, confirmatory sampling and final reporting are completed. Following Step 9, contaminated sites are considered to have been "addressed," other than where long-term monitoring (Step 10) is required. In 2007-08, approximately one third of sites were reported as Step 9 and 198 sites were marked as completed.
Figure 9 provides an overall picture of the highest step in which work was undertaken based on 2007-08 reporting and does not imply that the step is complete. Data are compiled at the project level and include two caveats: (1) not all sites in a project are necessarily in the same step and (2) the step is not necessarily complete - a project will often work through the same step for a number of years before proceeding to the next stage of the program.
Because remediation and risk management are non-linear processes, occasionally some projects experience an apparent "jump" in the step that is reported at fiscal year end. This is often the result of simultaneous assessment and remediation work occurring on larger projects. With complex multi-site projects, remediation may be occurring at one or more sites while assessment work or remediation planning is being undertaken at others. This apparent "back-tracking" of steps can also be related to the discovery of previously unidentified contamination, the need for additional delineation, and/or the overhaul or enhancement of an existing remediation plan, with the result that more work may be required than was previously anticipated. Therefore, the last step completed or the highest step with activity that is reported at the end of the fiscal year will reflect this change. Consequently, the proportion of projects within a given step (Figure 9) will reflect only the most advanced part of the project. The activities and expenditures for all remediation / risk management projects with FCSAP year-to-date expenditures greater than $1 million are summarized in Figure 10.
Figure 9: Status of FCSAP Remediation / Risk Management (RM) Projects by Step (2007-08)16

(Description of the above image)
| Steps in the Ten-Step Process (from the Federal Approach to Contaminated Sites) | |||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Federal custodian | Project | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | FCSAP funds spent on project ($) during FY 07-08 |
FCSAP funds spent on project ($) since FY 03-04 |
| Remediation / Risk management Projects | |||||||||||||
| * Funds spent in FY 2003-04 and 2004-05 under the Federal Contaminated Sites Accelerated Action Plan (FSCAAP) | |||||||||||||
| DFO | Bellville SCH | 464,684 | 1,641,090 | ||||||||||
| DND | 5 Wing Goose Bay | 3,315,444 | 12,913,025 | ||||||||||
| DND | 14 Wing Greenwood | 808,053 | 5,378,363 | ||||||||||
| DND | CAM1 - Jenny Lind Island | 2,473,850 | 2,650,410 | ||||||||||
| DND | CAM2 - Gladman Point | 94,316 | 7,948,212 | ||||||||||
| DND | CAM3 - Shepherd Bay | 4,605,906 | 10,143,911 | ||||||||||
| DND | CAM4 - Pelly Bay | 503,530 | 5,474,586 | ||||||||||
| DND | CAM5 - Mackar Inlet | 3,540,395 | 3,729,627 | ||||||||||
| DND | Colwood Aggregate | 2,895,982 | 6,415,694 | ||||||||||
| DND | DYEM - Cape Dyer | 5,135,020 | 26,794,104 | ||||||||||
| DND | FOX5 - Broughton Island | 223,505 | 8,046,152 | ||||||||||
| DND | FOX M - Hall Beach | 8,584,748 | 27,197,320 | ||||||||||
| DND | PIN 3 - Lady Franklin Point | 102,113 | 1,188,453 | ||||||||||
| DND | PIN 4 - Byron Bay | 1,979,982 | 3,864,034 | ||||||||||
| DND | Shea Heights/ Southside Tank Farm |
727,251 | 1,208,215 | ||||||||||
| DND | Suffield EPG | 328,356 | 1,464,322 | ||||||||||
| DND | Valcartier TCE | 2,915,968 | 14,915,905 | ||||||||||
| EC | Pacific Environment Centre | 2,523,305 | 7,845,254 | ||||||||||
| EC | Moose Factory Hospital | 144,000 | 1,308,182 | ||||||||||
| HC | Weagarrow Lake | 76,500 | 1,562,162 | ||||||||||
| INAC-IABL | 1550 Clifford Road | 113,000 | 1,245,430 | ||||||||||
| INAC-IABL | Barrenlands / Brochet Frontier School |
37,476 | 2,385,392 | ||||||||||
| INAC-IABL | Former God's Lake School Tankfarm | 250,560 | 1,006,044 | ||||||||||
| INAC-IABL | Former Red Sucker Lake School Tankfarm | 720,720 | 1,202,663 | ||||||||||
| INAC-IABL | Gixaala Nation Former Power House | 1,690,913 | 3,918,130 | ||||||||||
| INAC-IABL | God's lake Band Tankfarm | 250,560 | 1,171,545 | ||||||||||
| INAC-IABL | Mathias colomb Area 5B | 625,600 | 1,965,600 | ||||||||||
| INAC-IABL | Sandy lake Remediation Project | 833,380 | 1,407,898 | ||||||||||
| INAC-IABL | Wapekeka Soil Remediation Project | 1,480,000 | 1,480,000 | ||||||||||
| INAC-NAO | Axe Point | 1,481,313 | 2,218,024 | ||||||||||
| INAC-NAO | BARD - Atkinson Point | 1,481,313 | 2,218,024 | ||||||||||
| INAC-NAO | CAMF - Sarcpa Lake | 5,129,352 | 13,255,485 | ||||||||||
| INAC-NAO | Clinton Creek Mine | 147,686 | 2,307,336 | ||||||||||
| INAC-NAO | Colomac Mine | 11,730,181 | 67,468,314 | ||||||||||
| INAC-NAO | Contact Lake | 601,759 | 1,127,896 | ||||||||||
| INAC-NAO | Discovery Mine | 1,021,803 | 8,333,816 | ||||||||||
| INAC-NAO | Faro Mine | 15,537,999 | 65,999,183 | ||||||||||
| INAC-NAO | Fox C - Ekalugad Fiord | 5,009,951 | 14,328,319 | ||||||||||
| INAC-NAO | Giant Mine | 10,752,398 | 47,725,138 | ||||||||||
| INAC-NAO | Johnson Point | 382,897 | 1,952,815 | ||||||||||
| INAC-NAO | Mount Nansen Mine | 1,062,005 | 5,004,826 | ||||||||||
| INAC-NAO | Port Radium Mine | 4,012,197 | 10,099,631 | ||||||||||
| INAC-NAO | Radio Island | 2,906,473 | 6,705,672 | ||||||||||
| INAC-NAO | Roberts Bay Mine | 465,374 | 1,147,686 | ||||||||||
| INAC-NAO | Silver Bear Mines | 1,072,576 | 4,163,008 | ||||||||||
| INAC-NAO | Tundra-Taurcanis Mine | 4,700,244 | 10,179,121 | ||||||||||
| INAC-NAO | United Keno Hill Mine | 3,043,848 | 13,182,720 | ||||||||||
| INAC-NAO | Bushell Public Port | 2,985,241 | 5,675,207 | ||||||||||
| INAC-NAO | Former Remote Radar Site 59 | 102,367 | 3,493,854 | ||||||||||
| INAC-NAO | Fort Nelson Airport | 2,456,623 | 2,456,623 | ||||||||||
| INAC-NAO | Nitchequon | 254,981 | 3,588,350 | ||||||||||
| INAC-NAO | Rock Bay | 1,341,938 | 12,154,937 | ||||||||||
Remediation / Risk Management Activities
In 2007-08, 200 of 276 remediation / risk management projects undertook one or more remediation / risk management activity as part of Step 8 of the 10-step process. Of these 200 projects, 183 projects (66%) were reported as having active remediation / risk management activity (i.e. Step 8 B/C/D)17 , which is significantly higher than 2006-07, when only 44% of projects were actively being remediated / risk managed. The remaining 17 remediation / risk management projects reported activities in Step 8A.
A total of 513 remediation / risk management activities occurred across these 183 projects (123 (68%) of the 183 projects reported concurrent, multiple remediation / risk management activities). In total, 29 different classes of remediation / risk management activity were undertaken (Figure 11).
As in 2006-07, the most common remediation activities for 2007-08 were soil excavation (82 projects), the collection of hazardous materials (50 projects), and bioremediation (39 projects). The most common risk management strategies were the implementation of environmental (66 projects) and human health (41 projects) monitoring programs.
Figure 11: Remediation / Risk Management Activities Undertaken in 2007-08

(Description of the above image)
In addition to its primary objectives, FCSAP provides opportunities to maximize value for money by promoting linkages with other government of Canada socio-economic priority initiatives. Examples include links with skills development for, and training and employment of, Canadians, particularly in Aboriginal communities and in northern or rural areas; and competitiveness and technological advancement in the environment industry. Although custodians are generally responsible for identifying opportunities to incorporate such linkages into the management of their contaminated sites portfolio, they are largely supported in these activities by a number of other departments where there is alignment with departmental mandates.
Human Resources and Skills Development Canada has committed to working with custodians, Aboriginal organizations, the Environmental Careers Organization (ECO Canada), the private sector, learning institutions, and other stakeholders, to develop synergies between investments in the cleanup of contaminated sites and capacity building, for individual Canadians through training and skills development and for the environmental industry as a whole.
Similarly, through its expert support role, PWGSC, with support from Industry Canada, provides information on innovative technologies so that custodians, other levels of government, and industry can benefit from the technological advances that will accrue from this long-term program. PWGSC also provides liaison with the environment industry that delivers the remediation services required for program implementation, so that industry is aware of remediation requirements and can build capacity to meet projected future demand.
In 2007-08, ECO Canada tabled the report When Supply does not Meet Demand: Labour Gaps and Issues in Canada's Contaminated Sites Sector - 2008, which built on ECO Canada's previous study completed in 2006-07 Who will do the Cleanup? Canadian Labour Requirements for Remediation and Reclamation of Contaminated Sites - 2006-2009. The purposes of these studies were: (1) to provide a clearer picture of the labour demand for contaminated sites work; (2) to offer recommendations for next steps, which may include additional examination of the existing and forecasted labour supply, an analysis of training and educational gaps, and the development of procurement policies that reflect labour market reality and identified best practices; and (3) to build greater industry awareness and support for Government and private sector contaminated sites policies.
In response to the positive social and economic outcomes projected by ECO Canada, FCSAP has collected detailed data on the demand for Aboriginal skills and services generated by remediation / risk management projects funded under the Program. Overall in 2007-08, minimum levels of Aboriginal/Inuit employment (as stipulated by Comprehensive Land Claim Agreements in the North) were generally met or surpassed: eight custodians reported employing 663 Aboriginal individuals and training 202 Aboriginal individuals at 56 projects.
Examples of the range of FCSAP activities being undertaken in support of economic development and training for Aboriginal people in the environmental sector are highlighted below:
Indian and Northern Affairs Canada - Northern Affairs Organization
INAC-NAO is the custodian of most federal lands in the North. In the Northwest Territories and Nunavut, the NAO holds direct responsibilities for assessment and remediation of identified and suspected contaminated sites. Within the Yukon, the Organization's activities are guided by the requirements of the Devolution Transfer Agreement between the federal and Yukon governments, and responsibilities for contaminated sites are shared between the two levels of government.
As assessment and remediation / risk management activities are carried out in the North, the NAO strives to create social and economic benefits through direct employment of local people, support to local businesses, and training programs that develop local capacity and build skills. Commonly procured goods and services from local businesses include professional services (i.e., consulting, trades, remediation, construction, laboratory), winter road construction, transportation services, air charters, equipment rentals, and fuel.
Overall in 2007-08, a greater percentage of employees were northern Aboriginal, more employees received training, and a greater number of northern suppliers were hired than in 2006-07.
Employment and Business in the North (2007-08)
In 2007-08, the total reported employment for NAO-managed sites was 1027 people, down 28 people from the previous year. Despite the overall decrease in jobs in 2007-08, the proportion of Northern and Aboriginal employees increased: 73% of employees were from the North, and 49% of employees were Aboriginal. Twenty-eight sites reported doing business with 929 northern suppliers in 2007-08, of which 187 were northern Aboriginal suppliers. The total value of business with northern suppliers was roughly $25 million, 53% of which was from northern Aboriginal suppliers.
Workforce Training (2007-08)
Fifteen sites reported providing training to approximately 1460 employees in 2007-08, which is over twice the number of employees who were reportedly trained in 2006-07. Of the 1460 people who were trained in 2007-08, 73% were northerners and 26% were northern Aboriginal people. In total, 7278 hours of training were reported at sites in 2007-08, up from 5689 hours reported in 2006-07.
Source: Performance Report 2007-08, Indian and Northern Affairs Canada, Contaminated Sites Program
The scope of FCSAP presents a valuable opportunity for the Canadian remediation industry sector to respond to the needs and challenges of cleaning up federal contaminated sites by providing effective new solutions.
For the current purposes of FCSAP, the term "innovative technology" is defined as any treatment method for soil, groundwater or vapour, excluding traditional excavation and disposal or pump and treat technologies (i.e., ex situ treatment technologies where cost and performance data are readily available).18 However, the way that innovative technologies are analyzed is expected to evolve in future years of the Program, as technologies that were once considered innovative begin to form part of the standard suite of remediation options.
In 2007-08, 200 of 276 remediation / risk management projects undertook one or more remediation / risk management activity as part of Step 8 of the 10-step process. Of these 200 projects, 62 projects (31%) reported using one or more types of innovative remediation technology. Among the 62 projects that used innovative technology, 30 projects (48%) used innovative technology exclusively and 32 projects (52%) used a combination of innovative and conventional technologies or activities. Entirely conventional remediation / risk management technologies or activities occurred in the remaining 138 projects (69%) (Figure 12).
Figure 12: Conventional versus Innovative Remediation Options (2007-08)

(Description of the above image)
Under the current definition of innovative technology (see Section 3.1.2), 62 projects funded under FCSAP in 2007-08 incorporated one or more of the twelve types of innovative remediation technologies illustrated on Figure 13. Bioremediation accounted for the most significant proportion of innovative technologies (40%), followed by enhanced bioremediation/biopiles (17%), monitored natural attenuation (12%) and thermal treatment/desorption (9%).
In addition to the 62 projects that used innovative remediation technologies in 2007-08, innovative technologies were considered but not implemented at another 25 projects. Within this subset of projects that considered but did not implement innovative technologies, one or more of the following reasons were identified: cost (9 projects); time frame (13 projects); type of contamination (9 projects); site conditions (13 projects); public attitude/stakeholder consultation (6 projects); and/or the conventional technologies were considered most effective (15 projects).
Figure 13: Breakdown of Innovative Remediation Activity (2007-08)

(Description of the above image)
Over the same period, a number of conventional remediation technologies/activities occurred, as illustrated on Figure 14. Excavation accounted for the most significant proportion of conventional remediation technologies/activities (26%), followed by collection of hazardous materials (16%) and shipment to off-site landfills (13%).
Figure 14: Breakdown of Conventional Remediation Activity (2007-08)

(Description of the above image)
In a year-over-year comparison of remediation technology/activity by project, there was an increase in the number of projects in 2007-08 (276 vs. 61 in 2006-07) and an increase in the percentage of projects where remediation / risk management activities were taking place (72% vs. 28% in 2006-07). This reflects the increase in the number of new remediation / risk management projects being funded in 2007-08.
In terms of the distribution of technologies/activities within the active remediation portion of the process (Steps 8 B/C/D), in 2007-08 there was an increase in the number of projects using innovative technology (51 vs. 40 in 2006-07), but a decrease in the overall percentage of projects using innovative technology [51/183 projects (31%) vs. 40/61 projects (66%) in 2006-07]. There was also a decrease in the percentage of projects using innovative technologies exclusively [19/51 projects (48%) vs. 26/40 projects (65%) in 2006-07]. As in 2006-07, bioremediation was the most often implemented non-conventional technology in 2007-08.
Transport Canada: Bushell Public Port Facility Remediation
The Bushell Public Port Facility (PPF) was built in 1951, on the southeastern shore of Black Bay on Lake Athabasca in Saskatchewan, and was used until the mid-1980s to supply various goods and services to local mines as well as petroleum products to the communities of Bushell and Uranium City. As the mines closed and Bushell and Uranium City shrank in size, marine activity at the Bushell facility decreased to the occasional barge.
Over the years, the storage, unloading and loading of bunker C fuel oil at the facility resulted in oil contaminated soil, blast rock, bedrock and some sediment impacts in Black Bay. Following numerous assessments, EC's Pacific Region Environmental Services led the development of a Remedial Action Plan in early 2005 to address the remaining contamination. The Plan called for the excavation of the oil soaked blast rock and contaminated soil. Where oil had impregnated the bedrock within cracks and fissures, the bedrock was to be blasted and removed. The excavated contaminated soil, blast rock and bedrock were to be crushed in preparation for treatment by low-temperature thermal desorption, a process where the contaminated media would be put through an incinerator to burn off the oil residue. This method was chosen due to the costs and difficulty of other treatment strategies given the remote northern location of the facility.
When tendering the remediation contract in early 2005, a sustainable development component was incorporated, resulting in an alternative remedial option being revealed during the bid process. A local contractor was aware of Saskatchewan Highways' plan to resurface the Uranium City Airport runway within the next few years, and proposed the opportunity to recycle the oil contaminated rock and soil from the Bushell facility for use in the runway project. Given that Saskatchewan Highways would be quarrying and crushing new material and then applying oil to the crush in preparation for sealing the runway, this was considered a win-win opportunity. Saskatchewan Highways was contacted and an agreement was reached where Transport Canada would crush and mix the contaminated soil and rock to meet the required specification for the runway resurfacing, then transport it to the airport where Saskatchewan Highways would take ownership of the material. Cost savings of this option are $1,750,000 compared to the original plan for incineration. Cost savings for Saskatchewan Highways are expected in the order of $1,000,000. Considering the fuel savings, primarily from the incineration process that would have required nearly 1 000 000 litres of diesel fuel, this solution realizes a reduction in greenhouse gas emissions of approximately 2600 tonnes.
Transport Canada also signed an agreement with the Saskatchewan Research Council in order to transfer aggregate to them in its reclamation of the Cold War Legacy Uranium Mine and Mill Sites.

Penhold Transmitter Bunker - PWGSC Western Region
This is a former cold war-era communications bunker site located in farmland in southern Alberta. During the decommissioning of the bunker in 2001, petroleum hydrocarbon (PHC)-impacted soils were discovered both under the bunker and alongside the structure. Since there is no documentation indicating management of fuel at the military site, it is difficult to determine the time frame and the quantity of fuel released into the environment.
Multiple investigative programs were undertaken to complete delineation and to determine the best option for remediation of the soils. Due to the large amount of overburden materials that were not impacted, the cost of removal of the clean soil to access the contamination was prohibitive. A multi-phase extraction system was selected as the best way to remove the PHC product from the groundwater matrix and was installed at the site in 2004. This contract included hydraulic ground fracturing, installation of recovery wells and networks, and the supply and operation of a multi-phase recovery system to treat groundwater.
The system consists of six recovery wells installed 6 to 9 metres below surface, connected to two recovery networks. The recovery wells consist of 50-mm diameter PVC pipes, perforated with sand packs in the active zone. The infiltration gallery for return of treated groundwater consists of a trench 20 m long by 4 m deep, excavated and backfilled with pea gravel, located approximately 20 m up-gradient of the plume. Two summer networks were added in April 2006 to enhance the system, and these additional networks vastly improved productivity of removal of product within the groundwater matrix.
The custom multi-phase extraction system consists of a steel container unit divided by a firewall into a small control room and a larger process room. The control room houses the electrical power and control components and the air compressor, and the process room contains the treatment components, including liquid ring pump, vapour-liquid separator, in-line filter, oil-water separators, and carbon vessels for water treatment. The process room electrical equipment is equipped with explosion-proof components.
Fluid, vapour and air from the recovery wells are drawn into the network pipes and to the system by the liquid ring pump, and into the liquid-vapour separator. The vapour phase is discharged to the atmosphere. The liquid phase, consisting mainly of groundwater with diesel, is pumped to an oil-water separator. Floating product is skimmed off and transferred to two storage containers located in a lined area adjacent to the unit. The groundwater is then polished through two activated carbon vessels, and returned to the ground via the infiltration trench.
Between June 2004 and December 2008, over 4700 litres of diesel fuel have been successfully recovered from the groundwater through the system. Recovery rates have significantly dropped over the past year, however, and alternative remediation methods are now being considered to deal with the remaining PHCs in sub-surface soils.

For purposes of FCSAP, a federal brownfield is defined as an idle or underused property for which the Government of Canada has accepted all or partial responsibility for past environmental contamination, and that exhibits good potential for other uses (or upgrading) and/or provides viable social/economic opportunities. Brownfields are typically located in established areas, where existing municipal services are readily available, or along transportation corridors. In 2007-08, 22 projects identified the potential for one or more sites to be federal brownfields. Redevelopment plans, such as divestiture (4 project locations) or redevelopment by the federal government (2 project locations), were identified for 6 of the 22 projects.
The scope of FCSAP presents an opportunity for custodians to redevelop brownfields that are part of their real property portfolio. In 2005-06, PWGSC initiated the development of a brownfields classification tool to assist custodians in identifying candidate brownfield redevelopment sites. In 2006-07, PWGSC conducted several consultations with federal custodians and other levels of government in order to create a preliminary brownfields classification tool for the purposes of identifying, classifying, prioritizing and preparing brownfields sites, from the perspective of program planning and divestiture. In order to assist in the development of individual business cases, further refinement of this tool was scheduled for 2007-08. Trials of the tool were conducted using the PWGSC Real Property Inventory database and the TBS Directory of Federal Real Property. The Brownfields Portfolio Classification Tool has been refined in consultation with custodians, based on these initial trials.
In 2007-08, a total of $18,179,932 was approved for Secretariat and Expert Support Services. Of this amount, $14,995,312 was spent and $3,184,620 was lapsed. The expenditure breakdown is provided in Table 7.
| Secretariat and Expert Support Services | ||||
|---|---|---|---|---|
| Planned FCSAP Expenditures ($) |
Adjustment | Actual FCSAP Expenditures |
Variance ($) (approved + adjustment - expenditure) |
|
* Additional internal funds totalling approximately $780,000 were allocated by Health Canada to augment FCSAP Expert Support resources | ||||
| Environment Canada Secretariat/Expert Support | 6,640,276 | 4,067,566 | 2,572,710 | |
| Treasury Board of Canada Secretariat | 481,363 | 429,184 | 52,179 | |
| Health Canada Expert Support* | 6,772,656 | 7,502,223 | -779,567 | |
| Public Works and Government Services Canada | 1,000,000 | 780,810 | 219,190 | |
| Department of Fisheries and Oceans Expert Support | 3,335,637 | 2,215,529 | 1,120,108 | |
| Total Expenditures | 18,179,932 | 0 | 14,995,312 | 3,184,620 |
The main factor contributing to the variance (as identified by the expert support departments and the Secretariat) was the inability to staff the vacant positions funded by the Program. A lower than expected number of staff for expert support and the Secretariat functions created the inability to spend significant portions of operational funds.
In 2007-08, the FCSAP Secretariat undertook the following work:
In 2007-08, the Real Property and Materiel Policy Division of TBS undertook the following work related to FCSAP:
In 2007-08, much of the work of expert support departments focused on the development and delivery of guidance documents and training, the provision of advice, third-party review, and the promotion of innovative technologies:
Detailed information on the activities carried out by the four expert support departments (DFO, EC, HC and PWGSC) during the fiscal year can be obtained by contacting the specific expert support department directly:
Each year, financial information, including the overall environmental liability and contingent liability for federal contaminated sites, is reported to the Public Accounts of Canada. In the Public Accounts, total environmental liability includes the estimated costs for the management and remediation of contaminated sites and unexploded explosive ordnance-affected sites, as well as the estimated costs for decommissioning Atomic Energy of Canada Limited's nuclear facilities. For contaminated sites, a liability is accrued and an expense is recorded when the contamination occurs or when the Government becomes aware of the contamination and is obligated, or is likely obligated, to incur such costs. A contingent liability is recorded when the Government's obligation to incur these costs is unknown or unlikely, or if the amount cannot be reasonably estimated.19
The requirements for recording environmental liabilities can be found in the Treasury Board Policy on Accounting for Costs and Liabilities Related to Contaminated Sites (www.tbs-sct.gc.ca/pol/doc-eng.aspx?id=12152). Additional guidance is contained in the Treasury Board Guidance on Accounting for Environmental Liabilities (www.tbs-sct.gc.ca/rpm-gbi/doc/liabilities-passifs/liabilities-passifs-eng.aspx). As indicated in these documents, the environmental liability recorded for contaminated sites reflects the estimated cost of site remediation to a level appropriate to the land's current or intended federal use. Costs include any estimated expenses related to the remediation and management of federal sites associated with steps 5 to 10 of the Ten Step Process, for sites identified as a Class 1, Class 2 or, in limited cases, Class I (insufficient information) under the CCME classification. As noted in Guidance on Accounting for Environmental Liabilities, Class I sites may have a liability recorded when the federal custodian has sufficient information to determine that the Government is likely obligated to remediate the site but there are insufficient data to generate a classification under the CCME National Classification System. When a custodian intends to perform the remediation itself, the liability may include estimated project management costs. The liability amount excludes any expenses associated with determining the existence of contamination (i.e., steps 1 to 4 of the Ten Step Process), overhead costs, and project management costs internal to the custodian. This means that the costs associated with assessment (steps 1 to 4) and with care and maintenance activities are not included in the liability calculation, as they are undertaken to determine the existence and extent of contamination (assessment) or to mitigate the spread of contamination when the danger to human health or the environment is imminent (care and maintenance).
The 2007-08 Public Accounts show an increase in the accrued liability related to the management and remediation of federal contaminated sites. As of March 31, 2008, a liability of $3.332 billion was recorded for approximately 2360 contaminated sites, compared with a liability of $3.014 billion for 2630 sites in 2007.20 For a number of reasons, not all of the contaminated sites that are included in the Public Accounts' liability totals are eligible for, or have received, funding under FCSAP. Therefore, in order to obtain a more accurate picture of the impact that FCSAP has had on liability, exceptional sites such as the Sydney Tar Ponds and Port Hope Area Initiative are removed from the total. In addition, the liability amounts were excluded for federal custodians with contaminated sites that do not participate in FCSAP. As demonstrated in Table 8, once these amounts are removed from the total liability recorded in the Public Accounts for contaminated sites, there is a $306 million increase in liability during the period of March 31, 2007, to March 31, 2008. The majority (95%) of the net increase is attributed to an increase in the liability reported for three custodians-INAC, DND and DFO. This increase in federal environmental liability is primarily attributed to changes recorded to planned cost estimates for remediation activities of large projects. It is also attributed to the fact that increased spending on assessment activities results in a more accurate estimate of liability, often leading to an increase. Continued work on all types of FCSAP projects will result in further refinement of liability estimates, and total liability is expected to decline as sites are remediated.
March 31, 2007 ($) |
March 31, 2008 ($) |
|
|---|---|---|
Total contaminated sites liability21 |
6,061,913,899 |
6,668,721,493 |
Less: |
||
Unexploded explosive ordnance affected sites (Department of National Defence) |
119,143,584 |
327,757,635 |
Atomic Energy of Canada Limited's nuclear facility decommissioning |
2,927,934,000 |
3,008,236,000 |
Sydney Tar Ponds22 |
280,817,000 |
271,425,194 |
Port Hope Area Initiative23 |
387,173,243 |
335,373,318 |
Cape Breton Development Corporation24 |
108,857,000 |
180,338,000 |
VIA Rail Canada Inc. |
|
1,500,000 |
Industry Canada |
132,281 |
99,657 |
National Research Council of Canada |
300,000 |
100,000 |
Adjusted total contaminated sites liability |
2,237,556,791 |
2,543,891,689 |
The information in Table 9 shows liability for contaminated sites as reported in the 2007-08 Public Accounts.
Custodian |
Opening Liability |
Closing Liability |
Difference |
|---|---|---|---|
Agriculture and Agri-Food Canada |
1,779,574 |
1,925,334 |
145,760 |
Canada Border Services Agency |
867,400 |
769,165 |
(98,235) |
Correctional Service of Canada |
13,775,571 |
14,354,720 |
579,149 |
Environment Canada |
63,266,228 |
55,520,174 |
(7,746,054) |
Fisheries and Oceans Canada |
169,196,803 |
223,544,198 |
54,347,395 |
Health Canada |
3,197,100 |
2,303,800 |
(893,300) |
Indian and Northern Affairs Canada |
1,313,856,272 |
1,497,136,925 |
183,280,653 |
The Jacques Cartier and Champlain Bridges Inc. |
1,000,000 |
1,000,000 |
0 |
National Capital Commission |
21,794,000 |
24,799,000 |
3,005,000 |
Department of National Defence |
378,272,040 |
431,514,508 |
53,242,468 |
Natural Resources Canada24 |
387,792,662 |
336,678,572 |
(51,114,090) |
Parks Canada Agency |
40,027,640 |
42,017,836 |
1,990,196 |
Public Works and Government Services Canada25 |
320,154,947 |
310,523,035 |
(9,631,912) |
Royal Canadian Mounted Police |
3,752,007 |
4,275,715 |
523,708 |
Transport Canada |
186,814,790 |
204,327,220 |
17,512,430 |
Total |
2,905,547,034 |
3,150,690,202 |
245,143,168 |
In its third year of operation, FCSAP's key achievements included the development and enhancement of program policies and procedures, and further development of guidance material and training for federal custodians. Work was carried out to address the key program activity objectives of FCSAP, including reducing the number of high-risk sites, reducing human and ecological risks and financial liabilities, and increasing public confidence in the management of federal contaminated sites.
FCSAP spent $188.4 million on federal contaminated sites projects, program management, Secretariat/expert support services, and PWGSC accommodation costs, with the most significant proportion of the money allocated to the execution of assessment and remediation / risk management projects. Of the total amount budgeted for project expenditures ($217.7 million), $165.4 million was spent, representing an increase of approximately $2.5 million from the previous fiscal year. As a result of the amounts spent in 2007-08, activities were undertaken at 276 remediation / risk management projects (consisting of 519 sites) and 590 assessment projects (consisting of 2269 sites) across Canada.
As of March 31, 2008, a liability of $3.332 billion was recorded for approximately 2360 contaminated sites, compared with a liability of $3.014 billion for 2630 sites in 2007.26 This increase in federal environmental liability is primarily attributed to changes recorded to planned cost estimates for remediation activities of large projects. It is also attributed to the fact that increased spending on assessment activities results in a more accurate estimate of liability, often leading to an increase. Continued work on all types of FCSAP projects will result in further refinement of liability estimates, and total liability is expected to decline as sites are remediated.
Finally, in March 2008, the Office of the Auditor General of Canada (OAG) tabled a Status Report on the progress the federal government had made with respect to the management of federal contaminated sites. For this status report, the OAG assessed the progress that four departments - Fisheries and Oceans Canada, Indian and Northern Affairs Canada, National Defence, and Transport Canada - made in addressing select findings and recommendations from the 2002 Audit Report. These four departments were selected for examination because they are collectively responsible for approximately 89 percent of the contaminated sites under federal responsibility. The Report also assessed the actions of Environment Canada and the Treasury Board of Canada Secretariat in providing central leadership to deal with priority contaminated sites, and what the federal government did to determine and report the costs of dealing with these sites.
The OAG Status report concluded that the government has made satisfactory progress in managing its contaminated sites by initially allocating approximately $1.5 billion over five years as a first installment of its $3.5 billion budgetary announcement and by developing the FCSAP. The OAG found that the four audited departments are putting significant effort into managing their contaminated sites. They had remediated about 340 sites, and about 480 others were undergoing remediation. All four departments had developed management plans that include some time-bound commitments for dealing with their contaminated sites in order to meet the program's objective of reducing the risk they pose to human health and the environment.
To assist federal custodians in the evaluation of human health and environmental risks at federal contaminated sites, two key analytical tools were developed under the 2003-2005 Accelerated Action Plan and refined under FCSAP: (A) HC's Human Health Preliminary Quantitative Risk Assessment tool and (B) EC's Ecological Risk Evaluation framework.
The purpose of each tool is to define the level of risk posed by a contaminated site, based on the following three evaluation criteria and their relationship to contaminant movement between source and receptor (human or ecological):

(Description of the above image)
To create an accurate representation of the complex source-receptor pathway, multiple sources of information are required. As such, analytical factors can include, but are not limited to, any of the following considerations:
(A) Human Health Preliminary Quantitative Risk Assessment
In the preliminary quantitative risk assessment for a federal contaminated site, the following factors are considered:
Overall, Health Canada's Preliminary Quantitative Risk Assessment tool uses prescribed methods and assumptions, standard exposure pathways, human characteristics, and levels of toxicity in order to ensure that exposures and risk are not underestimated. When combined with site-specific information, the model helps in the assessment of toxicity and hazards associated with exposure to various chemicals.
For more details on the Preliminary Quantitative Risk Assessment, visit HC's website at http://hc-sc.gc.ca/ewh-semt/pubs/contamsite/index_e.html.
(B) Ecological Risk Evaluation
The Ecological Risk Evaluation framework was developed by EC as a tool to enable objective, transparent analysis of the ecological risks associated with individual federal contaminated sites.
More specifically, the framework assesses contaminated sites to determine the following:
Province/territory |
≤$250,000 |
>$250,000 to |
>$1,000,000 to |
>$10,000,000 |
Total |
|||||
|---|---|---|---|---|---|---|---|---|---|---|
Number of projects |
Number of sites |
Number of projects |
Number of sites |
Number of projects |
Number of sites |
Number of projects |
Number of sites |
Number of projects |
Number of sites |
|
Alberta |
2 |
2 |
- |
- |
2 |
2 |
1 |
6 |
5 |
10 |
British Columbia |
38 |
183 |
14 |
28 |
16 |
18 |
4 |
4 |
72 |
233 |
Manitoba |
5 |
5 |
3 |
3 |
7 |
7 |
- |
- |
15 |
15 |
New Brunswick |
7 |
7 |
1 |
1 |
1 |
1 |
- |
- |
9 |
9 |
Newfoundland and Labrador |
2 |
2 |
2 |
2 |
6 |
7 |
1 |
41 |
11 |
52 |
Nova Scotia |
21 |
24 |
3 |
6 |
5 |
6 |
- |
- |
29 |
36 |
Northwest Territories |
- |
- |
1 |
1 |
5 |
5 |
8 |
11 |
14 |
17 |
Nunavut |
2 |
4 |
2 |
3 |
4 |
4 |
20 |
20 |
28 |
31 |
Ontario |
14 |
17 |
4 |
6 |
9 |
23 |
1 |
2 |
28 |
48 |
Prince Edward Island |
7 |
7 |
- |
- |
- |
- |
- |
- |
7 |
7 |
Quebec |
30 |
38 |
12 |
26 |
3 |
6 |
1 |
1 |
46 |
71 |
Saskatchewan |
3 |
80 |
1 |
1 |
1 |
1 |
- |
- |
5 |
82 |
Yukon Territory |
2 |
2 |
- |
- |
1 |
1 |
4 |
4 |
7 |
7 |
Total |
133 |
371 |
43 |
77 |
60 |
81 |
40 |
89 |
276 |
618 |
Custodian |
≤ $250,000 |
>$250,000 to ≤$1,000,000 |
>$1,000,000 to ≤$10,000,000 |
>$10,000,000 |
Total |
|||||
|---|---|---|---|---|---|---|---|---|---|---|
Number of projects |
Number of sites |
Number of projects |
Number of sites |
Number of projects |
Number of sites |
Number of projects |
Number of sites |
Number of projects |
Number of sites |
|
Agriculture and Agri-Food Canada |
- |
- |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
Canada Border Services Agency |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
2 |
2 |
Correctional Service of Canada |
- |
0 |
- |
- |
1 |
1 |
- |
- |
1 |
1 |
Fisheries and Oceans Canada |
88 |
98 |
14 |
42 |
- |
- |
1 |
2 |
103 |
142 |
Environment Canada |
3 |
224 |
- |
- |
- |
- |
1 |
1 |
4 |
225 |
Health Canada |
4 |
4 |
- |
- |
3 |
3 |
- |
- |
7 |
7 |
Indian and Northern Affairs Canada (Indian and Inuit Affairs Business Line) |
|
|
|
|
|
|
|
|
|
|
IIABL |
9 |
9 |
8 |
8 |
14 |
28 |
- |
- |
31 |
45 |
NAO |
- |
- |
- |
- |
7 |
7 |
19 |
22 |
26 |
29 |
National Capital Commision |
1 |
1 |
- |
- |
1 |
1 |
- |
- |
2 |
2 |
Department of National Defence |
13 |
13 |
8 |
12 |
14 |
21 |
17 |
62 |
52 |
108 |
Parks Canada Agency |
6 |
8 |
2 |
2 |
1 |
1 |
- |
- |
9 |
11 |
Public Works and Government Services Canada |
3 |
5 |
3 |
5 |
9 |
9 |
- |
- |
15 |
19 |
Royal Canadian Mounted Police |
4 |
4 |
5 |
5 |
- |
- |
- |
- |
9 |
9 |
Transport Canada |
1 |
4 |
3 |
3 |
8 |
8 |
2 |
2 |
14 |
17 |
Total |
133 |
371 |
43 |
77 |
60 |
81 |
40 |
89 |
276 |
618 |
| Planned FCSAP Expenditures | Adjustments | Actual FCSAP Expenditures | |
|---|---|---|---|
| 1 Funding brought forward from previous fiscal years | |||
| 2 Funding brought forward from previous fiscal years. Total does not include $230,000 that was transferred to Parks Canada | |||
| 3 Funds received from the DFO Expert Support | |||
| 4 Custodian cost share owed to FCSAP from 2006-07 | |||
| 5 Total adjustments include $230,000 transferred from the INAC-IIABL | |||
| 6 $2,964,000 of remediation/risk management funds were returned to the fiscal framework | |||
| 7 Additional funds totalling approximately $780,000 were allocated by Health Canada to augment FCSAP Expert Support resourcces | |||
| Federal Contaminated Sites Projects | |||
| Indian and Northern Affairs Canada (INAC) | |||
| Northern Affairs Organizations | 97,657,635 | 3,133,3221 | 76,468,365 |
| Indian and Innuit Affairs Business Line | 12,531,245 | 1,216,2382 | 9,917,646 |
| Total INAC | 110,188,880 | 4,349,560 | 86,386,011 |
| Agriculture and Agri-Food Canada | 1,296,000 | 1,008,400 | |
| Canada Border Services Agency | 341,360 | 327,098 | |
| Correctional Service Canada | 180,000 | 910,0071 | 1,349 |
| Environment Canada | 9,340,559 | 3,331,006 | |
| Department of Fisheries and Oceans | 14,656,584 | 1,503,2601 | 7,697,967 |
| 712,2693 | |||
| Health Canada | 1,167,200 | 143,1664 | 578,585 |
| Jacques Cartier and Champlain Bridges Incorporated | 92,000 | 0 | |
| National Capital Commission | 800,800 | 8701 | 758,633 |
| Department of National Defence | 56,314,473 | 48,134,620 | |
| Natural Resources Canada | 128,000 | 47,8101 | 35,428 |
| Parks Agency Canada | 2,085,324 | 851,8735 | 2,347,896 |
| Public Works and Government Services Canada | 3,996,225 | 2,978,822 | |
| Royal Canadian Mounted Police | 5,033,600 | 2,932,734 | |
| Transport Canada | 12,068,948 | 2,964,0006 | 8,844,435 |
| -2,964,0006 | |||
| Total Project Expenditures | 217,689,953 | 8,518,815 | 165,362,984 |
| Program Management | |||
| Agriculture and Agri-Food Canada | 150,000 | 30,0001 | 120,000 |
| Correctional Service Canada | 67,670 | 67,670 | |
| Environment Canada | 467,958 | 467,958 | |
| Department of Fisheries and Oceans | 1,033,315 | 22,7313 | 894,046 |
| Health Canada | 121,429 | 121,429 | |
| Indian and Northern Affairs Canada (INAC) | |||
| Indian and Inuit Affairs Business Line | 735,035 | 735,035 | |
| Northern Affairs Organization | 2,213,980 | 2,293,652 | |
| Department of National Defence | 1,200,000 | 660,849 | |
| Natural Resources | 150,000 | 0 | |
| Parks Canada Agency | 366,713 | 418,4211 | 367,414 |
| Public Works and Government Services | 200,000 | 191,829 | |
| Royal Canadian Mounted Police | 395,500 | 340,434 | |
| Transport Canada | 451,000 | 451,000 | |
| Total Program Management Expenditures | 7,552,600 | 471,152 | 6,711,316 |
| Secretariat and Expert Support Services | |||
| Environment Canada (EC) | |||
| EC Secretariat | 3,465,995 | 1,855,534 | |
| EC Expert Support | 3,174,281 | 2,212,031 | |
| Total EC Secretariat/Expert Support | 6,640,276 | 4,067,566 | |
| Treasury Board of Canada Secretariat | 481,363 | 429,184 | |
| Health Canada Expert Support | 6,722,656 | 7,502,223 | |
| Public Works and Government Services | 1,000,000 | 780,810 | |
| Department of Fisheries and Oceans Expert Support | 3,335,637 | 2,215,529 | |
| Total Secretariat and Expert Support Expenditures | 18,179,932 | 0 | 14,995,312 |
| PWGSC Accommodation costs | 1,367,467 | 1,367,467 | |
| Total FCSAP Expenditures | 244,789,952 | 8,989,967 | 188,437,079 |
| Federal Contaminated Sites Projects | Planned FCSAP Funding | Adjustmentsa | Actual FCSAP Expenditures | FCSAP Variance(planned + adjustments - actual) | ||
|---|---|---|---|---|---|---|
| FCSAP Fund | Custodian Share | FCSAP Fund | Custodian Share | |||
| a Adjustments include the transfer of funds from the previous fiscal year, and FCSAP funds not requested | ||||||
| b FCSAP funds transferred from the previous fiscal year | ||||||
| c Total includes $882,086 of remediation/risk management funds transferred from the previous fiscal year | ||||||
| d FCSAP funds received from another Custodian | ||||||
| e Total includes $621,873 of remediation/risk management funds transferred from the previous fiscal year | ||||||
| Agriculture and Agri-Food Canada | ||||||
| ATL-1 Kentville Central Heating Plant (NS) | 500,000 | 100,000 | 562,503 | 140,626 | -62,503 | |
| Assessment (21 Projects) | 796,000 | 159,200 | 445,897 | 111,474 | 350,103 | |
| Total AAFC | 1,296,000 | 259,200 | 1,008,400 | 252,100 | 287,600 | |
| Canada Border Services Agency | ||||||
| Pleasant Camp Border Crossing (BC) | 181,360 | 36,272 | 181,360 | 45,912 | 0 | |
| West Poplar (SK) | 160,000 | 32,000 | 145,738 | 36,434 | 14,262 | |
| Assessment | 0 | 0 | 0 | |||
| Total CBSA | 341,360 | 68,272 | 327,098 | 82,346 | 14,262 | |
| Correctional Service Canada | ||||||
| Atlantic Fuel Spill Site, 231-C02 (NB) | 120,000 | 24,000 | 1,349 | 337 | 118,651 | |
| Bowden Fuel Depot Site 537-C02 (AB) | 60,000 | 12,000 | 0 | 0 | 60,000 | |
| Assessment | 0 | 0 | 27,921 b | 0 | 0 | 27,921 |
| Total CSC | 180,000 | 36,000 | 910,007 c | 1349 | 337 | 1,088,658 |
| Department of Fisheries and Oceans (DFO) | ||||||
| Active Pass (BC) | 8,595 | 1,719 | 6,542 | 1,635 | 2,053 | |
| Addenbroke Island (BC) | 8,595 | 1,719 | 6,542 | 1,635 | 2,053 | |
| Baccaro Point (NS) | 80,000 | 16,000 | 75,265 | 18,816 | 4,735 | |
| Ballenas Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Bear Point Small Craft Harbour (NS) | 11,200 | 2,240 | 16,025 | 4,006 | -4,825 | |
| Bear River (NS) | 80,000 | 16,000 | 47,057 | 11,764 | 32,943 | |
| Belleville Small Craft Harbour (ON) | 6,802,022 | 1,360,404 | 464,683 | 116,171 | 6,337,339 | |
| Berthier (QC) | 8,000 | 1,600 | 6,000 | 1,500 | 2,000 | |
| Betty Island (NS) | 0 | 0 | 12,000 | 3,000 | -12,000 | |
| Boat Bluff (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Bonilla Island Sector (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Camp Cove Small Craft Harbour (NS) | 40,000 | 8,000 | 92,864 | 23,216 | -52,864 | |
| Cap d'Espoir (QC) | 0 | 0 | 217,781 | 54,445 | -217,781 | |
| Cap Gaspé (QC) | 0 | 0 | 146,588 | 36,647 | -146,588 | |
| Cap Chat (QC) | 0 | 0 | 7,378 | 1,844 | -7,378 | |
| Cap de la Madeleine (QC) | 0 | 0 | 7,378 | 1,844 | -7,378 | |
| Cap-des-Rosiers (QC) | 0 | 0 | 55,404 | 13,851 | -55,404 | |
| Cap-Saint-Ignace, ancien amer (QC) | 64,000 | 12,800 | 2,672 | 668 | 61,328 | |
| Cape Beale (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Cape Bear (PE) | 0 | 0 | 10,400 | 2,610 | -10,400 | |
| Cape d'Or (NS) | 8,000 | 1,600 | 4,400 | 1,100 | 3,600 | |
| Cape Egmont (PE) | 8,000 | 1,600 | 18,431 | 4,608 | -10,431 | |
| Cape Mudge (BC) | 8,595 | 1,719 | 6,542 | 1,635 | 2,053 | |
| Cape Scott (BC) | 8,621 | 1,724 | 6,542 | 1,635 | 2,079 | |
| Cape St. Marys (NS) | 80,000 | 16,000 | 29,497 | 7,374 | 50,503 | |
| Caribou Ferry Small Craft Harbour (NS) | 11,600 | 2,320 | 0 | 0 | 11,600 | |
| Carmanah Point (BC) | 8,619 | 1,724 | 6,524 | 1,635 | 2,077 | |
| Cascades-Soulanges (QC) | 12,000 | 2,400 | 0 | 0 | 12,000 | |
| Caveau Point (NS) | 8,000 | 1,600 | 0 | 0 | 8,000 | |
| Chatham Point (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Chrome Island Range (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Cultus Lake Laboratory (BC) | 81,800 | 16,360 | 70,981 | 17,745 | 10,819 | |
| Discovery Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Dixon Point Light (NB) | 8,000 | 1,600 | 18,431 | 4,608 | -10,431 | |
| Drews Head (NB) | 0 | 0 | 12,634 | 3,159 | -12,634 | |
| Dryad Point (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Dublin Shore Small Craft Harbour (NS) | 6,800 | 1,360 | 9,795 | 2,449 | -2,995 | |
| East Point (PE) | 64,000 | 12,800 | 0 | 0 | 64,000 | |
| Egg Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Enrage Point (BC) | 8,000 | 1,600 | 0 | 0 | 8,000 | |
| Entrance Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Estevan Point (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Fox Harbour Loran C (NL) | 175,200 | 35,040 | 0 | 0 | 175,200 | |
| Gabarus (NS) | 80,000 | 16,000 | 44,297 | 11,074 | 35,703 | |
| Gillis Point (NS) | 80,000 | 16,000 | 53,097 | 13,274 | 26,903 | |
| Grand Bank Small Craft Harbour (NL) | 36,000 | 7,200 | 19,626 | 4,907 | 16,374 | |
| Green Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Howards Cove (PE) | 0 | 0 | 15,897 | 3,974 | -15,897 | |
| Île au Marteau (QC) | 0 | 0 | 4,240 | 1,060 | -4,240 | |
| Île aux Noix, ancien FP - 1 (QC) | 0 | 0 | 1,110 | 278 | -1,110 | |
| Île aux Noix, ancien FP - 2 (QC) | 0 | 0 | 1,110 | 278 | -1,110 | |
| Île Brion (QC) | 40,000 | 8,000 | 0 | 0 | 40,000 | |
| Île du Corossol (QC) | 32,000 | 6,400 | 12,185 | 3,046 | 19,815 | |
| Île Grosbois (ex-tour radar), ancien amer (QC) | 0 | 0 | 10,258 | 2,564 | -10,258 | |
| Île Sainte-Marie (QC) | 24,000 | 4,800 | 33,913 | 8,478 | -9,913 | |
| Institute of Ocean Sciences (and Victoria MCTS) (BC) | 81,799 | 16,360 | 147,952 | 36,988 | -66,153 | |
| Ivory Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Kenora base (ON) | 64,000 | 12,800 | 0 | 0 | 64,000 | |
| Killarney East (ON) | 25,600 | 5,120 | 24,635 | 6,159 | 965 | |
| Killarney Northwest (ON) | 28,000 | 5,600 | 52,188 | 13,047 | -24,188 | |
| Killarney West Entrance (ON) | 20,000 | 4,000 | 16,741 | 4,185 | 3,259 | |
| Knapp Point (ON) | 40,000 | 8,000 | 171,167 | 42,792 | -131,167 | |
| Lameque Small Craft Harbour (NB) | 64,000 | 12,800 | 25,654 | 6,413 | 38,346 | |
| Langara Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Lennard Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Longue Pointe (QC) | 8,000 | 1,600 | 11,396 | 2,849 | -3,396 | |
| Low Point (NS) | 40,000 | 8,000 | 59,497 | 14,874 | -19,497 | |
| Maughers Beach (NS) | 0 | 0 | 12,634 | 3,159 | -12,634 | |
| McInnes Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Melocheville (QC) | 12,000 | 2,400 | 3,640 | 910 | 8,360 | |
| Merry Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| New Aiyansh Office & Residences- Nass Camp (BC) | 166,400 | 33,280 | 5,641 | 1,410 | 160,759 | |
| Nine Mile Point (ON) | 126,400 | 25,280 | 21,592 | 5,398 | 104,808 | |
| Nootka Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| North Cape (PE) | 64,000 | 12,800 | 13,801 | 3,450 | 50,199 | |
| North Rustico Small Craft Harbour (PE) | 6800 | 1360 | 3,535 | 884 | 3,265 | |
| Pachena Point (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Pacific Biological Station Risk Management (BC) | 81,799 | 16,360 | 144,249 | 36,062 | -62,450 | |
| Partridge Island Light and DGPS Station (NB) | 80,000 | 16,000 | 512,634 | 3,159 | 67,366 | |
| Percé (QC) | 0 | 0 | 152,274 | 39,318 | -157,274 | |
| Pine Island (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Point Atkinson Lightstation Risk Management (BC) | 8,000 | 1,600 | 6,542 | 1,635 | 1,458 | |
| Point Escuminac (NB) | 0 | 0 | 18,431 | 4,608 | -18,431 | |
| Pointe au Baril Lightstation (ON) | 100,000 | 20,000 | 6,477 | 1,619 | 93,523 | |
| Pointe de l'Ouest (QC) | 240,000 | 48,000 | 65,870 | 16,467 | 174,130 | |
| Pointe Dowker (QC) | 12,000 | 2,400 | 5,510 | 1,377 | 6,490 | |
| Pointe du Débarquement, terrain pour héliport (QC) | 0 | 0 | 5,826 | 1,456 | -5,826 | |
| Pointe du Débarquement, terrain pour héliport - 2 (QC) | 0 | 0 | 5,826 | 1,456 | -5,826 | |
| Pointe Heath (QC) | 240,000 | 48,000 | 3,768 | 942 | 236,232 | |
| Pointe-Noire (QC) | 160,000 | 32,000 | 130,443 | 32,611 | 29,557 | |
| Port Bickerton (NS) | 80,000 | 16,000 | 16,049 | 4,012 | 63,951 | |
| Portlock Point (BC) | 8,618 | 1,724 | 6,542 | 1,635 | 2,076 | |
| Prim Point (NS) | 0 | 0 | 164,049 | 41,012 | -164,049 | |
| Prim Point (PEI) | 64,000 | 12,800 | 27,442 | 6,860 | 36,558 | |
| Prince Rupert - Seal Cove Risk Management (BC) | 81,802 | 16,360 | 164,298 | 41,075 | -82,496 | |
| Prince Rupert Marine Station - Sourdough Bay Risk Management (BC) | 81,802 | 16,360 | 149,383 | 37,346 | -67,581 | |
| Pulteney Point (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Quatsino (Kains Island) (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Richibucto Head (NB) | 0 | 0 | 5,874 | 1,469 | -5,874 | |
| Rocher aux Oiseaux (QC) | 40,000 | 8,000 | 43,283 | 10,821 | -3,283 | |
| Sainte-Angèle-de-Laval (QC) | 16,000 | 3,200 | 3,276 | 819 | 12,724 | |
| Sainte-Marthe-de-Gaspé (QC) | 0 | 0 | 7,378 | 1,844 | -7,378 | |
| Saturna Island Sector (BC) | 8,621 | 1,724 | 6,542 | 1,635 | 2,079 | |
| Scarlett Point (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Sea Island Hovercraft Base Risk Management (BC) | 81,800 | 16,360 | 170,924 | 42,731 | -89,124 | |
| Sheringham Point (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Souris East (NS) | 64,000 | 12,800 | 89,779 | 22,445 | -25,779 | |
| Swallowtail (NB) | 8,000 | 1,600 | 0 | 0 | 8,000 | |
| Terence Bay (NS) | 0 | 0 | 12,634 | 3,159 | -12,634 | |
| Trial Islands (BC) | 8,619 | 1,724 | 6,542 | 1,635 | 2,077 | |
| Victoria Base Risk Management (BC) | 57,798 | 11,560 | 35,604 | 8,901 | 22,194 | |
| West Vancouver Laboratory (BC) | 81,800 | 16,360 | 124,296 | 31,074 | -42,496 | |
| Wood Islands Light (PE) | 64,000 | 12,800 | 0 | 0 | 64,000 | |
| Assessment (71 projects) | 4,142,400 | 828,480 | 1,503,260 b | 3,819,994 | 954,998 | 2,537,935 |
| 712,269 c | ||||||
| Total DFO | 14,656,584 | 2,931,317 | 2,215,529 | 7,697,967 | 1,924,472 | 9,174,146 |
| Department of National Defence (DND) | ||||||
| 14 Wing Greenwood NSLZB (NS) | 540,000 | 108,000 | 808,053 | 202,013 | -268,053 | |
| 22 Wing Wood Hobby Club Site Remediation (ON) | 52,000 | 10,400 | 24,127 | 6,032 | 27,873 | |
| 5 Wing Goose Bay (NL) | 4,000,000 | 0 | 3,315,444 | 0 | 684,556 | |
| ADMIE OPSEE Remediation (BC) | 0 | 0 | 396,315 | 99,079 | -396,315 | |
| ADMMAT BAF-3 POL Storage Facility (NU) | 0 | 0 | 52,800 | 13,200 | -52,800 | |
| ADMMAT FOX B SRR SUMMIT (S-493) (NU) | 0 | 0 | 58,402 | 14,601 | -58,402 | |
| Ancienne SFC Moisie - site Admin (QC) | 420,000 | 84,000 | 252,009 | 63,002 | 167,991 | |
| Assainissement du site de l'ancien puit P-2 (QC) | 120,000 | 24,000 | 39,200 | 9,800 | 80,800 | |
| ASU London Highbury Complex (ON) | 80,000 | 16,000 | 28,981 | 7,245 | 51,019 | |
| ASU London Wolsley Barracks (ON) | 56,000 | 11,200 | 30,109 | 7,527 | 25,891 | |
| BFC Valcartier - Perchlorate - eau souterraine (QC) | 80,000 | 16,000 | 93,214 | 23,304 | -13,214 | |
| Cadet Camp Landfill (ON) | 0 | 0 | 42,917 | 10,729 | -42,917 | |
| CAM-1 Jenny Lind Island DEW Line (NU) | 3,136,000 | 627,200 | 2,473,850 | 618,463 | 662,150 | |
| CAM-2 Gladman Point DEW Line (NU) | 36,000 | 3,600 | 94,316 | 10,480 | -58,316 | |
| CAM-3 Shepherd Bay DEW Line (NU) | 3,284,936 | 525,590 | 4,605,906 | 917,315 | -1,320,970 | |
| CAM-4 Pelly Bay DEW Line (NU) | 810,000 | 81,000 | 503,530 | 55,948 | 306,470 | |
| CAM-5 Mackar Inlet DEW Line (NU) | 5,320,000 | 1,064,000 | 3,540,395 | 885,099 | 1,779,605 | |
| CFAD Bedford Dump Sites (CSites 801, 802, 803 & 820) Risk Mngmt (NS) | 50,400 | 10,080 | 76,581 | 19,145 | -26,181 | |
| CFAD Eastside Peninsula Area (CSite 7402) Remediation (NS) | 68,000 | 13,600 | 87,881 | 21,970 | -19,881 | |
| CFB Esquimalt DY-4 FMF Shops (BC) | 800,000 | 160,000 | 0 | 0 | 800,000 | |
| CFB Trenton FFTA - (ON) | 64,000 | 12,800 | 7,600 | 1,900 | 56,400 | |
| Colwood Aggregate (BC) | 1,600,000 | 320,000 | 2,895,982 | 723,996 | -1,295,982 | |
| DCD School CSite 909 Remediation (NS) | 200,000 | 40,000 | 167,002 | 41,751 | 32,998 | |
| DYE-M Cape Dyer DEW Line (NU) | 9,500,000 | 0 | 5,135,020 | 0 | 4,364,980 | |
| Former POL Storage Area, Naval Annex Dockyard (CSite 1107B) Risk (NS) | 50,800 | 10,160 | 24,617 | 6,154 | 26,183 | |
| FOX-2 Longstaff Bluff DEW Line - (NU) | 64,000 | 12,800 | 217,641 | 54,410 | -153,641 | |
| FOX-3 Dewar Lakes DEW Line (NU) | 200,000 | 40,000 | 354,677 | 88,669 | -154,677 | |
| FOX-5 Broughton Island DEW Line (NU) | 36,000 | 3,600 | 223,505 | 24,834 | -187,505 | |
| FOX-M Hall Beach DEW Line (NU) | 6,300,000 | 630,000 | 8,584,748 | 953,861 | -2,284,748 | |
| Marlant Bedford Rifle Range (NS) | 496,000 | 99,200 | 512,478 | 128,120 | -16,478 | |
| Marlant Former Firefighter Training Area Site 907, DCD School (NS) | 40,000 | 8,000 | 36,795 | 9,199 | 3,205 | |
| Marlant Great Village Former AST Remediation (NS) | 40,000 | 8,000 | 30,677 | 7,669 | 9,323 | |
| METC Nicolet Building 5 - (QC) | 112,000 | 22,400 | 79,686 | 19,922 | 32,314 | |
| METC Nicolet OP-6 - (QC) | 48,000 | 9,600 | 14,484 | 3,621 | 33,516 | |
| NAD 1 - Jr. NCM (BC) | 560,000 | 112,000 | 848,371 | 212,093 | -288,371 | |
| PCB Amended Paint Removal Project (NU) | 400,000 | 80,000 | 3,034 | 758 | 396,966 | |
| PIN-2 Cape Young DEW Line (NU) | 64,000 | 12,800 | 62,860 | 15,715 | 1,140 | |
| PIN-3 Lady Franklin Point DEW Line (NU) | 32,000 | 6,400 | 102,113 | 25,528 | -70,113 | |
| PIN-4 Byron Bay DEW Line (NU) | 3,776,000 | 755,200 | 1,979,982 | 494,995 | 1,796,018 | |
| RDDC Valcartier-Secteurs d'essais et Batiment 307 (QC) | 80,000 | 16,000 | 332,842 | 83,211 | -252,842 | |
| Remediation of PCB contaminated soil at BAF-3, Brevoot Island (NU) | 0 | 0 | 27,740 | 6,935 | -27,740 | |
| Restauration champ de tir 600 verges à St-Bruno (QC) | 80,000 | 16,000 | 167,012 | 41,753 | -87,012 | |
| Restauration du dépotoir à St-Bruno (QC) | 60,000 | 12,000 | 31,354 | 7,839 | 28,646 | |
| Saglek Sediments (NL) | 120,000 | 24,000 | 93,918 | 23,480 | 26,082 | |
| Shea Heights/Southside Tank Farm (NL) | 640,000 | 128,000 | 727,251 | 181,813 | -87,251 | |
| Shearwater (CSite 207) - Former USTs at Hangar 3 (NS) | 4,000 | 800 | 4,000 | 1,000 | 0 | |
| Shearwater (CSite 230)-Buidlings 31,31A,31B,32 (Mobile support) (NS) | 4,000 | 800 | 4,000 | 1,000 | 0 | |
| Shirley Road Dump/Landfill (NB) | 40,000 | 8,000 | 36,802 | 9,201 | 3,198 | |
| Suffield EPG (AB) | 800,000 | 160,000 | 328,356 | 82,089 | 471,644 | |
| Summerside Armoury (PE) | 40,000 | 8,000 | 45,260 | 11,315 | -5,260 | |
| Sydney Underground Storage Tank Removal (NS) | 400,000 | 80,000 | 118,521 | 29,630 | 281,479 | |
| TCE Contamination Valcartier (QC) | 4,700,000 | 0 | 2,915,968 | 0 | 1,784,032 | |
| YA 2 - Small Boat Float (BC) | 1,600,000 | 320,000 | 185,957 | 46,489 | 1,414,043 | |
| Assessments (43 projects) | 5,310,337 | 1,062,067 | 5,310,337 | 2,347,114 | 0 | |
| Total DND | 56,314,473 | 6,773,297 | 48,134,620 | 8,671,016 | 8,179,853 | |
| Environment Canada (EC) | ||||||
| Hydrometric Stations in BC (BC) | 74,400 | 14,880 | 81,876 | 20,468 | -7,476 | |
| Hydrometric Stations in QC (QC) | 100,000 | 20,000 | 0 | 0 | 100,000 | |
| Hydrometric Stations in SK 2007-08 (SK) | 144,400 | 28,880 | 62,708 | 15,677 | 81,692 | |
| Lansdowne House (EC) (0N) | 77,684 | 15,537 | 0 | 0 | 77,684 | |
| PEC (BC) | 4,786,600 | 574,392 | 2,523,305 | 429,908 | 2,263,295 | |
| Pointe-de-l'Est RNF (APEC) (QC) | 42,120 | 8,424 | 28,465 | 7,116 | 13,655 | |
| Projet de rehabilitation - Ile de la Providence (QC) | 91,941 | 18,388 | 0 | 0 | 91,941 | |
| Sable Island Upper Air Station (NS) | 47,064 | 9,413 | 0 | 0 | 47,064 | |
| Assessments (15) | 3,976,350 | 795,270 | 634,652 | 158,663 | 3,341,698 | |
| Total EC | 9,340,559 | 1,485,184 | 3,331,006 | 631,832 | 6,009,553 | |
| Health Canada (HC) | ||||||
| Kasabonika (ON) | 52,800 | 10,560 | 41,290 | 20,443 | 11,510 | |
| Lansdowne House (ON) | 52,800 | 10,560 | 0 | 0 | 52,800 | |
| Moose Factory Hospital (ON) | 320,000 | 64,000 | 144,000 | 31,833 | 176,000 | |
| Remediation of North Spirit Lake (former) Nursing Station (ON) | 104,000 | 20,800 | 0 | 0 | 104,000 | |
| Remediation of Norway House Hospital (MB) | 96,000 | 19,200 | 103,000 | 25,750 | -7,000 | |
| Remediation of Red Sucker Lake Nursing Station (MB) | 96,000 | 19,200 | 14,769 | 3,872 | 81,231 | |
| Remediation of Shamattawa Nursing Station (MB) | 80,000 | 16,000 | 52,676 | 13,169 | 27,324 | |
| Remediation of Summer Beaver Nursing Station (ON) | 96,000 | 19,200 | 10,350 | 16,983 | 85,650 | |
| Remediation of Wapekeka Nursing Station (ON) | 53,600 | 10,720 | 0 | 0 | 53,600 | |
| Weagamow Lake (ON) | 80,000 | 16,000 | 76,500 | 24,333 | 3,500 | |
| Assessment (10) | 136,000 | 27,200 | 136,000 | 262,381 | 0 | |
| Total HC | 1,167,200 | 233,440 | 143,166 b | 578,585 | 398,764 | 731,781 |
| Indian and Northern Affairs Canada - Indian and Inuit Affairs Business Line (INAC-IIABL) | ||||||
| 1550 Clifford Road (BC) | 0 | 0 | 113,000 | 28,250 | -113,000 | |
| Barrenlands Former DOT Site (MB) | 240,000 | 48,000 | 88,800 | 22,200 | 151,200 | |
| Barrenlands/Brochet Frontier School Tankfarm (MB) | 68,240 | 13,648 | 37,476 | 9,369 | 30,764 | |
| Big Grassy First Nation (ON) | 64,000 | 12,800 | 32,200 | 8,000 | 31,800 | |
| Bob Thomas and IR # 5 (BC) | 1,051,600 | 210,320 | 136,800 | 34,200 | 914,800 | |
| Burnt Church - Off old bridge road contaminated site remediation (NB) | 0 | 0 | 120,000 | 30,000 | -120,000 | |
| Former Beren's River Pumphouse Tankfarm (MB) | 372,960 | 74,592 | 198,880 | 49,720 | 174,080 | |
| Former God's Lake School Tankfarm (MB) | 221,840 | 44,368 | 250,560 | 62,640 | -28,720 | |
| Former Northlands School Tankfarm (MB) | 52,880 | 10,576 | 29,104 | 7,276 | 23,776 | |
| Former Red Sucker Lake School Tankfarm (MB) | 1,004,000 | 200,800 | 720,720 | 180,180 | 283,280 | |
| Former School Site "Manto Sipi Cree Nation" (MB) | 360,000 | 72,000 | 104,400 | 26,100 | 255,600 | |
| Gitwinksihlkw Front of Village Administration Office (BC) | 55,000 | 11,000 | 0 | 0 | 55,000 | |
| Gitxaala Nation Former Power House (BC) | 0 | 0 | 1,690,913 | 422,728 | -1,690,913 | |
| God's Lake Band Tankfarm (MB) | 221,840 | 44,368 | 250,560 | 62,640 | -28,720 | |
| Goodfish Drycleaning Plant Remediation (AB) | 0 | 0 | 48,954 | 12,239 | -48,954 | |
| Heiltsuk Community School (BC) | 80,634 | 16,127 | 0 | 0 | 80,634 | |
| Kahnawake - ancien dépotoir Beauvais (QC) | 10,400 | 2,080 | 6,031 | 1,508 | 4,369 | |
| Kahnawake - Ancien dépotoir Goodleaf (QC) | 10,400 | 2,080 | 6,031 | 1,508 | 4,369 | |
| Kahnawake - Ancien dépotoir Johnson's Point (QC) | 10,400 | 2,080 | 6,031 | 1,508 | 4,369 | |
| Kahnawake - Ancien dépotoir Khanata (QC) | 10,400 | 2,080 | 6,031 | 1,508 | 4,369 | |
| Kahnawake - Ancien dépotoir Morris (QC) | 10,400 | 2,080 | 6,031 | 1,508 | 4,369 | |
| Kahnawake - Ancien dépotoir Patton-Lawrence (QC) | 10,400 | 2,080 | 6,031 | 1,508 | 4,369 | |
| Kingfisher Lake Omahama Store (ON) | 50,240 | 10,048 | 50,240 | 12,560 | 0 | |
| Kwadacha Powerhouse (BC) | 318,200 | 63,640 | 43,191 | 10,798 | 275,009 | |
| Macoah I.R. 1 Generator Site Remediation (BC) | 179,136 | 35,827 | 285,341 | 71,335 | -106,205 | |
| Mathias Colomb Area 5B (MB) | 1,249,600 | 249,920 | 625,600 | 156,400 | 624,000 | |
| Mistawasis Bluestone Pit (SK) | 64,000 | 12,800 | 26,080 | 6,520 | 37,920 | |
| Nemaska - station service Cree Energy (QC) | 8,000 | 1,600 | 0 | 0 | 8,000 | |
| Obedjiwan - Poste de police (QC) | 48,000 | 9,600 | 0 | 0 | 48,000 | |
| Red Bridge Spur (BC) | 2,000 | 400 | 0 | 0 | 2,000 | |
| Remediation of Former Cutler Acid Site (ON) | 200,000 | 40,000 | 253,880 | 63,470 | -53,880 | |
| Sandy Lake Remediation Project (ON) | 960,000 | 192,000 | 833,380 | 208,320 | 126,620 | |
| Squamish Nation Kits Wye Site (BC) | 39,144 | 7,829 | 0 | 0 | 39,144 | |
| St. Theresa Point - Former School Tankfarm & Distribution Lines (MB) | 320,000 | 64,000 | 100,000 | 25,000 | 220,000 | |
| Tahltan First Nation- Dease Lake band maintenance yard (BC) | 174,023 | 34,805 | 0 | 0 | 174,023 | |
| Tsay Keh Dene generator station (BC) | 286,900 | 57,380 | 41,482 | 10,371 | 245,418 | |
| Unamen Shipu - Camp des travailleurs (QC) | 0 | 0 | 9,784 | 2,446 | -9,784 | |
| Wapekeka Soil Remediation Project (ON) | 1,469,600 | 293,920 | 1,480,000 | 370,000 | -10,400 | |
| Assessment (47) | 3,307,008 | 661,402 | 154,995 b | 2,310,115 | 567,679 | 921,888 |
| -230,000 c | ||||||
| Total INAC-IIABL | 12,531,245 | 2,506,249 | 1,216,238 d | 9,917,646 | 2,469,489 | 3,829,837 |
| Indian and Northern Affairs Canada - Northern Affairs Organization (INAC-NAO) | ||||||
| Axe Point (NT) | 2,944,000 | 588,800 | 1,481,313 | 370,328 | 1,462,687 | |
| BAR D - Atkinson Point (NT) | 7,935,512 | 1,428,392 | 3,843,779 | 960,945 | 4,091,733 | |
| Bear Island (NU) | 16,000 | 3,200 | 455,756 | 113,939 | -439,756 | |
| CAM D - Simpson Lake (NU) | 96,000 | 19,200 | 239,941 | 59,985 | -143,941 | |
| CAM F - Sarcpa Lake (NU) | 5,630,286 | 563,029 | 5,129,352 | 569,928 | 500,934 | |
| Cape Christian (NU) | 2,684,000 | 536,800 | 444,958 | 111,239 | 2,239,042 | |
| Clinton Creek Mine (YT) | 298,400 | 59,680 | 147,686 | 36,921 | 150,714 | |
| Colomac Mine (NT) | 9,170,534 | 0 | 11,730,181 | 0 | -2,559,647 | |
| Contact Lake (NT) | 619,200 | 123,840 | 601,759 | 150,440 | 17,441 | |
| Discovery Mine (NT) | 981,796 | 196,359 | 1,021,803 | 102,922 | -40,007 | |
| El Bonanza Mine (NT) | 669,200 | 133,840 | 477,633 | 119,408 | 191,567 | |
| Faro Mine (YT) | 14,620,000 | 0 | 15,537,999 | 0 | -917,999 | |
| FOX A - Bray Island (NU) | 120,000 | 24,000 | 9,959 | 2,490 | 110,041 | |
| FOX C - Ekalugad Fjord (NU) | 8,398,574 | 1,679,715 | 5,009,951 | 556,661 | 3,388,623 | |
| Giant Mine (NT) | 11,680,000 | 0 | 10,752,398 | 0 | 927,602 | |
| Indore Gold Mine-Beaverlodge Lake (NT) | 388,695 | 77,739 | 250,165 | 62,541 | 138,530 | |
| Johnson Pt (NT) | 956,000 | 191,200 | 382,897 | 95,724 | 573,103 | |
| Mount Nansen Mine (YT) | 1,476,000 | 295,200 | 1,062,005 | 265,501 | 413,995 | |
| North Inca Mine - Remediation (NT) | 446,695 | 89,339 | 282,006 | 70,501 | 164,689 | |
| Padloping Island (NU) | 296,000 | 59,200 | 0 | 0 | 296,000 | |
| PIN B - Clifton Point (NU) | 244,000 | 48,800 | 507,306 | 126,826 | -263,306 | |
| PIN E - Cape Peel (NU) | 16,000 | 3,200 | 0 | 0 | 16,000 | |
| Port Radium Mine (NT) | 7,110,328 | 853,239 | 4,012,197 | 179,523 | 3,098,131 | |
| Radio Island (NU) | 2,677,150 | 535,430 | 2,906,473 | 726,618 | -229,323 | |
| Roberts Bay Mine (NU) | 1,526,560 | 305,312 | 465,374 | 116,343 | 1,061,186 | |
| Silver Bear Mines (NT) | 3,444,800 | 688,960 | 1,072,576 | 268,144 | 2,372,224 | |
| Tundra-Taurcanis Mine (NT) | 8,959,500 | 1,791,900 | 4,700,244 | 522,249 | 4,259,256 | |
| United Keno Hill Mine (YT) | 3,132,405 | 313,241 | 3,043,848 | 338,205 | 88,557 | |
| Assessment (118) | 1,120,000 | 224,000 | 439,122 b | 898,806 | 224,706 | 660,316 |
| Total INAC-NAO | 97,657,635 | 10,833,615 | 3,133,322 c | 76,468,365 | 6,152,087 | 24,322,592 |
| National Capital Commission (NCC) | ||||||
| Bayview Remediation (ON) | 56,000 | 11,200 | 56,000 | 33,474 | 0 | |
| Ridge Road Landfill (ON) | 136,000 | 27,200 | 136,000 | 79,665 | 0 | |
| Assessment (23) | 608,800 | 121,760 | 870 b | 566,633 | 141,658 | 43,037 |
| Total NCC | 800,800 | 160,160 | 870 | 758,633 | 254,797 | 43,037 |
| Natural Resources Canada (NRCan) | ||||||
| Assessments (4) | 128,000 | 25,600 | 47,810 b | 35,428 | 8,857 | 140,382 |
| Total NRCan | 128,000 | 25,600 | 47,810 | 35,428 | 8,857 | 140,382 |
| Parks Canada Agency (PC) | ||||||
| Banff National Park Site Remediation (AB) | 14,400 | 2,880 | 14,400 | 51,100 | 0 | |
| Cape Breton Highlands NP (NS) | 296,451 | 59,290 | 613,854 | 153,463 | -317,403 | |
| Dégagement chenal (QC) | 0 | 0 | 0 | 0 | 0 | |
| Enlèvement haut fonds (QC) | -18,400 | -3,680 | 0 | 0 | -18,400 | |
| Glacier National Park (BC) | 13,200 | 2,640 | 19,900 | 5,600 | -6,700 | |
| Ingonish Compound Remediation (NS) | 184,000 | 36,800 | 0 | 0 | 184,000 | |
| Ivvavik NP, Sheep Creek Fuel Spill (YT) | 19,248 | 3,850 | 8,548 | 2,137 | 10,700 | |
| Lachine site 12.2 (QC) | 192,000 | 38,400 | 48,800 | 12,200 | 143,200 | |
| Quttinirpaaq NP - Tanquary Fiord (NU) | 142,032 | 28,406 | 130,675 | 32,669 | 11,357 | |
| Remediation of Gilman River, Quttinirpaaq National Park (NU) | 8,080 | 1,616 | 27,437 | 10,554 | -19,357 | |
| Riding Mountain NP, Maintenance Compound Garage, Former UST (MB) | 13,780 | 2,756 | 26,480 | 6,620 | -12,700 | |
| Waterton Lakes NP - Stalage Salt Storage remediation (AB) | 44,192 | 8,838 | 114,680 | 28,670 | -70,488 | |
| Assessment (34) | 1,176,341 | 235,268 | 230,000 d | 1,343,122 | 391,705 | 63,219 |
| Total PC | 2,085,324 | 417,065 | 851,873 e | 2,347,896 | 694,718 | 589,301 |
| Public Works and Government Services Canada (PWGSC) | ||||||
| 350 King Edward Monitoring Program (ON) | 40,000 | 8,000 | 39,605 | 9,901 | 395 | |
| Alaska Highway - Fireside Maintenance Camp R/RM (BC) | 186,160 | 37,232 | 129,360 | 32,340 | 56,800 | |
| Alaska Highway - Fort Nelson Gravel Pit R/RM (BC) | 31,200 | 6,240 | 36,560 | 9,140 | -5,360 | |
| Alaska Highway - Iron Creek Maintenance Camp (YT) | 140,514 | 28,103 | 102,116 | 25,529 | 38,398 | |
| Alaska Highway - Liard River Maintenance Camp R/RM (BC) | 622,960 | 124,592 | 743,009 | 185,752 | -120,049 | |
| Alaska Highway - Muncho Lake Maintenance Camp R/RM (BC) | 204,880 | 40,976 | 122,480 | 30,620 | 82,400 | |
| Alaska Highway - Sikanni Maintenance Camp R/RM (BC) | 101,140 | 20,228 | 73,940 | 18,485 | 27,200 | |
| Alaska Highway - Steamboat Maintenance Camp R/RM (BC) | 36,400 | 7,280 | 17,760 | 4,440 | 18,640 | |
| Alaska Highway - Toad Maintenance Camp - R/RM (BC) | 528,320 | 105,664 | 536,320 | 134,080 | -8,000 | |
| Campbell River Federal Building - Risk Management (BC) | 20,047 | 4,009 | 0 | 0 | 20,047 | |
| Décontamination des sols Beauceville (QC) | 680,000 | 136,000 | 26,247 | 6,561 | 653,753 | |
| Esquimalt Graving Dock Uplands - Risk Management (BC) | 14,000 | 2,800 | 6,954 | 1,738 | 7,046 | |
| Esquimalt Graving Dock Waterlot - Risk Management (BC) | 267,600 | 53,520 | 170,466 | 42,617 | 97,134 | |
| Former DND Radar Base Restoration (ON) | 0 | 0 | 0 | 50,335 | 0 | |
| Kelowna Federal Building - Risk Management (BC) | 6,400 | 1,280 | 0 | 0 | 6,400 | |
| Penhold Transmitter Bunker MPES (AB) | 137,840 | 27,568 | 105,702 | 26,425 | 32,138 | |
| Remedial Action at Moose Factory (ON) | 20,000 | 4,000 | 17,184 | 7,500 | 2,816 | |
| Assessment (11) | 958,764 | 191,753 | 851,119 | 350,940 | 107,645 | |
| Total PWGSC | 3,996,225 | 799,245 | 2,978,822 | 936,403 | 1,017,403 | |
| Royal Canadian Mounted Police (RCMP) | ||||||
| Coquitlam RCMP Gun Range (BC) | 176,000 | 35,200 | 345,994 | 86,498 | -169,994 | |
| Ft. Providence RCMP Remediation (NT) | 40,000 | 8,000 | 35,110 | 8,777 | 4,890 | |
| Haines Junction RCMP Garage (YT) | 72,000 | 14,400 | 52,569 | 13,142 | 19,431 | |
| Holman Detachment Remediation (NT) | 56,000 | 11,200 | 0 | 0 | 56,000 | |
| Hopedale RCMP Remediation (NL) | 48,000 | 9,600 | 65,906 | 16,477 | -17,906 | |
| Lac Megantic Remediation (QC) | 196,000 | 39,200 | 0 | 0 | 196,000 | |
| Nain RCMP Complex (NL) | 158,400 | 31,680 | 62,423 | 15,606 | 95,977 | |
| Nelson RCMP District Office (BC) | 132,000 | 26,400 | 68,934 | 17,233 | 63,066 | |
| Old Crow RCMP Detachment Compound (YT) | 88,800 | 17,760 | 0 | 0 | 88,800 | |
| Old Firing Range, RCMP Depot Training Academy (SK) | 940,000 | 188,000 | 139,015 | 34,753 | 800,985 | |
| Rigolet (Former Detachment Location) (NL) | 110,400 | 22,080 | 12,866 | 3,217 | 97,534 | |
| Winnipeg Air Services Hangar (MB) | 196,000 | 39,200 | 129,295 | 32,324 | 66,705 | |
| Assessment (188) | 2,820,000 | 564,000 | 2,020,622 | 519,515 | 799,378 | |
| Total RCMP | 5,033,600 | 1,006,720 | 2,932,734 | 747,542 | 2,100,866 | |
| Transport Canada (TC) | ||||||
| Bonnechere Airport remediation (ON) | 188,000 | 37,600 | 221,013 | 55,253 | -33,013 | |
| Bushell Public Port Facility Remediation (SK) | 3,333,920 | 666,784 | 2,985,241 | 746,310 | 348,679 | |
| Coal Harbour Public Port Facility Remediation (BC) | 16,560 | 3,312 | 16,000 | 4,000 | 560 | |
| Décontamination – Terrains excédentaires . Villlage de Kuujjuaq (QC) | 481,040 | 96,208 | 99,533 | 24,883 | 381,507 | |
| Former Remote Radar Site 59 (NL) | 240,000 | 48,000 | 102,367 | 25,592 | 137,633 | |
| Fort Nelson Airport Environmental Remediation (BC) | 2,804,050 | 560,810 | 2,456,623 | 614,156 | 347,427 | |
| Nitchequon (QC) | 397,920 | 79,584 | 254,981 | 63,745 | 142,939 | |
| Pickering Lands Site PIN 614462 Remediation (ON) | 567,504 | 113,501 | 589,918 | 147,480 | -22,414 | |
| Remediate Helicopter Site (NL) | 24,000 | 4,800 | 10,270 | 2,567 | 13,730 | |
| Remediate Marine Fire Training Area (NL) | 280,000 | 56,000 | 188,000 | 47,000 | 92,000 | |
| Remediate Soil and Groundwater at FTA (NL) | 325,440 | 65,088 | 6,148 | 1,537 | 319,292 | |
| Rock Bay (BC) | 1,476,000 | 147,600 | 1,341,938 | 149,104 | 134,062 | |
| Smithers Airport FFTA Remediation (BC) | 217,040 | 43,408 | 94,116 | 23,529 | 122,924 | |
| Watson Lake Remediation (YT) | 747,634 | 149,527 | 0 | 0 | 747,634 | |
| Williams Lake Airport FFTA Remediation (BC) | 449,840 | 89,968 | 367,287 | 91,822 | 82,553 | |
| Assessment (5 projects) | 520,000 | 104,000 | 111,000 | 103,000 | 409,000 | |
| Total TC | 12,068,948 | 2,266,190 | 0 b | 8,844,435 | 2,099,978 | 3,224,513 |
| Jacques Cartier and Champlain Bridges Incorporated (JCCBI) | ||||||
| Projet pilote Parcelle 3 (QC) | 92,000 | 18,400 | 0 | 0 | 92,000 | |
| Total JCCBI | 92,000 | 18,400 | 0 | 0 | 92,000 | |
| Total for remediation/risk management | 192,689,953 | 24,819,953 | 5,632,568 | 146,879,259 | 19,182,048 | 51,443,262 |
| Total for assessment | 25,000,000 | 5,000,000 | 2,886,247 | 18,483,725 | 6,142,690 | 9,402,522 |
| GRAND TOTAL | 217,689,953 | 29,819,953 | 8,518,815 | 165,362,984 | 25,324,738 | 60,845,784 |
[1] Taking Action on Federal Contaminated Sites: An Environmental and Economic Priority (Environment Canada, July 2005), p. ii.
[2] Public Accounts of Canada 2008, Volume I (PWGSC, 2008), S. 5, p. 5.12.
[3] Taking Action on Federal Contaminated Sites: An Environmental and Economic Priority (EC, July 2005), p. ii
[4] The CCME provides the principal forum among governments in Canada for the joint development of environmental policies and technical guidance for environmental management. The National Classification System for Contaminated Sites is a screening tool for the evaluation of contaminated sites according to their current or potential adverse impacts on human health and the environment. Sites are classified as:
The National Classification System for Contaminated Sites was updated and a new version was released in 2008. Custodians may also seek remediation / risk management funding for sites classified as Class 1 or 2 using the Federal Contaminated Sites Action Plan Classification System (2005).
[5] Care and maintenance activities are initiated in exceptional circumstances to prevent severe environmental damage or catastrophes from occurring before a site assessment can be completed and/or an action plan can be developed. Short-term activities are undertaken to reduce or prevent the spread of contamination in order to avoid an imminent environmental disaster that would harm human and/or wildlife populations. In past years, care and maintenance have been implemented at several abandoned/idled mines or other large properties with extensive contamination.
[6] In 2007-08, six projects received 100% FCSAP funding: Giant Mine, Faro Mine, Colomac Mine, 5 Wing Goose Bay, TCE Valcartier and DYE-M Cape Dyer DEW Line. Six projects received 90% FCSAP funding: FOX-M Hall Beach DEW Line, United Keno Hill Mine, Rock Bay, CAM-F Sarcpa Lake, FOX-C Ekalugad Fjord, and CAM-2 Gladman Point. Four projects received between 82.5% and 84.9% FCSAP funding: Port Radium Mine (83.8%), CAM-3 Shepherd Bay (84.9%), Tundra-Taurcanis Mine (84.5%) and PEC (82.5%).
[7] The allocated amount presented does not include the FCSAP funds of approximately $8.5M carried forward from 2006-07. Actual available funding for 2007-08 would therefore be $226M.
[8] The actual amount of assessment expenditures by province/territory was not reported in 2007-08. Instead, the national distribution of fuds was estimated using a proportion of each department's reported expenditures and the number of sites that the department worked on in each province/territory. Confirmed assessment expenditures by province/territory are expected to be included within reporting in future years of the Program.
[9] Actual total assessment expenditure reported for 2007-08.
[10] $2,886,247 = Five custodians transferred FCSAP funds from fiscal year 2006-2007 to 2007-2008 in the amount of $47,810 (Natural Resources Canada [NRCan]), $594,117 (Indian and Northern Affairs Canada [INAC] : $154,995 (INAC-IIABL) and $439,122 (INAC-NAO)), $1,503,260 (DFO), $27,921 (Correctional Service of Canada [CSC]), $870 (National Capital Commission [NCC]). One custodian received funds from DFO Expert Support in the amount of $712,269 (DFO).
[11]Ten custodians transferred FCSAP funds from fiscal year 2007-2008 to 2008-2009, in the amount of $1,843,320 (INAC : $660,316 (INAC-NAO) and $1,183,004 (INAC-IIABL)), $790,465 (RCMP), $2,537,935 (DFO), $63,219 (Parks Canada Agency [PC]), $128,000 (NRCan), $1,532,145 (EC), $43,037 (NCC), $27,921 (CSC), $287,600 (AAFC) and $409,000 (TC).
[12] The streamlined process refers to the provision of an NCS or FCSAP score for projects with a total estimated project cost of $50,000 while the regular process refers to the provision of an NCS or FCSAP score as well as the completion of an ecological risk evaluation and a preliminary quantitative risk assessment for the project. Refer to Appendix 1 for details on these processes.
[13] Atlantic Canada includes: New Brunswick, Nova Scotia, Prince Edward Island, and Newfoundland and Labrador.
[14] Four custodians transferred FCSAP funds from fiscal year 2006-2007 to 2007-2008, in the amount of $143,166 (HC), $3,985,443 (INAC : $2,694,200 (NAO) and $1,291,243 (IIABL)), $882,086 (CSC), and $621,873 (PC). In 2006-07 two custodians had identified that they were transferring funds to 2008-09. Of these funds, TC reported that they returned $2,964,000 to the fiscal framework and transferred $5,710,000 originally allocated in 2006-07 to fiscal year 2008-09. This includes assessment funding in the amount of $459,457 that was transferred to 2007-08 with the intention of being spent on remediation / risk management projects. DFO transferred $3,360,000 originally allocated in 2006-07 to fiscal year 2008-09.
[15] Eight custodians transferred FCSAP funds from fiscal year 2007-2008 to 2008-2009, in the amount of $2,532,000 (TC), $19,748,371 (INAC : $17,258,825 (NAO) and $2,489,546 (IIABL)), $526,082 (PC), $6,636,211 (DFO), $1,060,737 (CSC), $731,781 (HC), $1,251,751 (RCMP), and $2,667,855 (EC).
[16] A small percentage of these remediation / risk management projects are found in early steps of the 10-step for a few reasons: unexpected contamination and/or addition of new sites to a project may require stepping back from remediation activities and conduct additional assessment activities at those sites.
[17] Activities under step 8 can be categorized as active, being risk-reducing activities (Steps 8 B (removal of contaminated media off-site) / 8 C (treatment of contaminated media) / 8 D (containment or other risk reduction activities)) and planning activities (Step 8 A). As an example, activity under Step 8 A could include technology evaluation or contractor selection.
[18] The existing definition was intended to ensure that all possible treatment technologies applied to FCSAP sites were identified. However, this initial definition is under review, and, based on consultations within the federal contaminated sites community, it is expected that the term "innovative technology" will be revised in future years of FCSAP. Thus, the annual statistical analysis of innovative technology uptake will not be directly comparable year over year until this definition is finalized.
[19] Public Accounts of Canada 2008, Volume I (PWGSC, 2008), S. 2, pp. 2.10-2.11.
[20] Ibid., S. 5, p. 5.12.
[21] Public Accounts of Canada 2008, Volume I (PWGSC, 2008), S. 5, p. 5.12.
[22] Public Works and Government Services Canada Departmental Performance Report 2007-2008 (PWGSC, 2008), S. IV, Notes to the Consolidated Financial Statements (Unaudited).
[23] Natural Resources Canada 2008-2011 Contaminated Sites Management Plan.
[24] Includes the environmental liability for Port Hope Area Initiative (shared responsibility site which is managed outside of FCSAP).
[25] Includes the environmental liability for Sydney Tar Ponds.
[26] Public Accounts of Canada 2008, Volume I (PWGSC, 2008), S. 5, p. 5.12.
[27] National Classification System for Contaminated Sites, CCME, March 1992.