Federal Contaminated Sites
Symbol of the Government of Canada

Institutional links


Federal Contaminated Sites Action Plan
Annual Report
2007-08

January 21, 2010

Executive Summary

The Federal Contaminated Sites Action Plan (FCSAP) is a collaborative effort by federal departments, agencies, and consolidated Crown corporations ("custodians") to identify, assess and prioritize the remediation or risk management of federal contaminated sites based on the level of risk posed to human health and the environment.

Originally developed in response to the 2004 federal budget commitment of $3.5 billion in multi-year funding, the FCSAP is a 15-year cost-shared program that provides a mechanism to accelerate the remediation or risk management of priority federal contaminated sites. The FCSAP expands on the previous Federal Contaminated Sites Accelerated Action Plan (FCSAAP) (which ran during 2003-04 and 2004-05), prior to which the majority of departments and agencies collectively reallocated up to $100 million per year1 from other priorities to risk-manage and/or remediate their federal contaminated sites.

In its third year of operation (2007-08), expenditures were reported nationally by 15 custodians for 276 remediation / risk management projects (consisting of 519 sites where activity was undertaken) and 590 assessment projects (consisting of 2269 sites where activity was undertaken). These projects included the cleanup of sites where the environmental consequences of past practices were not fully understood, including such sites as: harbours and ports, military bases, former Distant Early Warning (DEW) line sites, light stations, and abandoned mines.

FY 2007-08 at a glance:

$188.4 million in total FCSAP expenditures, including federal contaminated sites projects, program management, secretariat/expert support services, and PWGSC accommodation costs

$146.9 million in FCSAP funds spent on remediation/risk management projects

$19.2 million in federal custodian funds spent on remediation/risk management projects funded under FCSAP

$18.5 million in FCSAP funds spent on assessment projects

$6.1 million in custodian funds spent on assessment projects

276 priority remediation/risk management projects funded

2269 assessment sites funded (on 590 projects)

In 2007-08, $188.4 million of FCSAP funds were spent on federal contaminated sites projects, program management, secretariat/expert support services, and Public Works and Government Services Canada (PWGSC) accommodation costs. In addition to the FCSAP funds, and in adherence to the Government of Canada's "polluter pays" principle, custodians contributed $25.3 million in cost-share. Of the total amount spent ($213.7 million), the greatest proportion of the funds ($190.7 million) went towards the actual assessment and remediation / risk management of federal contaminated sites.

As of March 31, 2008, a liability of $3.332 billion was recorded for approximately 2360 contaminated sites, compared with a liability of $3.014 billion for 2630 sites in 20072. This increase in federal environmental liability is primarily attributed to changes recorded to planned cost estimates for remediation activities of large projects. It is also attributed to the fact that increased spending on assessment activities results in a more accurate estimate of liability, often leading to an increase. Continued work on all types of FCSAP projects will result in further refinement of liability estimates, and total liability is expected to decline as sites are remediated. If you have questions or comments on this report, or wish to obtain additional copies of this report, please contact:

FCSAP Secretariat
Contaminated Sites Division
Environmental Protection Operations Directorate
Environment Canada
351 St. Joseph Boulevard, 15th Floor
Gatineau QC K1A 0H3
Tel: 819-934-2155 / Fax: 819-994-0502
Email: fcsap.pascf@ec.gc.ca

Table of Contents

1.0 Introduction

The Federal Contaminated Sites Action Plan (FCSAP) is a collaborative effort by federal departments, agencies, and consolidated Crown corporations ("custodians") to identify, assess and prioritize the management of federal contaminated sites based on the level of risk they pose to human health and the environment. The Program has a number of key objectives:

  1. to remediate and/or manage the risk associated with federal contaminated sites classified as requiring action or likely to require action under the National Classification System or an accepted alternative classification system (i.e., Class 1 and 2);
  2. to reduce federal financial liability or, in the case of care and maintenance sites, prevent increases in federal financial liability related to known federal contaminated sites;
  3. to reduce human health and ecological risks at the highest risk federal sites; and
  4. to increase public confidence in the overall management of federal contaminated sites and in the remediation / risk management of individual federal contaminated sites.

Contaminated Site

A site at which substances occur at concentrations (1) above background levels (background is defined as an area not influenced by chemicals released from the site under evaluation) and posing or likely to pose an immediate or long-term hazard to human health or the environment, or (2) exceeding levels specified in policies and regulations.

From A Federal Approach to Contaminated Sites, developed by the Contaminated Sites Management Working Group, November 1999

The FCSAP was established as a 15-year cost-shared program, developed in response to the 2004 federal budget commitment of $3.5 billion in multi-year funding for priority federal contaminated sites.

The number of custodians that participate in FCSAP varies annually, as do the number and type of projects that receive funding under FCSAP. In the fiscal year 2007-08, 15 custodians received funding through FCSAP. Projects included sites where the environmental consequences of past practices were not fully understood, including such sites as: harbours and ports, military bases, former DEW line sites, light stations, and abandoned mines.

The FCSAP builds on the previous two-year Federal Contaminated Sites Accelerated Action Plan (FCSAAP), which was in place from fiscal year 2003-2004 to fiscal year 2004-2005. Before FCSAAP, the majority of departments and agencies collectively reallocated up to $100 million per year3 from other priorities in order to remediate or to manage the risks associated with their contaminated sites. The majority of the spending was concentrated in a small number of departments that were responsible for the highest proportion of federal contaminated sites.

1.1 Program Structure

Environment Canada (EC) and the Treasury Board Secretariat (TBS) jointly administer FCSAP. Within EC, the FCSAP Secretariat provides program oversight and administers the non-financial aspects of the program. EC manages the project selection process, maintains a secure website, develops communication materials, and monitors and reports on progress. TBS ensures the Program's adherence to Treasury Board (TB) policies on the management of federal real property, reviews the financial aspects of proposals, assesses custodians' reallocation capacity, administers the fund, and advises the FCSAP Secretariat on the monitoring of Government-wide progress.

The FCSAP helps custodians address priority contaminated sites where the nature and mobility of contaminants represent the highest risk to human health and the environment. The responsibility and accountability for managing contaminated sites rests with custodians. Custodians are the project champions and are responsible for program delivery: identifying and prioritizing sites of concern; conducting risk assessments; developing remediation / risk management plans and project funding proposals consistent with their contaminated sites management plans; implementing approved projects; and achieving the contaminated sites management objectives set out in the contaminated sites management plans and project proposals. Custodians are also expected to incorporate linkages with other government of Canada initiatives such as Aboriginal training and employment, innovative technology usage, and federal brownfields, where possible.

EC, Health Canada (HC), Fisheries and Oceans Canada (DFO), and Public Works and Government Services Canada (PWGSC) are FCSAP expert support departments. The role of the expert support departments is to assist the Secretariat with development and promotion of best practices, and to ensure that custodians adopt a consistent approach to the assessment to human health and ecological risk across the program. EC, HC and DFO also:

  • provide project/site-specific advice and training to custodians;
  • assist in communicating the rules and policies of the Program to custodians;
  • assist in the development of standardized approaches, tools and guidance materials, and in the understanding and management of health and ecological issues;
  • provide expert review of risk assessments and risk scoring of sites;
  • provide liaison with provincial and territorial counterparts;
  • lead and co-ordinate Interdepartmental Regional Working Groups;
  • advise on risk management and risk communication strategies;
  • assist with the development of communication strategies and public outreach activities; and
  • offer expert knowledge related to federal environmental laws (e.g., Canadian Environmental Protection Act, 1999, Fisheries Act, Species at Risk Act, Canadian Environmental Assessment Act).

EC, HC, and DFO also carry out their mandates related to regulatory compliance. EC and HC focus on improving and promoting environmental and health risk assessments as a key part of the project selection process, while DFO ensures that site remediation or risk management activities do not further compromise any fish or fish habitat resources.

PWGSC provides project management tools and related training, and acts as the lead department for liaison with industry. PWGSC also works closely with Industry Canada (IC), which supports the Program by working to optimize the participation of the Canadian environmental industry in the remediation of federal contaminated sites, and to facilitate the introduction and use of innovative remediation technologies at these sites. PWGSC is responsible for disseminating information on innovative technologies so that custodian departments, other levels of government, and industry can benefit from technological advances and strategies.

In addition, three interdepartmental groups provide strategic direction:

  1. Federal Contaminated Sites Steering Committee. This steering committee is an interdepartmental group at the Assistant Deputy Minister (ADM) level. It oversees the implementation of FCSAP. The committee is co-chaired by EC and TBS, and comprises representatives from all federal custodians with responsibility for contaminated sites and from expert support departments as well as other departments, agencies, and consolidated Crown corporations with an interest in the Program. The steering committee recommends strategic direction, approves the work plans of the Secretariat and the expert support departments, guides the development of the strategic plan, approves funding options, and ratifies funding recommendations. The steering committee oversees program implementation and is responsible for setting project priorities, monitoring progress, and providing recommendations on the funding of sites under FCSAP.
  2. Contaminated Sites Management Working Group (CSMWG). The CSMWG is a working-level committee comprising representatives from expert support departments and federal custodians with contaminated sites. The CSMWG contributes to the development of procedures, tools, guidance, and program funding plans, and makes recommendations to the Steering Committee. The CSMWG also establishes sub committees and working groups to provide support to departments on opportunities related to linkages to other socio-economic outcomes such as skills development, training and employment of Canadians, and technological development in the environment industry.
  3. Interdepartmental Regional Working Groups. The Interdepartmental Regional Working Groups are in place in regions to advise custodians on the management of contaminated sites. The Groups provide custodians with training and access to the advice of expert support departments on compliance, health and ecological risks/impacts of contaminated sites and risk-assessment approaches, as well as advice on the development of remediation / risk management plans for their sites, with priority given to those projects funded under FCSAP.

1.2 Program Administration

FCSAP was developed in 2005 as a comprehensive 15-year program intended to support custodians in reducing risks to human health and the environment and decreasing federal financial liabilities associated with priority federal contaminated sites. Although any site that has been identified as potentially contaminated based on past (prior to July 1, 2002) activities on or near the site is entitled to assessment funding, only those sites classified as Class 1 or 2 under the Canadian Council of Ministers of the Environment (CCME) National Classification System4 are eligible for remediation / risk management funding. It is expected that the existing list of Class 1 and Class 2 priority sites that will seek funding under FCSAP will change in future years as remediation / risk management projects progress, newly assessed sites are considered, and remediation / risk management plans are fine-tuned.

In recognition of the "polluter pays" principle underlying the program, FCSAP operates on a cost-shared basis with custodians. To assist custodians in classifying their contaminated sites, assessment funding is available through FCSAP at an 80/20 (FCSAP/custodian) cost-share, up to a program maximum of $25 million per year. For remediation / risk management projects with total estimated project costs of $10 million or less, the cost-share is also 80/20 (FCSAP/custodian). Once estimated project costs for remediation / risk management projects exceed $10 million, the custodian's share is reduced to 10% on the amount exceeding $10 million. Certain exceptionally large projects with total costs in excess of $90 million may be eligible for full funding of project costs.

In order to give custodians the flexibility to better manage their contaminated sites programs, FCSAP allows custodians to internally reallocate FCSAP funds in-year among projects. In so doing, FCSAP is providing custodians with the flexibility to respond to unforeseen circumstances within a given fiscal year, while continuing to make progress and meet the requirements of the Program.

1.3 Program Resources

In 2007-08, funding was approved for assessment and remediation / risk management projects, program management activities, and program support activities for expert support departments, the FCSAP Secretariat, and TBS. Of the $280 million that was available in the fiscal framework to be allocated to remediation / risk management and assessment projects in 2007-08, $217.7 million was allocated to the custodian departments, with no more than $25 million of this amount to be used to conduct assessment projects. Actual FCSAP project expenditures for 2007-08 totalled $165.4 million-approximately $52 million less than was requested. Available FCSAP funding for 2007-08 included the funds allocated ($217.7 million) and the annual in-year adjustments (including funds carried forward from 2006-07) of $8.5 million, giving a total of $226 million. Hence, the total variance between available funding and spent funds was $61 million.

In addition to federal contaminated sites expenditures, program management funds were spent by custodians on salaries to support the implementation of the custodian's contaminated sites management program through FCSAP, and to fund various operational costs related to program planning, implementation and reporting (i.e. travel, training, etc.).

In 2007-08, $8,023,752 of program management funding was available to 12 custodians. Of the total amount available, $471,152 was transferred from previous fiscal years and $7,552,600 was approved in Treasury Board submissions. Overall, $6,711,316 was spent.

The breakdown of program management expenditures and variance for 2007-08 is outlined in Table 1.

Table 1: Summary of FCSAP Program Management Expenditures by Custodian (2007-08)
  Program Management
Planned
FCSAP
Expenditures
($)
Adjustments
($)
Actual
FCSAP
Expenditures
($)
Variance
($)
(approved +
adjustment -
expenditure)
1 Funding brought forward from the previous fiscal year
2 Funds received from the FCSAP Secretariat or Expert Support
Agriculture and Agri-Food Canada 150,000 30,0001 120,000 60,000
Correctional Service Canada 67,670   67,670 0
Environment Canada 467,958   467,958 0
Fisheries and Oceans Canada 1,033,315 22,7312 894,046 162,000
Health Canada 121 429   121 429 0
Indian and Northern Affairs Canada        
  Indian and Inuit Affairs Business Line 735,035   735,035 0
  Northern Affairs Organizations 2,213,980   2,293,652 -79,672
Department of National Defense 150,000   0 150,000
National Resources Canada 150,000   0 150,000
Parks Canada Agency 366,713 418,4211 367,414 417,720
Public Works and Government Services Canada 200,000   191,829 8,171
Royal Canadian Mounted Police 395,500   340,434 55,066
Transport Canada 451,000   451,000 0
Total Expenditures 7,552,600 471,152 6,711,316 1,312,436

1.4 Project Types

FCSAP funded two types of projects in 2007-08: assessment and remediation / risk management. In the past, there were also several care and maintenance projects funded under FCSAP5 , however, given that the majority of activities on these previously-identified care and maintenance projects are now remediation activities, these projects have been converted to remediation / risk management projects. Some remediation / risk management projects may still have one or more care and maintenance activities.

Assessment Projects - Funding assessment work is an important part of FCSAP. By assessing sites suspected of being contaminated, the federal government is able to more accurately estimate human health and environmental risk, and the level of financial liability for historically contaminated federal sites.

A full-scale assessment of the severity of contamination at a site can be a lengthy and complex process (see steps 1 to 6 in the Ten Step Process in section 2.0). An FCSAP assessment project is considered completed once all sites within the project have a status of either "Assessment Completed: Requires no Further Action" or "Assessment Completed: Requires Remediation / Risk Management."

Following assessment, many sites are determined not to pose a risk to human health and/or the environment-these sites are considered closed.

Remediation / Risk Management Projects - After a site is assessed and the need for contamination to be addressed is confirmed, a remediation / risk management plan is used to explore the various alternatives and to identify the preferred option to reduce the risk to human health and the environment. The remediation / risk management method that is chosen is designed to address the unique conditions of the site. Common remediation activities involve reducing exposure to contaminants by removing, destroying or containing them.

Under FCSAP, a site is considered completed once Step 9 (confirmatory sampling and final reporting) has been finished following site remediation, or once Step 10 (long-term monitoring) is finished at risk managed sites. A completed site is not eligible for FCSAP funds in the future unless it is reactivated by the custodian based on the discovery of new information.

An FCSAP remediation / risk management project is considered completed once all sites within the project have been completed.

2.0 2007-08 Program Achievements: FCSAP Projects

Federal Approach for Addressing Contaminated Sites-Ten Step Process

Step 1 - Identify Suspect Sites: Identify potentially contaminated sites based on activities (past or current) on or near the site.

Step 2 - Historical Review: Assemble and review all historical information pertaining to the site.

Step 3 - Initial Testing Program: Provide a preliminary characterization of contamination and site conditions.

Step 4 - Classify Contaminated Site using the CCME National Classification System: Prioritize the site for future investigations and/or remediation / risk management actions.

Step 5 - Detailed Testing Program: Focus on specific areas of concern identified in Step 3 and provide further in-depth investigations and analysis.

Step 6 - Reclassify the Site using CCME National Classification System: Update the ranking based on the results of the detailed investigations.

Step 7 - Develop Remediation / Risk Management Strategy: Develop a site-specific plan to address contamination issues.

Step 8 - Implement Remediation / Risk Management Strategy: Implement the site-specific plan that addresses contamination issues.

Step 9 - Confirmatory Sampling and Final Reporting: Verify and document the success of the remediation/risk management strategy.

Step 10 - Long-Term Monitoring: If required, long term-monitoring ensures that remediation and long-term risk management goals are achieved.

Source: A Federal Approach to Contaminated Sites (CSMWG, 1999)

Note: The steps indicate the stage of each site and not the effort associated with each step. Significantly more time and energy are required to complete Step 8 than any other step.

Progress in managing FCSAP projects is tracked according to the 10 steps of the CSMWG Federal Approach to Contaminated Sites (see box). However, managing a contaminated site is a complex and multi faceted undertaking, particularly at large and/or highly contaminated sites. Because contaminated sites may contain various types of contaminants in different media (e.g. soil, sediment, groundwater), different remediation activities may be required at different times throughout the project life cycle. This variability can affect how progress is described. Also, activities on contaminated sites do not necessarily progress in the linear manner described by the Ten Step Process. At times, it may be necessary to carry out urgent activities that would normally be undertaken in later steps in order to prevent a severe environmental event from occurring.

In 2007-08, 15 custodians reported activity at 276 remediation / risk management projects, and 590 assessment projects. Total expenditures under FCSAP by custodian and project category are summarized in Table 2.

Table 2: FCSAP Project Expenditures by Custodian (2006–07)

Custodian

Assessment

Remediation/risk management

Number of projects with activity

Number of sites with activity

FCSAP funding available*($)

FCSAP funds spent ($)

Custodian share spent

Number of projects with activity

Number of sites with activity

FCSAP funding available*($)

FCSAP funds spent ($)

Custodian share spent

Total

590

2269

27,886,247

18,483,725

6,142,690

276

519

198,322,521

146,879,259

19,182,048

Total FCSAP funds spent on assessment and remediation/risk management projects

162,362,984

Agriculture and Agri-Food Canada (AAFC)

21

36

796,000

445,897

111,474

1

1

500,000

562,503

140,626

Canada Border Services Agency

-

-

-

-

-

2

2

341,360

327,098

82,346

Correctional Service of Canada

-

-

27,921

-

-

1

1

1,062,086

1,349

337

Environment Canada (EC)

15

203

3,976,350

634,652

158,663

4

140

5,364,209

2,696,354

473,169

Fisheries and Oceans Canada (DFO)

71

605

6,357,929

3,819,994

954,998

103

103

10,514,184

3,877,973

969,474

Health Canada (HC)

10

10

136,000

136,000

262,381

7

7

1,174,366

442,585

136,383

Indian and Northern Affairs Canada (Indian and Inuit Affairs Business Line)

47

580

3,232,003

2,310,115

567,679

31

45

10,515,480

7,607,531

1,901,810

Indian and Northern Affairs Canada (Northern Affairs Program)

118

118

1,559,122

898,806

224,706

26

29

99,231,835

75,569,559

5,927,381

The Jacques Cartier and Champlain Bridges Inc. (JCCBI)

-

-

-

-

-

-

-

92,000

-

-

National Defence (DND)

43

167

5,310,337

5,310,337

2,347,114

52

103

51,004,136

42,824,283

6,323,902

National Capital Commission (NCC)

23

66

609,670

566,633

141,658

2

2

192,000

192,000

113,139

Natural Resources Canada (NRCan)

4

4

175,810

35,428

8,857

-

-

-

-

-

Parks Canada Agency (PC)

34

50

1,406,341

1,343,122

391,705

9

11

1,530,856

1,004,774

303,013

Public Works and Government Services Canada (PWGSC)

34

50

1,406,341

1,343,122

391,705

9

11

1,530,856

1,004,774

303,013

Royal Canadian Mounted Police (RCMP)

188

397

2,820,000

2,020,622

519,515

9

9

2,213,600

912,112

228,027

Transport Canada (TC)

5

7

520,000

111,000

103,000

14

17

11,548,948

8,733,435

1,996,978

* Total FCSAP funding available = 2007–08 allocated amount + brought forward amounts from 2006–07.

2.1 FCSAP Priority Sites

2.1.1 FCSAP Funding Approvals and Expenditures

Table 3 provides a summary of the approved FCSAP funding, actual FCSAP expenditures and the corresponding custodian expenditures.

As described in Section 1.2, custodians are required to meet cost shares on an annual basis. In fiscal year 2007-08, four custodians (Department of National Defence [DND], Indian and Northern Affairs Canada-Northern Affairs Organization [INAC-NAO], EC and Transport Canada [TC]) had projects that produced adjusted FCSAP cost shares6. All other federal custodians were required to respect the typical 80/20 (FCSAP/custodian) cost share requirement.

In 2007-08, all but two custodians (INAC (including both NAO and Indian and Inuit Affairs Business Line [IIABL]) and EC) either met or surpassed their annual cost share requirement. The shortfalls were calculated as follows: $837,179 for INAC-NAO (which represents 14% of their total custodian expenditures); $85,713 for EC (14% of their total custodian expenditures); and $9,923 for INAC-IIABL (less than 1% of their total custodian expenditures).

Table 3: Summary of Project Funding Approvals and Actual Expenditures (2007-08)

Project type

FCSAP funding allocated (millions)

Project work undertaken in fiscal year 2007–08

Number of projects with activity

Number of sites with activity

FCSAP Fund expenditures (millions)

Custodian expenditures (millions)

Total

$217.697

866

2788

$165.36

$25.32

Remediation/risk management

$192.69

276

519

$146.88

$19.18

Assessment

$25.0

590

2269

$18.48

$6.14

2.1.2 Assessment Projects

Funding of assessment projects is an important part of FCSAP. The results of assessments facilitate the identification of risks to human health and the environment, and the accurate estimation of federal financial liability for contaminated sites. In assessment Steps 1 to 4 (initial) and 5 to 6 (detailed) of the Ten Step Process, scientifically defensible work is undertaken to identify the presence, nature and extent of site contamination.

In 2007-08, $18,483,725 of the available FCSAP assessment funds ($27,886,247) were spent by 12 different custodians at 2269 sites, grouped into 590 projects. The available amount included $25,000,000 that was allocated in 2007-08, and $2,886,247 of unused FCSAP assessment funds that were transferred from the previous fiscal year. Assessment activities were most prominent in Manitoba (567 sites), Atlantic Canada (482 sites), and Quebec (228 sites), as a result of large scale assessment initiatives undertaken by DFO and the Royal Canadian Mounted Police (RCMP) in Atlantic Canada, and Quebec and INAC-IIABL in Manitoba. Overall, the number of sites assessed in 2007-08 (2269) was almost double the number of assessments in fiscal year 2006-07 (1252) and more than three times the number of sites assessed in 2005-06 (660). A summary of 2007-08 assessment projects, sites and FCSAP expenditures is presented by province/territory in Table 4 and by custodian in Table 5.

Table 4: Number of Assessment Projects and Sites by Province/Territory (2007-08)

Province/territory

Number of projects with activity

Number of sites with activity

Estimated FCSAP funds spent ($)8

Total

590

2269

18,483,7259

Alberta

44

142

1,479,860

British Columbia

52

163

1,268,335

Manitoba

27

567

2,553,448

New Brunswick

56

106

718,102

Newfoundland and Labrador

20

218

1,185,452

Northwest Territories

51

311

2,246,400

Nova Scotia

26

25

219,687

Nunavut

111

148

2,070,820

Ontario

53

150

1,820,041

Prince Edward Island

11

30

196,418

Quebec

62

228

3,403,393

Saskatchewan

35

183

901,028

Yukon Territory

6

6

84,851

Table 5: Number of Assessment Projects and Sites by Custodian (2007-08)

Federal custodian

Number of projects

Number of sites

FCSAP funds spent ($)

Total

590

2269

18,483,725

Agriculture and Agri-Food Canada

21

36

445,897

Environment Canada

15

203

634,652

Fisheries and Oceans Canada

17

605

3,819,994

Health Canada

10

10

136,000

Indian and Northern Affairs Canada

 

 

 

   Indian and Inuit Affairs Business Line

47

580

2,310,115

   Northern Affairs Organization

118

118

898,806

National Capital Commission

23

66

566,633

Department of National Defence

43

167

5,310,337

Natural Resources Canada

4

4

35,428

Parks Canada Agency

34

50

1,343,122

Public Works and Government Services Canada

11

26

851,119

Royal Canadian Mounted Police

188

397

2,020,622

Transport Canada

5

7

111,000

2.1.2.1 Explanation of Financial Variance for FCSAP Assessment Projects (2007-08)

A total of $25,000,000 was approved for assessment activities in 2007-08. As shown in Table 3, custodians contributed funds amounting to $6,142,690 and FCSAP provided $18,483,725 in funding for assessment activities. As indicated in the financial table in Appendix 3b, the difference between planned and actual expenditures for assessment projects was $9,402,522, after adjusting for the funds transferred from the previous fiscal year and funds transferred from Expert Support ($2,886,24710). The variance is due to the following factors:

  1. Custodians who received funds and could not complete the assessment work in 2007-08 rescheduled the work for the next season and transferred unspent FCSAP funds in the amount of $7,662,64211 to fiscal year 2008-09.
  2. INAC-IIABL spent $418,403 of its FCSAP funds that had been allocated for remediation / risk management on assessment projects.
  3. Agriculture and Agri-Food Canada (AAFC) spent $62,503 of its FCSAP funds for assessment on remediation / risk management projects.
  4. FCSAP funds in the amount of $2,095,780 were not spent.

Variance between planned and actual expenditures for individual assessment projects can be attributed to a variety of factors, including the reallocation of funding from previously approved sites to more urgent assessment requirements, shifting custodian demands or priorities, and the difficulty in initial estimation of the projected costs of assessments because the nature and extent of contamination is unknown at the outset of the project.

Fisheries and Oceans Canada: Assessment of Minor Shore Lights
Multiple Locations across Canada

The Fisheries and Oceans Canada (DFO) is the custodian of a diverse array of urban, rural (mostly coastal) and remote properties. DFO is one of the largest custodians of real property within the federal government, with interest in more than 8200 properties across the country. The Department is a program manager, regulator and facilitator; a building owner; an operator; and a manager of assets such as buildings, vehicles, aircraft, vessels and harbours.

Minor Shore Lights have served as navigational aids to vessels for centuries. Of DFO's entire property portfolio, approximately 2200 properties are classified as Minor Shore Lights. There are a variety of different types of Minor Shore Lights under the custodianship of DFO, including those with an aluminum/steel skeleton tower, a wooden structure, or a fibreglass cylindrical structure, among others. These aids are fixed in place, equipped with a light, and can also include former light stations. Historically, the use of mercury baths, compressed gas, batteries and lead-based paint were common to these sites and have subsequently resulted in high levels of heavy metals, hydrocarbons and other pollutants at many of these locations.

The assessment of these properties is risk-based and takes into account the likelihood of contamination based on past and/or present operations, and the potential for risks to human health and the environment. The anticipated future use of the site is taken into account during the assessment and management of these sites, including whether or not the Department intends to retain the site or the site is being actively marketed for divestiture.

2.1.2.2 Results of Assessment for FCSAP Assessment Projects (2007-08)

In 2007-08, assessment activity-resulting in one of the following four outcomes-was reported for 2269 sites. Figure 1 presents the distribution of the 2007-08 assessment outcomes on these sites.

There were an additional 1063 sites, which were reported as not assessed with no further action planned. These had generally been divested in-year or were the result of multiple Federal Contaminated Sites Inventory numbers that had been consolidated into one site. There were an additional 3263 active assessment sites that were not assessed in 2007-08.

Figure 1: FCSAP Assessment Results (2007-08)

Figure 1: FCSAP Assessment Results (2007-08)

(Description of the above image)

Referring to Figure 1 above, approximately 20% of the sites indicated the need for additional investigation and 16% of sites confirmed contamination in need of remediation / risk management. The remaining 65% of sites (for which assessment was either partially [23%] or fully [42%] completed) indicated that no further assessment activities would be undertaken in future fiscal years.

For the 2269 sites where assessment activity occurred, Figure 2 presents the last step completed in 2007-08. Seventy-six percent (76%) of sites were in the process of completing or had completed initial assessment work, which is delivered as steps 1 to 4 (identification of a suspect site, historical review, initial testing, and classification). Eleven percent (11%) of sites reported activity in the final stages of and/or the completion of a full site assessment, the second stage of assessment work which is undertaken in steps 5 and 6 (intrusive testing and site reclassification). The remaining 13% of sites had completed activities in Step 7 or higher (or were archived); and while Step 6 is normally considered the end point for the funding of assessments, occasionally-if the contamination is minimal-it is often more efficient and cost effective to undertake site remediation concurrent with assessment activities.

Figure 2: Status of FCSAP Assessment Projects by Step (2007-08)

Figure 2: Status of FCSAP Assessment Projects by Step (2007-08)

(Description of the above image)

2.1.3 Remediation / Risk Management Projects

FCSAP supports federal custodians responsible for contaminated sites in all parts of Canada. In 2007-08, remediation / risk management accounted for 87% of total expenditure under the FCSAP and activity was reported throughout Canada at 276 remediation / risk management projects consisting of 519 sites. Within these 276 projects, 35% of projects (96 projects) reported delays or project setbacks, such as weather (12% of projects), industry capacity issues (8% of projects), the identification of new contamination (7% of projects), legal issues (3% of projects), and lack of custodian financial resources (1%).

2.1.3.1 Nature of Contamination in Remediation / Risk Management Projects Funded under FCSAP

A contaminated site is an area in which substances occur at concentrations above normally occurring background levels and pose, or are likely to pose, an immediate or long-term hazard to human health or the environment. Determining the risk posed by the presence of these substances involves identifying the potential receptors, determining potential exposure pathways, and estimating the level of risk based on the pathways. Refer to Appendix 1 for more information on how human health and ecological risks are evaluated under FCSAP.

Contamination of sites is primarily a result of past practices and activities whose environmental consequences were not fully understood at the time. The size and scope of federal contaminated sites vary greatly. Common examples include abandoned mines on federal Crown land in the North, airports, government laboratories, harbours, lighthouse stations, national parks, military bases and training facilities, former DEW line sites, and Aboriginal communities (Figure 3).

In 2007-08, the greatest proportion of remediation / risk management activity was reported for DFO light station projects (32% of all remediation / risk management projects) comprising 2% of total remediation / risk management FCSAP expenditures. The most significant proportion of expenditures was reported by INAC-NAO and DND (67% of all remediation / risk management expenditures) for activities undertaken at abandoned mines (6% of all remediation / risk management projects) and former DEW line sites (7% of all remediation / risk management projects) in the Canadian North.

Figure 3: Remediation / Risk Management Project Categories (2007-08)

A) Distribution of Projects by Project Category

Figure 3: Remediation / Risk Management Project Categories (2007-08)

(Description of the above image)

B) Distribution of Expenditures by Project Category

B) Distribution of Expenditures by Project Category

Remediation / risk management sites targeted for FCSAP funding have multiple types of affected media (Figure 4) that are contaminated by a wide variety of substances (Figure 5) resulting from one or more historic activities (Table 6). In 2007-08, soil contamination (86% of projects) and groundwater contamination (31% of projects) was most often related to the presence of metals (71% of projects), petroleum hydrocarbons (68% of projects), and polycyclic aromatic hydrocarbons (PAHs) (42% of projects). The main sources of contamination were fuelling activities/spilling (33% of projects), the presence of above ground storage tanks (AST)/piping (20% of projects with above-ground storage tank capacity of less than 2500 litres [AST< 2500L]; 21% of projects with AST>= 2500L), lead/metal/PCB containing paints (28% of projects), and batteries (24% of projects) on site.

Table 6: Contaminant Sources Identified for Remediation / Risk Management Projects (2007-08)

Contaminant Soources

Number of projects

Percentage of projects

Above-ground Storage Tank(s)/Piping (<2500L)

56

20%

Above-ground Storage Tank(s)/Piping (>=2500L))

57

21%

Active Waste Disposal Site

40

14%

Adjacent Property

3

1%

Batteries

66

24%

Burn Pit

21

8%

Chemical Storage / Spill

11

4%

Creosote / Chromated Copper Arsenate Materials

2

1%

Dredging Materials

1

0.3%

Fill Materials

13

5%

Fire Fighting Training Area

5

2%

Fuelling Activities / Spill

90

33%

Galvanized Steel

5

2%

Golf Course Maintenance / Landscaping Activities

0

0%

Hazardous Construction Materials

9

3%

Historical Vessel Activities

7

3%

Inactive Waste Disposal Site

35

13%

Lead/Metal/PCB-Containing Paint

78

28%

Mercury Bath

23

8%

Mining and/or Milling Industries

15

5%

Miscellaneous On-Shore Harbour/Port Activities

6

2%

Oil and Gas Extraction Activities

0

0%

Other

55

20%

Other Waste Materials

9

3%

PCB Storage

2

1%

Pesticide / Herbicide Dump

2

1%

Petroleum Products Storage Area

11

4%

Road Salt Storage / Application

9

3%

Sewage / Liquid or Sewage Effluent

5

2%

Snow Disposal

0

0%

Tires

1

0.3%

Underground Storage Tank(s)/Piping

28

10%

Unknown/Unsure

4

1%

Waste Storage

17

6%

Figure 4: Contaminated Media at Remediation / Risk Management Sites (2007-08)

Figure 4: Contaminated Media at Remediation / Risk Management Sites (2007-08)

(Description of the above image)

Figure 5: Types of Contamination at Remediation / Risk Management Sites (2007-08)

Figure 5: Types of Contamination at Remediation / Risk Management Sites (2007-08)

(Description of the above image)

2.1.3.2 Location and Distribution of FCSAP Remediation / Risk Management Projects

Due to the large number of remediation / risk management projects funded by FCSAP in 2007-08, for the purpose of distribution analyses the projects have been categorized based on their total expected completion costs. The estimated completion costs serve two functions: (1) to determine whether the project approval submission follows the streamlined or regular risk evaluation process12 and (2) to provide the FCSAP Secretariat with information useful for work-planning and estimating future demands on the program.

Total expected completion costs are structured as follows:

  • less than or equal to $250,000
  • greater than $250,000 up to and including $1,000,000
  • greater than $1,000,000 up to and including $10,000,000
  • greater than $10,000,000

A detailed summary of the provincial/territorial distribution of remediation / risk management projects funded in 2007-08 is provided in Appendix 2, and the national distribution is mapped in Figure 6. The map identifies the number and location of projects with expected completion costs less than or equal to $10 million and projects with expected completion costs greater than $10 million. A large number of small projects that fall under DFO are distributed along the coastlines. High-cost projects (with total estimated expenditures of greater than $10 million) managed by INAC-NAO and by DND are concentrated in northern Canada.

Figure 6: National Distribution of FCSAP Remediation / Risk Management Projects (2007-08)

Figure 6: National Distribution of FCSAP Remediation / Risk Management Projects (2007-08)

(Description of the above image)

The distribution of remediation / risk management projects is greatest in British Columbia (26% of projects), Atlantic Canada13 (21% of projects), and Quebec (17% of projects). However, when the location and expenditure data are compared, it becomes clear that the number of projects is not directly related to the overall project expenditures. Together, British Columbia, Quebec, and Atlantic Canada account for 64% of the number of projects but less than one quarter (<23%) of the associated expenditures. Similarly, northern Canada-Nunavut, Yukon, and the Northwest Territories-has only 18% of the projects but accounts for nearly three quarters (72%) of the FCSAP expenditures. The remaining 18% of projects and >5% of expenditures are distributed among the Prairies. (Figure 7)

Figure 7: National Distribution of Remediation / Risk Management Projects (2007-08)

A) Distribution of Projects by Province/Territory

A) Distribution of Projects by Province/Territory

B) Distribution of Expenditures by Province/Territory

B) Distribution of Expenditures by Province/Territory

(Description of the above images)

The relatively large concentration of remediation / risk management projects being undertaken in Quebec, Atlantic Canada, and British Columbia (Figure 7) is the direct result of many smaller scale projects (such as light stations and small craft harbours) that are being managed by DFO. As an overall percentage, in 2007-08 DFO was responsible for 37% of projects but only received 3% of the FCSAP annual funding allocated to remediation / risk management projects.

Unlike DFO, DND and INAC have fewer projects but they tend to be larger-primarily abandoned mines and former DEW line sites in the Canadian North. Located in Nunavut, the Yukon, and the Northwest Territories, these projects are associated with significant costs for logistics. In 2007-08 alone, DND and INAC-NAO combined spent $118,393,842 (80%) of the FCSAP funds allocated to remediation / risk management on 78 (28%) projects.

Refer to Figures 8A/B for details of the 2007-08 distribution of projects and expenditures by custodian.

Figure 8: Distribution of Remediation / Risk Management Projects by Custodian (2007-08)

A) Distribution of Projects by Custodian

B) Distribution of Expenditures by Custodian

(Description of the above images)

2.1.3.3 Explanation of Financial Variance for FCSAP Remediation / Risk Management Projects (2007-08)

As indicated in Table 3, the total funding approved in 2007-2008 for FCSAP remediation / risk management projects was $192,689,953. Over the course of the year, custodians contributed funds amounting to $19,182,048, and spent $146,879,259 of FCSAP funding. The variance between allocated FCSAP funding and actual expenditures is $51,443,262, after adjusting for the funds transferred from the previous fiscal year ($5,632,568 14). This variance is due to several factors:

  1. Custodians rescheduled some planned 2007-2008 work activities for the next season, transferring FCSAP funding in the amount of $35,154,78815 to fiscal year 2008-2009.
  2. AAFC spent $62,503 of their approved FCSAP assessment funding on their remediation / risk management projects.
  3. INAC-IIABL spent $418,403 of their approved FCSAP remediation / risk management funds on assessment projects.
  4. INAC-NAO spent $79,672 of FCSAP remediation / risk management funds on program management activities.
  5. FCSAP funds in the amount of $15,852,902 were not spent. Reasons for this funding not being spent can include the following:
    • change in scope of work
    • actual costs different from estimates
    • some activities were postponed to future years
    • required access to site was not possible due to weather, transportation, or other factors
    • litigation or legal issues prevented work from proceeding
2.1.3.4 Remediation / Risk Management Project Achievements

Under normal conditions, the implementation of the remediation / risk management plan falls under Step 8 of the Ten Step Process. Step 8 is composed of a wide variety of activities, which include evaluating the available remediation / risk management technology, performing cost-benefit analyses, selecting a contractor, and obtaining the necessary permits (i.e., water licence, land use permit, or approval under the Canadian Environmental Assessment Act). Because of the large number and variety of activities that can be undertaken under Step 8, it is often many years before a project is ready to proceed to Step 9. In Step 9 of the Ten Step Process, confirmatory sampling and final reporting are completed. Following Step 9, contaminated sites are considered to have been "addressed," other than where long-term monitoring (Step 10) is required. In 2007-08, approximately one third of sites were reported as Step 9 and 198 sites were marked as completed.

Figure 9 provides an overall picture of the highest step in which work was undertaken based on 2007-08 reporting and does not imply that the step is complete. Data are compiled at the project level and include two caveats: (1) not all sites in a project are necessarily in the same step and (2) the step is not necessarily complete - a project will often work through the same step for a number of years before proceeding to the next stage of the program.

Because remediation and risk management are non-linear processes, occasionally some projects experience an apparent "jump" in the step that is reported at fiscal year end. This is often the result of simultaneous assessment and remediation work occurring on larger projects. With complex multi-site projects, remediation may be occurring at one or more sites while assessment work or remediation planning is being undertaken at others. This apparent "back-tracking" of steps can also be related to the discovery of previously unidentified contamination, the need for additional delineation, and/or the overhaul or enhancement of an existing remediation plan, with the result that more work may be required than was previously anticipated. Therefore, the last step completed or the highest step with activity that is reported at the end of the fiscal year will reflect this change. Consequently, the proportion of projects within a given step (Figure 9) will reflect only the most advanced part of the project. The activities and expenditures for all remediation / risk management projects with FCSAP year-to-date expenditures greater than $1 million are summarized in Figure 10.

Figure 9: Status of FCSAP Remediation / Risk Management (RM) Projects by Step (2007-08)16

Figure 9: Status of FCSAP Remediation / Risk Management (RM) Projects by Step (2007-08)

(Description of the above image)

Figure 10: Progress of Remediation / Risk Management Projects Funded under FCSAP with Project Expenditures Greater than $1 Million (2007-08)

Description of the table

Steps in the Ten-Step Process (from the Federal Approach to Contaminated Sites)
Federal custodian Project 1 2 3 4 5 6 7 8  9  10 FCSAP
funds
spent on
project ($)
during FY 07-08
FCSAP
funds
spent on
project ($)
since FY 03-04
Remediation / Risk management Projects
Table lines : Steps completed up to the end of FY 2006-07
Table lines : Steps with work undertaken during FY 2007-08
* Funds spent in FY 2003-04 and 2004-05 under the Federal Contaminated Sites Accelerated Action Plan (FSCAAP)
DFO Bellville SCH Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       464,684 1,641,090
DND 5 Wing Goose Bay Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       3,315,444 12,913,025
DND 14 Wing Greenwood Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       808,053 5,378,363
DND CAM1 - Jenny Lind Island Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       2,473,850 2,650,410
DND CAM2 - Gladman Point Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       94,316 7,948,212
DND CAM3 - Shepherd Bay Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       4,605,906 10,143,911
DND CAM4 - Pelly Bay Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       503,530 5,474,586
DND CAM5 - Mackar Inlet Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       3,540,395 3,729,627
DND Colwood Aggregate Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines    Table lines 2,895,982 6,415,694
DND DYEM - Cape Dyer Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       5,135,020 26,794,104
DND FOX5 - Broughton Island Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       223,505 8,046,152
DND FOX M - Hall Beach Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       8,584,748 27,197,320
DND PIN 3 - Lady Franklin Point Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       102,113 1,188,453
DND PIN 4 - Byron Bay Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       1,979,982 3,864,034
DND Shea Heights/
Southside Tank Farm
Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       727,251 1,208,215
DND Suffield EPG Table lines Table lines Table lines Table lines Table lines Table lines Table lines          328,356 1,464,322
DND Valcartier TCE Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       2,915,968 14,915,905
EC Pacific Environment Centre Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       2,523,305 7,845,254
EC Moose Factory Hospital Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       144,000 1,308,182
HC Weagarrow Lake Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       76,500 1,562,162
INAC-IABL 1550 Clifford Road Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       113,000 1,245,430
INAC-IABL Barrenlands
/ Brochet Frontier School
Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       37,476 2,385,392
INAC-IABL Former God's Lake School Tankfarm Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       250,560 1,006,044
INAC-IABL Former Red Sucker Lake School Tankfarm Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       720,720 1,202,663
INAC-IABL Gixaala Nation Former Power House Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       1,690,913 3,918,130
INAC-IABL God's lake Band Tankfarm Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       250,560 1,171,545
INAC-IABL Mathias colomb Area 5B Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       625,600 1,965,600
INAC-IABL Sandy lake Remediation Project Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       833,380 1,407,898
INAC-IABL Wapekeka Soil Remediation Project Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       1,480,000 1,480,000
INAC-NAO Axe Point Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines    1,481,313 2,218,024
INAC-NAO BARD - Atkinson Point Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       1,481,313 2,218,024
INAC-NAO CAMF - Sarcpa Lake Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       5,129,352 13,255,485
INAC-NAO Clinton Creek Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       147,686 2,307,336
INAC-NAO Colomac Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       11,730,181 67,468,314
INAC-NAO Contact Lake Table lines Table lines Table lines Table lines Table lines Table lines Table lines          601,759 1,127,896
INAC-NAO Discovery Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       1,021,803 8,333,816
INAC-NAO Faro Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       15,537,999 65,999,183
INAC-NAO Fox C - Ekalugad Fiord Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       5,009,951 14,328,319
INAC-NAO Giant Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       10,752,398 47,725,138
INAC-NAO Johnson Point Table lines Table lines Table lines Table lines Table lines Table lines Table lines          382,897 1,952,815
INAC-NAO Mount Nansen Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       1,062,005 5,004,826
INAC-NAO Port Radium Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines    4,012,197 10,099,631
INAC-NAO Radio Island Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines    2,906,473 6,705,672
INAC-NAO Roberts Bay Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines          465,374 1,147,686
INAC-NAO Silver Bear Mines Table lines Table lines Table lines Table lines Table lines Table lines Table lines          1,072,576 4,163,008
INAC-NAO Tundra-Taurcanis Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       4,700,244 10,179,121
INAC-NAO United Keno Hill Mine Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       3,043,848 13,182,720
INAC-NAO Bushell Public Port Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines    2,985,241 5,675,207
INAC-NAO Former Remote Radar Site 59 Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines       102,367 3,493,854
INAC-NAO Fort Nelson Airport Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines    2,456,623 2,456,623
INAC-NAO Nitchequon Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines Table lines    254,981 3,588,350
INAC-NAO Rock Bay Table lines Table lines Table lines Table lines Table lines Table lines Table lines          1,341,938 12,154,937
2.1.3.5 Activities at Remediation / Risk Management Projects

Remediation / Risk Management Activities

In 2007-08, 200 of 276 remediation / risk management projects undertook one or more remediation / risk management activity as part of Step 8 of the 10-step process. Of these 200 projects, 183 projects (66%) were reported as having active remediation / risk management activity (i.e. Step 8 B/C/D)17 , which is significantly higher than 2006-07, when only 44% of projects were actively being remediated / risk managed. The remaining 17 remediation / risk management projects reported activities in Step 8A.

A total of 513 remediation / risk management activities occurred across these 183 projects (123 (68%) of the 183 projects reported concurrent, multiple remediation / risk management activities). In total, 29 different classes of remediation / risk management activity were undertaken (Figure 11).

As in 2006-07, the most common remediation activities for 2007-08 were soil excavation (82 projects), the collection of hazardous materials (50 projects), and bioremediation (39 projects). The most common risk management strategies were the implementation of environmental (66 projects) and human health (41 projects) monitoring programs.

Figure 11: Remediation / Risk Management Activities Undertaken in 2007-08

Figure 11: Remediation / Risk Management Activities Undertaken in 2007-08

(Description of the above image)

3.0 2007-08 Program Achievements: Linkages

In addition to its primary objectives, FCSAP provides opportunities to maximize value for money by promoting linkages with other government of Canada socio-economic priority initiatives. Examples include links with skills development for, and training and employment of, Canadians, particularly in Aboriginal communities and in northern or rural areas; and competitiveness and technological advancement in the environment industry. Although custodians are generally responsible for identifying opportunities to incorporate such linkages into the management of their contaminated sites portfolio, they are largely supported in these activities by a number of other departments where there is alignment with departmental mandates.

Human Resources and Skills Development Canada has committed to working with custodians, Aboriginal organizations, the Environmental Careers Organization (ECO Canada), the private sector, learning institutions, and other stakeholders, to develop synergies between investments in the cleanup of contaminated sites and capacity building, for individual Canadians through training and skills development and for the environmental industry as a whole.

Similarly, through its expert support role, PWGSC, with support from Industry Canada, provides information on innovative technologies so that custodians, other levels of government, and industry can benefit from the technological advances that will accrue from this long-term program. PWGSC also provides liaison with the environment industry that delivers the remediation services required for program implementation, so that industry is aware of remediation requirements and can build capacity to meet projected future demand.

3.1 Key Activities in 2007-2008

3.1.1 Socio-Economic

In 2007-08, ECO Canada tabled the report When Supply does not Meet Demand: Labour Gaps and Issues in Canada's Contaminated Sites Sector - 2008, which built on ECO Canada's previous study completed in 2006-07 Who will do the Cleanup? Canadian Labour Requirements for Remediation and Reclamation of Contaminated Sites - 2006-2009. The purposes of these studies were: (1) to provide a clearer picture of the labour demand for contaminated sites work; (2) to offer recommendations for next steps, which may include additional examination of the existing and forecasted labour supply, an analysis of training and educational gaps, and the development of procurement policies that reflect labour market reality and identified best practices; and (3) to build greater industry awareness and support for Government and private sector contaminated sites policies.

In response to the positive social and economic outcomes projected by ECO Canada, FCSAP has collected detailed data on the demand for Aboriginal skills and services generated by remediation / risk management projects funded under the Program. Overall in 2007-08, minimum levels of Aboriginal/Inuit employment (as stipulated by Comprehensive Land Claim Agreements in the North) were generally met or surpassed: eight custodians reported employing 663 Aboriginal individuals and training 202 Aboriginal individuals at 56 projects.

Examples of the range of FCSAP activities being undertaken in support of economic development and training for Aboriginal people in the environmental sector are highlighted below:

  • Through the Procurement Strategy for Aboriginal Business and the Aboriginal Benefits Packages, and by soliciting bids locally on lower value contracts, INAC is bringing socio-economic benefits to local communities, where possible. The objective of the Procurement Strategy is to maximize Northern and Aboriginal community, business and individual participation, as well as economic development opportunities. The Aboriginal Benefits Strategy, which includes an Aboriginal Benefits Plan, is part of the overall competitive procurement process.
  • DND is committed to encouraging the training and employment of Aboriginal people across Canada. DND has entered into co operative agreements with the Inuvialuit and the Inuit people of the Yukon, Northwest Territories and Nunavut, for the cleanup of 21 contaminated sites. These agreements contain clearly marked requirements regarding the minimum Aboriginal employment content, as well as the minimum Aboriginal contracting content for each site. This has resulted in the successful training and employment of many Aboriginal people in the North as well as the use of Aboriginal firms to complete work on these sites.
  • EC has developed a Student Mentoring Program to guide students into the environmental industry. Over the longer term, the objective is to enlarge the pool of technical talent accessible to EC and the environmental industry in general.
  • By encouraging the participation of its Aboriginal and Inuit employees in the remediation and risk management of contaminated sites in the North, the Parks Canada Agency (PC) is contributing directly to the Northern Strategy in the area of environmental protection. The assessment of Stokes Point, a former DEW line site located along the coast of the Beaufort Sea in Ivvavik National Park, Yukon Territory, is a concrete example of environmental protection with links to the Northern Strategy. Through consultation with local Inuvialuit stakeholders and federal departments, an advisory committee has been established. The objective of the committee is to study and approve proposed cleanup criteria as well as the development of a future remediation plan.
  • TC is committed to using the Government of Canada's Aboriginal Set-Aside and Procurement Strategy Program for Aboriginal Business for projects in the North. In 2007-08, TC employed between 5-7 aboriginals for two weeks for the Airport Apron and Sea Can Drum Cache projects in Iqaluit. In addition, aboriginal sub-contractors were employed for remediation work at Inuvik and Norman Wells in the Northwest Territories. Contaminated site projects have social, environmental and economic benefits for local communities. These projects inject revenue into the local economies not only through employment but also local procurement of goods and services. For projects in the North, approximately half of the expenditures are spent within the local community.

Indian and Northern Affairs Canada - Northern Affairs Organization

INAC-NAO is the custodian of most federal lands in the North. In the Northwest Territories and Nunavut, the NAO holds direct responsibilities for assessment and remediation of identified and suspected contaminated sites. Within the Yukon, the Organization's activities are guided by the requirements of the Devolution Transfer Agreement between the federal and Yukon governments, and responsibilities for contaminated sites are shared between the two levels of government.

As assessment and remediation / risk management activities are carried out in the North, the NAO strives to create social and economic benefits through direct employment of local people, support to local businesses, and training programs that develop local capacity and build skills. Commonly procured goods and services from local businesses include professional services (i.e., consulting, trades, remediation, construction, laboratory), winter road construction, transportation services, air charters, equipment rentals, and fuel.

Overall in 2007-08, a greater percentage of employees were northern Aboriginal, more employees received training, and a greater number of northern suppliers were hired than in 2006-07.

Employment and Business in the North (2007-08)

In 2007-08, the total reported employment for NAO-managed sites was 1027 people, down 28 people from the previous year. Despite the overall decrease in jobs in 2007-08, the proportion of Northern and Aboriginal employees increased: 73% of employees were from the North, and 49% of employees were Aboriginal. Twenty-eight sites reported doing business with 929 northern suppliers in 2007-08, of which 187 were northern Aboriginal suppliers. The total value of business with northern suppliers was roughly $25 million, 53% of which was from northern Aboriginal suppliers.

Workforce Training (2007-08)

Fifteen sites reported providing training to approximately 1460 employees in 2007-08, which is over twice the number of employees who were reportedly trained in 2006-07. Of the 1460 people who were trained in 2007-08, 73% were northerners and 26% were northern Aboriginal people. In total, 7278 hours of training were reported at sites in 2007-08, up from 5689 hours reported in 2006-07.

Source: Performance Report 2007-08, Indian and Northern Affairs Canada, Contaminated Sites Program

3.1.2 Innovative Technology

The scope of FCSAP presents a valuable opportunity for the Canadian remediation industry sector to respond to the needs and challenges of cleaning up federal contaminated sites by providing effective new solutions.

For the current purposes of FCSAP, the term "innovative technology" is defined as any treatment method for soil, groundwater or vapour, excluding traditional excavation and disposal or pump and treat technologies (i.e., ex situ treatment technologies where cost and performance data are readily available).18 However, the way that innovative technologies are analyzed is expected to evolve in future years of the Program, as technologies that were once considered innovative begin to form part of the standard suite of remediation options.

3.1.2.1 2007-08 Remediation Activities and the Use of Innovative Technologies

In 2007-08, 200 of 276 remediation / risk management projects undertook one or more remediation / risk management activity as part of Step 8 of the 10-step process. Of these 200 projects, 62 projects (31%) reported using one or more types of innovative remediation technology. Among the 62 projects that used innovative technology, 30 projects (48%) used innovative technology exclusively and 32 projects (52%) used a combination of innovative and conventional technologies or activities. Entirely conventional remediation / risk management technologies or activities occurred in the remaining 138 projects (69%) (Figure 12).

Figure 12: Conventional versus Innovative Remediation Options (2007-08)

Figure 12: Conventional versus Innovative Remediation Options (2007-08)

(Description of the above image)

Under the current definition of innovative technology (see Section 3.1.2), 62 projects funded under FCSAP in 2007-08 incorporated one or more of the twelve types of innovative remediation technologies illustrated on Figure 13. Bioremediation accounted for the most significant proportion of innovative technologies (40%), followed by enhanced bioremediation/biopiles (17%), monitored natural attenuation (12%) and thermal treatment/desorption (9%).

In addition to the 62 projects that used innovative remediation technologies in 2007-08, innovative technologies were considered but not implemented at another 25 projects. Within this subset of projects that considered but did not implement innovative technologies, one or more of the following reasons were identified: cost (9 projects); time frame (13 projects); type of contamination (9 projects); site conditions (13 projects); public attitude/stakeholder consultation (6 projects); and/or the conventional technologies were considered most effective (15 projects).

Figure 13: Breakdown of Innovative Remediation Activity (2007-08)

Figure 13: Breakdown of Innovative Remediation Activity (2007-08)

(Description of the above image)

Over the same period, a number of conventional remediation technologies/activities occurred, as illustrated on Figure 14. Excavation accounted for the most significant proportion of conventional remediation technologies/activities (26%), followed by collection of hazardous materials (16%) and shipment to off-site landfills (13%).

Figure 14: Breakdown of Conventional Remediation Activity (2007-08)

Figure 14: Breakdown of Conventional Remediation Activity (2007-08)

(Description of the above image)

In a year-over-year comparison of remediation technology/activity by project, there was an increase in the number of projects in 2007-08 (276 vs. 61 in 2006-07) and an increase in the percentage of projects where remediation / risk management activities were taking place (72% vs. 28% in 2006-07). This reflects the increase in the number of new remediation / risk management projects being funded in 2007-08.

In terms of the distribution of technologies/activities within the active remediation portion of the process (Steps 8 B/C/D), in 2007-08 there was an increase in the number of projects using innovative technology (51 vs. 40 in 2006-07), but a decrease in the overall percentage of projects using innovative technology [51/183 projects (31%) vs. 40/61 projects (66%) in 2006-07]. There was also a decrease in the percentage of projects using innovative technologies exclusively [19/51 projects (48%) vs. 26/40 projects (65%) in 2006-07]. As in 2006-07, bioremediation was the most often implemented non-conventional technology in 2007-08.

Transport Canada: Bushell Public Port Facility Remediation

The Bushell Public Port Facility (PPF) was built in 1951, on the southeastern shore of Black Bay on Lake Athabasca in Saskatchewan, and was used until the mid-1980s to supply various goods and services to local mines as well as petroleum products to the communities of Bushell and Uranium City. As the mines closed and Bushell and Uranium City shrank in size, marine activity at the Bushell facility decreased to the occasional barge.

Over the years, the storage, unloading and loading of bunker C fuel oil at the facility resulted in oil contaminated soil, blast rock, bedrock and some sediment impacts in Black Bay. Following numerous assessments, EC's Pacific Region Environmental Services led the development of a Remedial Action Plan in early 2005 to address the remaining contamination. The Plan called for the excavation of the oil soaked blast rock and contaminated soil. Where oil had impregnated the bedrock within cracks and fissures, the bedrock was to be blasted and removed. The excavated contaminated soil, blast rock and bedrock were to be crushed in preparation for treatment by low-temperature thermal desorption, a process where the contaminated media would be put through an incinerator to burn off the oil residue. This method was chosen due to the costs and difficulty of other treatment strategies given the remote northern location of the facility.

When tendering the remediation contract in early 2005, a sustainable development component was incorporated, resulting in an alternative remedial option being revealed during the bid process. A local contractor was aware of Saskatchewan Highways' plan to resurface the Uranium City Airport runway within the next few years, and proposed the opportunity to recycle the oil contaminated rock and soil from the Bushell facility for use in the runway project. Given that Saskatchewan Highways would be quarrying and crushing new material and then applying oil to the crush in preparation for sealing the runway, this was considered a win-win opportunity. Saskatchewan Highways was contacted and an agreement was reached where Transport Canada would crush and mix the contaminated soil and rock to meet the required specification for the runway resurfacing, then transport it to the airport where Saskatchewan Highways would take ownership of the material. Cost savings of this option are $1,750,000 compared to the original plan for incineration. Cost savings for Saskatchewan Highways are expected in the order of $1,000,000. Considering the fuel savings, primarily from the incineration process that would have required nearly 1 000 000 litres of diesel fuel, this solution realizes a reduction in greenhouse gas emissions of approximately 2600 tonnes.

Transport Canada also signed an agreement with the Saskatchewan Research Council in order to transfer aggregate to them in its reclamation of the Cold War Legacy Uranium Mine and Mill Sites.

Transport Canada: Bushell Public Port Facility Remediation

Penhold Transmitter Bunker - PWGSC Western Region

This is a former cold war-era communications bunker site located in farmland in southern Alberta. During the decommissioning of the bunker in 2001, petroleum hydrocarbon (PHC)-impacted soils were discovered both under the bunker and alongside the structure. Since there is no documentation indicating management of fuel at the military site, it is difficult to determine the time frame and the quantity of fuel released into the environment.

Multiple investigative programs were undertaken to complete delineation and to determine the best option for remediation of the soils. Due to the large amount of overburden materials that were not impacted, the cost of removal of the clean soil to access the contamination was prohibitive. A multi-phase extraction system was selected as the best way to remove the PHC product from the groundwater matrix and was installed at the site in 2004. This contract included hydraulic ground fracturing, installation of recovery wells and networks, and the supply and operation of a multi-phase recovery system to treat groundwater.

The system consists of six recovery wells installed 6 to 9 metres below surface, connected to two recovery networks. The recovery wells consist of 50-mm diameter PVC pipes, perforated with sand packs in the active zone. The infiltration gallery for return of treated groundwater consists of a trench 20 m long by 4 m deep, excavated and backfilled with pea gravel, located approximately 20 m up-gradient of the plume. Two summer networks were added in April 2006 to enhance the system, and these additional networks vastly improved productivity of removal of product within the groundwater matrix.

The custom multi-phase extraction system consists of a steel container unit divided by a firewall into a small control room and a larger process room. The control room houses the electrical power and control components and the air compressor, and the process room contains the treatment components, including liquid ring pump, vapour-liquid separator, in-line filter, oil-water separators, and carbon vessels for water treatment. The process room electrical equipment is equipped with explosion-proof components.

Fluid, vapour and air from the recovery wells are drawn into the network pipes and to the system by the liquid ring pump, and into the liquid-vapour separator. The vapour phase is discharged to the atmosphere. The liquid phase, consisting mainly of groundwater with diesel, is pumped to an oil-water separator. Floating product is skimmed off and transferred to two storage containers located in a lined area adjacent to the unit. The groundwater is then polished through two activated carbon vessels, and returned to the ground via the infiltration trench.

Between June 2004 and December 2008, over 4700 litres of diesel fuel have been successfully recovered from the groundwater through the system. Recovery rates have significantly dropped over the past year, however, and alternative remediation methods are now being considered to deal with the remaining PHCs in sub-surface soils.

Penhold Transmitter Bunker - PWGSC Western Region

3.1.3 Federal Brownfields

For purposes of FCSAP, a federal brownfield is defined as an idle or underused property for which the Government of Canada has accepted all or partial responsibility for past environmental contamination, and that exhibits good potential for other uses (or upgrading) and/or provides viable social/economic opportunities. Brownfields are typically located in established areas, where existing municipal services are readily available, or along transportation corridors. In 2007-08, 22 projects identified the potential for one or more sites to be federal brownfields. Redevelopment plans, such as divestiture (4 project locations) or redevelopment by the federal government (2 project locations), were identified for 6 of the 22 projects.

The scope of FCSAP presents an opportunity for custodians to redevelop brownfields that are part of their real property portfolio. In 2005-06, PWGSC initiated the development of a brownfields classification tool to assist custodians in identifying candidate brownfield redevelopment sites. In 2006-07, PWGSC conducted several consultations with federal custodians and other levels of government in order to create a preliminary brownfields classification tool for the purposes of identifying, classifying, prioritizing and preparing brownfields sites, from the perspective of program planning and divestiture. In order to assist in the development of individual business cases, further refinement of this tool was scheduled for 2007-08. Trials of the tool were conducted using the PWGSC Real Property Inventory database and the TBS Directory of Federal Real Property. The Brownfields Portfolio Classification Tool has been refined in consultation with custodians, based on these initial trials.

4.0 2007-08 Program Achievements: Program Administration

4.1 Expert Support and Secretariat Funding

In 2007-08, a total of $18,179,932 was approved for Secretariat and Expert Support Services. Of this amount, $14,995,312 was spent and $3,184,620 was lapsed. The expenditure breakdown is provided in Table 7.

Table 7: Summary of FCSAP Program Management Expenditures for Secretariat and Expert Support Services (2007-08)
  Secretariat and Expert Support Services
Planned
FCSAP
Expenditures
($)
Adjustment Actual
FCSAP
Expenditures
Variance ($)
(approved +
adjustment -
expenditure)

* Additional internal funds totalling approximately $780,000 were allocated by Health Canada to augment FCSAP Expert Support resources

Environment Canada Secretariat/Expert Support 6,640,276   4,067,566 2,572,710
Treasury Board of Canada Secretariat 481,363   429,184 52,179
Health Canada Expert Support* 6,772,656   7,502,223 -779,567
Public Works and Government Services Canada 1,000,000   780,810 219,190
Department of Fisheries and Oceans Expert Support 3,335,637   2,215,529 1,120,108
Total Expenditures 18,179,932 0 14,995,312 3,184,620

The main factor contributing to the variance (as identified by the expert support departments and the Secretariat) was the inability to staff the vacant positions funded by the Program. A lower than expected number of staff for expert support and the Secretariat functions created the inability to spend significant portions of operational funds.

4.2 Key Activities in 2007-08

4.2.1 Federal Contaminated Sites Action Plan Secretariat

In 2007-08, the FCSAP Secretariat undertook the following work:

  • Developed and co-ordinated the fall 2007 project submission and 2006-07 reporting processes, including the development and delivery of bilingual training to all custodians.
  • Screened and analyzed funding proposals for eligibility, and developed funding options for committee approval and inclusion in the 2008 annual TB Submission.
  • Developed and co-ordinated multi-departmental approval of the 2007 TB Submission and commenced the development of the 2008 TB Submission.
  • Assisted with the completion of the FCSAP Formative Evaluation Plan, in co operation with EC's Evaluation group.
  • Maintained and upgraded the Interdepartmental Data Exchange Application (IDEA) for the 2007 project submission process and 2007-2008 reporting module.
  • Prepared ministerial dockets and communication materials for ministerial announcement, in co-operation with the FCSAP communications group.
  • Provided ongoing secretariat support to the CSMWG and the Federal Contaminated Sites ADM Steering committee; co-chaired monthly CSMWG meetings and organized tri-annual ADM Steering committee meetings.
  • Completed, in co-operation with TBS, the draft fiscal year 2004-2005 and fiscal year 2005-2006 annual reports.
  • Co-ordinated departmental review and sign-off of the Auditor General's follow-up report on federal contaminated sites released in March 2008.
  • Co-ordinated the "train the trainer" session on the Canada-Wide Standard for Petroleum Hydrocarbons in soils: participants from EC Regions and HQ and from other expert support departments attended the day-and-a-half course that took place in Gatineau, Quebec.
  • In consultation with TBS, assisted EC Communications with the development and approval of a FCSAP Web portal that provides general information about the program and about activities on federal contaminated sites.
  • Updated the FCSAP guidance documents (Handbook, eligible costs document, FCSAP classification, Ecological Risk Evaluation 1 & 2) to assist custodians in understanding FCSAP requirements.

4.2.2 Treasury Board Secretariat

In 2007-08, the Real Property and Materiel Policy Division of TBS undertook the following work related to FCSAP:

  • Supported the FCSAP Secretariat in program development activities, including the preparation of funding approval documentation, preliminary work on the Program risk profile and key performance indicators, and annual reporting.
  • Assisted EC in the development of an Evaluation Plan for the FCSAP Formative Program Evaluation.
  • Co-ordinated the TBS response to the Auditor General's follow-up audit on contaminated sites, tabled in March 2008.
  • Chaired and co-ordinated planning for the 2008 Federal Contaminated Sites National Workshop, held in Vancouver, British Columbia, from April 28 to May 1, 2008. The workshop brought together more than 500 federal managers, remediation specialists and industry representatives from across the country, to learn about technical, scientific and organizational innovations and best practices for the management of federal contaminated sites.
  • Administered the Federal Contaminated Sites Inventory, monitored custodian reporting and data quality, and supported ongoing system improvements through creation of an interdepartmental working group.
  • Participated in interdepartmental working groups and contributed to the development and refinement of program guidance material.
  • Developed guidance for the preparation of contaminated sites management plans and reviewed annual submissions.
  • Elaborated content for the FCSAP Web portal.

4.2.3 Expert Support Departments

In 2007-08, much of the work of expert support departments focused on the development and delivery of guidance documents and training, the provision of advice, third-party review, and the promotion of innovative technologies:

  • DFO created internal inter-regional working groups (training, reporting, communications, tools, and capacity building) to track progress and help deliver Program management tools, including a draft training plan, improvements to the reporting process, information management (update the Program Activity Tracking System (PATH) DFO Expert Support data archive and retrieval tool), the final draft of the Expert Support handbook, the annual report, and major changes to DFO's reporting mechanisms (revisions to DFO Expert Support mid-year and annual reporting templates for management of funds allocated to regions).
  • DFO focused on the development, improvement and application of science-based risk assessment tools within DFO and in conjunction with HC and EC.
  • EC promoted the use of widely accepted and standardized approaches to ecological risk assessment from the CCME and U.S. Environmental Protection Agency. EC also initiated the development of supplemental guidance for ecological risk assessment based on the existing CCME framework (CCME, 1996, 1997). This guidance, which comprises 13 technical modules, will provide custodians of federal contaminated sites with nationally consistent advice with respect to ecological risk assessment and risk management of their sites.
  • EC, through its Atlantic Region, chaired a task group to update/upgrade the ecological risk assessment component of the Atlantic risk-based tool. In addition, this region continued to develop a regional background soil database and is partnering with the North American Soil Geochemical Landscape Project, a tri-national initiative led in Canada by Natural Resources Canada (NRCan) to collaborate on sampling efforts and share data sets.
  • EC provided expert support advice to custodians, including DFO, other units of EC, PC, INAC, DND and PWGSC, on the best practices and management options for the remediation and risk management of federal contaminated sites.
  • EC performed reviews of site classification and assessment reports and of the ecological risk evaluations (Ecological Risk Evaluation 1 and 2) and conducted site visits for projects in the regions.
  • EC provided custodians with training and access to the advice of expert support departments on compliance, health and ecological risks/impacts of contaminated sites and risk-assessment approaches, as well as advice on the development of remediation / risk management plans for their sites through the facilitation of Interdepartmental Regional Working Groups.
  • HC peer reviewed risk assessment reports regarding 44 federal contaminated sites , in order to assist custodians and the Secretariat with the consistent determination of risks posed by federal contaminated sites across Canada, and as part of the FCSAP funding application process.
  • HC continued work on the development and advancement of human health based soil quality guidelines and toxicological reference values for several chemicals that are typically found at federal contaminated sites across Canada.
  • HC continued work on developing and updating the series of human health risk assessment guidance documents for use at federal contaminated sites, to allow for a standardized and consistent approach in assessing and quantifying the risks to human health posed by contaminants present on federal sites across Canada.
  • HC provided training to the various FCSAP stakeholders in human health risk assessment and in the areas of public involvement and risk communication. This training resulted in considerable advancement in the custodians' knowledge and understanding of these areas.
  • HC, EC and DFO conducted site visits to gain further understanding of the unique situations at many sites and to enable the departments to provide better guidance and advice relating to activities at contaminated sites. HC, EC and DFO also provided custodians with advice regarding risk assessments, site classifications, regulations, remedial plans, and technical requirements.
  • PWGSC prepared four project management tools (Quality Management, Integration Management, Communication Management, and Risk Management) to assist custodians in better managing their contaminated sites projects. PWGSC also developed a training session for each of these project management tools. Training sessions related to these tools were presented in Ottawa, Québec, Montréal, Toronto and Calgary.
  • PWGSC collected and communicated results of projects that employed innovative technologies, and shared best practices with other federal custodians, other levels of government, and the environment industry, by participating in interdepartmental regional workgroups, organizing the Innovative Remediation Solutions workshop held in Montréal in November 2007, participating in the Interdepartmental Technology Advancement Working Group, and developing the Guidance and Orientation for the Selection of Technologies database.
  • PWGSC developed the Demand Forecast Analysis to share information with the private sector regarding the anticipated federal contaminated sites projects for which private sector assistance would be required to enable implementation.

Detailed information on the activities carried out by the four expert support departments (DFO, EC, HC and PWGSC) during the fiscal year can be obtained by contacting the specific expert support department directly:

  • DFO - Expert Support Federal Contaminated Sites, Habitat Program Services Branch, Habitat Management, Oceans Sector, Fisheries and Oceans Canada, 200 Kent Street, Ottawa ON K1A 0E6.
  • EC - Contaminated Sites Division, Environmental Protection Operations Directorate, Environment Canada, 351 St. Joseph Blvd, 15th Floor, Gatineau QC K1A 0H3.
  • HC - Contaminated Sites Division, Bureau of Risk and Impact Assessment, Safe Environments Program, Healthy Environments and Consumer Safety Branch, Health Canada, 269 Laurier Avenue West, Ottawa ON K1A 0K9.
  • PWGSC - National Manager, Contaminated Sites, Environmental Services Directorate, Public Works and Government Services Canada, 11 Laurier Avenue, Gatineau QC K1A 0S5.

5.0 Federal Contaminated Sites Financial Liability

Each year, financial information, including the overall environmental liability and contingent liability for federal contaminated sites, is reported to the Public Accounts of Canada. In the Public Accounts, total environmental liability includes the estimated costs for the management and remediation of contaminated sites and unexploded explosive ordnance-affected sites, as well as the estimated costs for decommissioning Atomic Energy of Canada Limited's nuclear facilities. For contaminated sites, a liability is accrued and an expense is recorded when the contamination occurs or when the Government becomes aware of the contamination and is obligated, or is likely obligated, to incur such costs. A contingent liability is recorded when the Government's obligation to incur these costs is unknown or unlikely, or if the amount cannot be reasonably estimated.19

The requirements for recording environmental liabilities can be found in the Treasury Board Policy on Accounting for Costs and Liabilities Related to Contaminated Sites (www.tbs-sct.gc.ca/pol/doc-eng.aspx?id=12152). Additional guidance is contained in the Treasury Board Guidance on Accounting for Environmental Liabilities (www.tbs-sct.gc.ca/rpm-gbi/doc/liabilities-passifs/liabilities-passifs-eng.aspx). As indicated in these documents, the environmental liability recorded for contaminated sites reflects the estimated cost of site remediation to a level appropriate to the land's current or intended federal use. Costs include any estimated expenses related to the remediation and management of federal sites associated with steps 5 to 10 of the Ten Step Process, for sites identified as a Class 1, Class 2 or, in limited cases, Class I (insufficient information) under the CCME classification. As noted in Guidance on Accounting for Environmental Liabilities, Class I sites may have a liability recorded when the federal custodian has sufficient information to determine that the Government is likely obligated to remediate the site but there are insufficient data to generate a classification under the CCME National Classification System. When a custodian intends to perform the remediation itself, the liability may include estimated project management costs. The liability amount excludes any expenses associated with determining the existence of contamination (i.e., steps 1 to 4 of the Ten Step Process), overhead costs, and project management costs internal to the custodian. This means that the costs associated with assessment (steps 1 to 4) and with care and maintenance activities are not included in the liability calculation, as they are undertaken to determine the existence and extent of contamination (assessment) or to mitigate the spread of contamination when the danger to human health or the environment is imminent (care and maintenance).

The 2007-08 Public Accounts show an increase in the accrued liability related to the management and remediation of federal contaminated sites. As of March 31, 2008, a liability of $3.332 billion was recorded for approximately 2360 contaminated sites, compared with a liability of $3.014 billion for 2630 sites in 2007.20 For a number of reasons, not all of the contaminated sites that are included in the Public Accounts' liability totals are eligible for, or have received, funding under FCSAP. Therefore, in order to obtain a more accurate picture of the impact that FCSAP has had on liability, exceptional sites such as the Sydney Tar Ponds and Port Hope Area Initiative are removed from the total. In addition, the liability amounts were excluded for federal custodians with contaminated sites that do not participate in FCSAP. As demonstrated in Table 8, once these amounts are removed from the total liability recorded in the Public Accounts for contaminated sites, there is a $306 million increase in liability during the period of March 31, 2007, to March 31, 2008. The majority (95%) of the net increase is attributed to an increase in the liability reported for three custodians-INAC, DND and DFO. This increase in federal environmental liability is primarily attributed to changes recorded to planned cost estimates for remediation activities of large projects. It is also attributed to the fact that increased spending on assessment activities results in a more accurate estimate of liability, often leading to an increase. Continued work on all types of FCSAP projects will result in further refinement of liability estimates, and total liability is expected to decline as sites are remediated.

Table 8: Adjusted Total Environmental Liability for Contaminated Sites (2007-08)
 

March 31, 2007 ($)

March 31, 2008 ($)

Total contaminated sites liability21

6,061,913,899

6,668,721,493

Less:

   

Unexploded explosive ordnance affected sites (Department of National Defence)

119,143,584

327,757,635

Atomic Energy of Canada Limited's nuclear facility decommissioning

2,927,934,000

3,008,236,000

Sydney Tar Ponds22

280,817,000

271,425,194

Port Hope Area Initiative23

387,173,243

335,373,318

Cape Breton Development Corporation24

108,857,000

180,338,000

VIA Rail Canada Inc.

 

1,500,000

Industry Canada

132,281

99,657

National Research Council of Canada

300,000

100,000

Adjusted total contaminated sites liability

2,237,556,791

2,543,891,689

The information in Table 9 shows liability for contaminated sites as reported in the 2007-08 Public Accounts.

Table 9: Federal Custodians Participating in FCSAP - Environmental Liability for Contaminated Sites

Custodian

Opening Liability
April 1, 2007 ($)

Closing Liability
March 31, 2008 ($)

Difference

Agriculture and Agri-Food Canada

1,779,574

1,925,334

145,760

Canada Border Services Agency

867,400

769,165

(98,235)

Correctional Service of Canada

13,775,571

14,354,720

579,149

Environment Canada

63,266,228

55,520,174

(7,746,054)

Fisheries and Oceans Canada

169,196,803

223,544,198

54,347,395

Health Canada

3,197,100

2,303,800

(893,300)

Indian and Northern Affairs Canada

1,313,856,272

1,497,136,925

183,280,653

The Jacques Cartier and Champlain Bridges Inc.

1,000,000

1,000,000

0

National Capital Commission

21,794,000

24,799,000

3,005,000

Department of National Defence

378,272,040

431,514,508

53,242,468

Natural Resources Canada24

387,792,662

336,678,572

(51,114,090)

Parks Canada Agency

40,027,640

42,017,836

1,990,196

Public Works and Government Services Canada25

320,154,947

310,523,035

(9,631,912)

Royal Canadian Mounted Police

3,752,007

4,275,715

523,708

Transport Canada

186,814,790

204,327,220

17,512,430

Total

2,905,547,034

3,150,690,202

245,143,168

6.0 Measuring Performance and Looking Forward

In its third year of operation, FCSAP's key achievements included the development and enhancement of program policies and procedures, and further development of guidance material and training for federal custodians. Work was carried out to address the key program activity objectives of FCSAP, including reducing the number of high-risk sites, reducing human and ecological risks and financial liabilities, and increasing public confidence in the management of federal contaminated sites.

FCSAP spent $188.4 million on federal contaminated sites projects, program management, Secretariat/expert support services, and PWGSC accommodation costs, with the most significant proportion of the money allocated to the execution of assessment and remediation / risk management projects. Of the total amount budgeted for project expenditures ($217.7 million), $165.4 million was spent, representing an increase of approximately $2.5 million from the previous fiscal year. As a result of the amounts spent in 2007-08, activities were undertaken at 276 remediation / risk management projects (consisting of 519 sites) and 590 assessment projects (consisting of 2269 sites) across Canada.

As of March 31, 2008, a liability of $3.332 billion was recorded for approximately 2360 contaminated sites, compared with a liability of $3.014 billion for 2630 sites in 2007.26 This increase in federal environmental liability is primarily attributed to changes recorded to planned cost estimates for remediation activities of large projects. It is also attributed to the fact that increased spending on assessment activities results in a more accurate estimate of liability, often leading to an increase. Continued work on all types of FCSAP projects will result in further refinement of liability estimates, and total liability is expected to decline as sites are remediated.

Finally, in March 2008, the Office of the Auditor General of Canada (OAG) tabled a Status Report on the progress the federal government had made with respect to the management of federal contaminated sites. For this status report, the OAG assessed the progress that four departments - Fisheries and Oceans Canada, Indian and Northern Affairs Canada, National Defence, and Transport Canada - made in addressing select findings and recommendations from the 2002 Audit Report. These four departments were selected for examination because they are collectively responsible for approximately 89 percent of the contaminated sites under federal responsibility. The Report also assessed the actions of Environment Canada and the Treasury Board of Canada Secretariat in providing central leadership to deal with priority contaminated sites, and what the federal government did to determine and report the costs of dealing with these sites.

The OAG Status report concluded that the government has made satisfactory progress in managing its contaminated sites by initially allocating approximately $1.5 billion over five years as a first installment of its $3.5 billion budgetary announcement and by developing the FCSAP. The OAG found that the four audited departments are putting significant effort into managing their contaminated sites. They had remediated about 340 sites, and about 480 others were undergoing remediation. All four departments had developed management plans that include some time-bound commitments for dealing with their contaminated sites in order to meet the program's objective of reducing the risk they pose to human health and the environment.

Appendix 1: Evaluation of Human Health and Ecological Risks at Federal Contaminated Sites

To assist federal custodians in the evaluation of human health and environmental risks at federal contaminated sites, two key analytical tools were developed under the 2003-2005 Accelerated Action Plan and refined under FCSAP: (A) HC's Human Health Preliminary Quantitative Risk Assessment tool and (B) EC's Ecological Risk Evaluation framework.

The purpose of each tool is to define the level of risk posed by a contaminated site, based on the following three evaluation criteria and their relationship to contaminant movement between source and receptor (human or ecological):

  1. Contaminant characteristics - the relative hazard of contaminants present at a site
  2. Exposure pathways - the route a contaminant may follow (e.g., groundwater, surface water, direct contact, and/or air) to a receptor
  3. Receptors - living beings or resources that may be exposed to and affected by contamination (e.g., humans, plants, animals, or environmental resources)

Evaluation of Human Health and Ecological Risks at Federal Contaminated Sites

(Description of the above image)

To create an accurate representation of the complex source-receptor pathway, multiple sources of information are required. As such, analytical factors can include, but are not limited to, any of the following considerations:

  • Description of the site location
  • Type of contaminants or materials likely to be present at site (and/or description of historical activities)
  • Approximate size of site and quantity of contaminants
  • Approximate depth of water table
  • Geologic map or survey information (soil, overburden, and bedrock information)
  • Annual rainfall data (can be inferred from rainfall map of Canada)
  • Surface-cover information
  • Proximity to surface water
  • Topographic information
  • Flood potential of site
  • Proximity of drinking water supply
  • Uses of adjacent water resources
  • Land use information (on site and surrounding) 27

(A) Human Health Preliminary Quantitative Risk Assessment

In the preliminary quantitative risk assessment for a federal contaminated site, the following factors are considered:

  • historical information to identify previous site uses and the possible contaminants to be investigated in soil and groundwater;
  • identification of contaminants of concern by comparing measured concentrations to regulatory guidelines;
  • identification of potential human exposure, which will vary depending on land use and the accessibility of the site;
  • examination of contaminant exposure pathways, i.e., the ways in which the individuals will contact the contaminant (ingestion, inhalation, dermal contact), and an estimation of the movement of contaminants in the environment.

Overall, Health Canada's Preliminary Quantitative Risk Assessment tool uses prescribed methods and assumptions, standard exposure pathways, human characteristics, and levels of toxicity in order to ensure that exposures and risk are not underestimated. When combined with site-specific information, the model helps in the assessment of toxicity and hazards associated with exposure to various chemicals.

For more details on the Preliminary Quantitative Risk Assessment, visit HC's website at http://hc-sc.gc.ca/ewh-semt/pubs/contamsite/index_e.html.

(B) Ecological Risk Evaluation

The Ecological Risk Evaluation framework was developed by EC as a tool to enable objective, transparent analysis of the ecological risks associated with individual federal contaminated sites.

More specifically, the framework assesses contaminated sites to determine the following:

  • if the contaminated area is affecting or has the potential to affect specific habitat(s);
  • the types of chemicals found at the site and the degree to which individual chemicals exceed environmental guidelines;
  • how the chemical(s) are finding their way into the environment;
  • any physical (non-chemical) impacts or hazards that may affect the quality of the environment or pose a risk to humans or wildlife.

Appendix 2: Provincial/Territorial and Custodial Distribution of Remediation / Risk Management Projects by Expected Completion Cost (2007-08)

a) Provincial/Territorial Distribution of Remediation / Risk Management Projects and Sites by Expected Completion Cost (2007-08)

Province/territory

≤$250,000

>$250,000 to
≤$1,000,000

>$1,000,000 to
≤$10,000,000

>$10,000,000

Total

Number of projects

Number of sites

Number of projects

Number of sites

Number of projects

Number of sites

Number of projects

Number of sites

Number of projects

Number of sites

Alberta

2

2

-

-

2

2

1

6

5

10

British Columbia

38

183

14

28

16

18

4

4

72

233

Manitoba

5

5

3

3

7

7

-

-

15

15

New Brunswick

7

7

1

1

1

1

-

-

9

9

Newfoundland and Labrador

2

2

2

2

6

7

1

41

11

52

Nova Scotia

21

24

3

6

5

6

-

-

29

36

Northwest Territories

-

-

1

1

5

5

8

11

14

17

Nunavut

2

4

2

3

4

4

20

20

28

31

Ontario

14

17

4

6

9

23

1

2

28

48

Prince Edward Island

7

7

-

-

-

-

-

-

7

7

Quebec

30

38

12

26

3

6

1

1

46

71

Saskatchewan

3

80

1

1

1

1

-

-

5

82

Yukon Territory

2

2

-

-

1

1

4

4

7

7

Total

133

371

43

77

60

81

40

89

276

618

b) Custodial Distribution of Remediation / Risk Management Projects and Sites by Custodian by Expected Completion Cost (2007-08)

Custodian

≤ $250,000

>$250,000 to ≤$1,000,000

>$1,000,000 to ≤$10,000,000

>$10,000,000

Total

Number of projects

Number of sites

Number of projects

Number of sites

Number of projects

Number of sites

Number of projects

Number of sites

Number of projects

Number of sites

Agriculture and Agri-Food Canada

-

-

-

-

1

1

-

-

1

1

Canada Border Services Agency

1

1

-

-

1

1

-

-

2

2

Correctional Service of Canada

-

0

-

-

1

1

-

-

1

1

Fisheries and Oceans Canada

88

98

14

42

-

-

1

2

103

142

Environment Canada

3

224

-

-

-

-

1

1

4

225

Health Canada

4

4

-

-

3

3

-

-

7

7

Indian and Northern Affairs Canada (Indian and Inuit Affairs Business Line)

 

 

 

 

 

 

 

 

 

 

  IIABL

9

9

8

8

14

28

-

-

31

45

  NAO

-

-

-

-

7

7

19

22

26

29

National Capital Commision

1

1

-

-

1

1

-

-

2

2

Department of National Defence

13

13

8

12

14

21

17

62

52

108

Parks Canada Agency

6

8

2

2

1

1

-

-

9

11

Public Works and Government Services Canada

3

5

3

5

9

9

-

-

15

19

Royal Canadian Mounted Police

4

4

5

5

-

-

-

-

9

9

Transport Canada

1

4

3

3

8

8

2

2

14

17

Total

133

371

43

77

60

81

40

89

276

618

Appendix 3: Expenditure Tables

a: Program Expenditures

  Planned FCSAP Expenditures Adjustments Actual FCSAP Expenditures
1 Funding brought forward from previous fiscal years
2 Funding brought forward from previous fiscal years. Total does not include $230,000 that was transferred to Parks Canada
3 Funds received from the DFO Expert Support
4 Custodian cost share owed to FCSAP from 2006-07
5 Total adjustments include $230,000 transferred from the INAC-IIABL
6 $2,964,000 of remediation/risk management funds were returned to the fiscal framework
7 Additional funds totalling approximately $780,000 were allocated by Health Canada to augment FCSAP Expert Support resourcces
Federal Contaminated Sites Projects      
Indian and Northern Affairs Canada (INAC)      
  Northern Affairs Organizations 97,657,635 3,133,3221 76,468,365
  Indian and Innuit Affairs Business Line 12,531,245 1,216,2382 9,917,646
Total INAC 110,188,880 4,349,560 86,386,011
Agriculture and Agri-Food Canada 1,296,000   1,008,400
Canada Border Services Agency 341,360   327,098
Correctional Service Canada 180,000 910,0071 1,349
Environment Canada 9,340,559   3,331,006
Department of Fisheries and Oceans 14,656,584 1,503,2601 7,697,967
    712,2693  
Health Canada 1,167,200 143,1664 578,585
Jacques Cartier and Champlain Bridges Incorporated 92,000   0
National Capital Commission 800,800 8701 758,633
Department of National Defence 56,314,473   48,134,620
Natural Resources Canada 128,000 47,8101 35,428
Parks Agency Canada 2,085,324 851,8735 2,347,896
Public Works and Government Services Canada 3,996,225   2,978,822
Royal Canadian Mounted Police 5,033,600   2,932,734
Transport Canada 12,068,948 2,964,0006 8,844,435
    -2,964,0006  
Total Project Expenditures 217,689,953 8,518,815 165,362,984
       
Program Management      
Agriculture and Agri-Food Canada 150,000 30,0001 120,000
Correctional Service Canada 67,670   67,670
Environment Canada 467,958   467,958
Department of Fisheries and Oceans 1,033,315 22,7313 894,046
Health Canada 121,429   121,429
Indian and Northern Affairs Canada (INAC)      
  Indian and Inuit Affairs Business Line 735,035   735,035
  Northern Affairs Organization 2,213,980   2,293,652
Department of National Defence 1,200,000   660,849
Natural Resources 150,000   0
Parks Canada Agency 366,713 418,4211 367,414
Public Works and Government Services 200,000   191,829
Royal Canadian Mounted Police 395,500   340,434
Transport Canada 451,000   451,000
Total Program Management Expenditures 7,552,600 471,152 6,711,316
       
Secretariat and Expert Support Services      
Environment Canada (EC)      
  EC Secretariat 3,465,995   1,855,534
  EC Expert Support 3,174,281   2,212,031
Total EC Secretariat/Expert Support 6,640,276   4,067,566
Treasury Board of Canada Secretariat 481,363   429,184
Health Canada Expert Support 6,722,656   7,502,223
Public Works and Government Services 1,000,000   780,810
Department of Fisheries and Oceans Expert Support 3,335,637   2,215,529
Total Secretariat and Expert Support Expenditures 18,179,932 0 14,995,312
       
PWGSC Accommodation costs 1,367,467   1,367,467
       
Total FCSAP Expenditures 244,789,952 8,989,967 188,437,079

b) Detailed FSCAP and Custodian Expenditures

Federal Contaminated Sites Projects Planned FCSAP Funding Adjustmentsa Actual FCSAP Expenditures FCSAP Variance(planned + adjustments - actual)
FCSAP Fund Custodian Share FCSAP Fund Custodian Share
a Adjustments include the transfer of funds from the previous fiscal year, and FCSAP funds not requested
b FCSAP funds transferred from the previous fiscal year
c Total includes $882,086 of remediation/risk management funds transferred from the previous fiscal year
d FCSAP funds received from another Custodian
e Total includes $621,873 of remediation/risk management funds transferred from the previous fiscal year
Agriculture and Agri-Food Canada            
ATL-1 Kentville Central Heating Plant (NS) 500,000 100,000   562,503 140,626 -62,503
Assessment (21 Projects) 796,000 159,200   445,897 111,474 350,103
Total AAFC 1,296,000 259,200   1,008,400 252,100 287,600
             
Canada Border Services Agency            
Pleasant Camp Border Crossing (BC) 181,360 36,272   181,360 45,912 0
West Poplar (SK) 160,000 32,000   145,738 36,434 14,262
Assessment 0 0       0
Total CBSA 341,360 68,272   327,098 82,346 14,262
             
Correctional Service Canada            
Atlantic Fuel Spill Site, 231-C02 (NB) 120,000 24,000   1,349 337 118,651
Bowden Fuel Depot Site 537-C02 (AB) 60,000 12,000   0 0 60,000
Assessment 0 0 27,921 b 0 0 27,921
Total CSC 180,000 36,000 910,007 c 1349 337 1,088,658
             
Department of Fisheries and Oceans (DFO)            
Active Pass (BC) 8,595 1,719   6,542 1,635 2,053
Addenbroke Island (BC) 8,595 1,719   6,542 1,635 2,053
Baccaro Point (NS) 80,000 16,000   75,265 18,816 4,735
Ballenas Island (BC) 8,619 1,724   6,542 1,635 2,077
Bear Point Small Craft Harbour (NS) 11,200 2,240   16,025 4,006 -4,825
Bear River (NS) 80,000 16,000   47,057 11,764 32,943
Belleville Small Craft Harbour (ON) 6,802,022 1,360,404   464,683 116,171 6,337,339
Berthier (QC) 8,000 1,600   6,000 1,500 2,000
Betty Island (NS) 0 0   12,000 3,000 -12,000
Boat Bluff (BC) 8,619 1,724   6,542 1,635 2,077
Bonilla Island Sector (BC) 8,619 1,724   6,542 1,635 2,077
Camp Cove Small Craft Harbour (NS) 40,000 8,000   92,864 23,216 -52,864
Cap d'Espoir (QC) 0 0   217,781 54,445 -217,781
Cap Gaspé (QC) 0 0   146,588 36,647 -146,588
Cap Chat (QC) 0 0   7,378 1,844 -7,378
Cap de la Madeleine (QC) 0 0   7,378 1,844 -7,378
Cap-des-Rosiers (QC) 0 0   55,404 13,851 -55,404
Cap-Saint-Ignace, ancien amer (QC) 64,000 12,800   2,672 668 61,328
Cape Beale (BC) 8,619 1,724   6,542 1,635 2,077
Cape Bear (PE) 0 0   10,400 2,610 -10,400
Cape d'Or (NS) 8,000 1,600   4,400 1,100 3,600
Cape Egmont (PE) 8,000 1,600   18,431 4,608 -10,431
Cape Mudge (BC) 8,595 1,719   6,542 1,635 2,053
Cape Scott (BC) 8,621 1,724   6,542 1,635 2,079
Cape St. Marys (NS) 80,000 16,000   29,497 7,374 50,503
Caribou Ferry Small Craft Harbour (NS) 11,600 2,320   0 0 11,600
Carmanah Point (BC) 8,619 1,724   6,524 1,635 2,077
Cascades-Soulanges (QC) 12,000 2,400   0 0 12,000
Caveau Point (NS) 8,000 1,600   0 0 8,000
Chatham Point (BC) 8,619 1,724   6,542 1,635 2,077
Chrome Island Range (BC) 8,619 1,724   6,542 1,635 2,077
Cultus Lake Laboratory (BC) 81,800 16,360   70,981 17,745 10,819
Discovery Island (BC) 8,619 1,724   6,542 1,635 2,077
Dixon Point Light (NB) 8,000 1,600   18,431 4,608 -10,431
Drews Head (NB) 0 0   12,634 3,159 -12,634
Dryad Point (BC) 8,619 1,724   6,542 1,635 2,077
Dublin Shore Small Craft Harbour (NS) 6,800 1,360   9,795 2,449 -2,995
East Point (PE) 64,000 12,800   0 0 64,000
Egg Island (BC) 8,619 1,724   6,542 1,635 2,077
Enrage Point (BC) 8,000 1,600   0 0 8,000
Entrance Island (BC) 8,619 1,724   6,542 1,635 2,077
Estevan Point (BC) 8,619 1,724   6,542 1,635 2,077
Fox Harbour Loran C (NL) 175,200 35,040   0 0 175,200
Gabarus (NS) 80,000 16,000   44,297 11,074 35,703
Gillis Point (NS) 80,000 16,000   53,097 13,274 26,903
Grand Bank Small Craft Harbour (NL) 36,000 7,200   19,626 4,907 16,374
Green Island (BC) 8,619 1,724   6,542 1,635 2,077
Howards Cove (PE) 0 0   15,897 3,974 -15,897
Île au Marteau (QC) 0 0   4,240 1,060 -4,240
Île aux Noix, ancien FP - 1 (QC) 0 0   1,110 278 -1,110
Île aux Noix, ancien FP - 2 (QC) 0 0   1,110 278 -1,110
Île Brion (QC) 40,000 8,000   0 0 40,000
Île du Corossol (QC) 32,000 6,400   12,185 3,046 19,815
Île Grosbois (ex-tour radar), ancien amer (QC) 0 0   10,258 2,564 -10,258
Île Sainte-Marie (QC) 24,000 4,800   33,913 8,478 -9,913
Institute of Ocean Sciences (and Victoria MCTS) (BC) 81,799 16,360   147,952 36,988 -66,153
Ivory Island (BC) 8,619 1,724   6,542 1,635 2,077
Kenora base (ON) 64,000 12,800   0 0 64,000
Killarney East (ON) 25,600 5,120   24,635 6,159 965
Killarney Northwest (ON) 28,000 5,600   52,188 13,047 -24,188
Killarney West Entrance (ON) 20,000 4,000   16,741 4,185 3,259
Knapp Point (ON) 40,000 8,000   171,167 42,792 -131,167
Lameque Small Craft Harbour (NB) 64,000 12,800   25,654 6,413 38,346
Langara Island (BC) 8,619 1,724   6,542 1,635 2,077
Lennard Island (BC) 8,619 1,724   6,542 1,635 2,077
Longue Pointe (QC) 8,000 1,600   11,396 2,849 -3,396
Low Point (NS) 40,000 8,000   59,497 14,874 -19,497
Maughers Beach (NS) 0 0   12,634 3,159 -12,634
McInnes Island (BC) 8,619 1,724   6,542 1,635 2,077
Melocheville (QC) 12,000 2,400   3,640 910 8,360
Merry Island (BC) 8,619 1,724   6,542 1,635 2,077
New Aiyansh Office & Residences- Nass Camp (BC) 166,400 33,280   5,641 1,410 160,759
Nine Mile Point (ON) 126,400 25,280   21,592 5,398 104,808
Nootka Island (BC) 8,619 1,724   6,542 1,635 2,077
North Cape (PE) 64,000 12,800   13,801 3,450 50,199
North Rustico Small Craft Harbour (PE) 6800 1360   3,535 884 3,265
Pachena Point (BC) 8,619 1,724   6,542 1,635 2,077
Pacific Biological Station Risk Management (BC) 81,799 16,360   144,249 36,062 -62,450
Partridge Island Light and DGPS Station (NB) 80,000 16,000   512,634 3,159 67,366
Percé (QC) 0 0   152,274 39,318 -157,274
Pine Island (BC) 8,619 1,724   6,542 1,635 2,077
Point Atkinson Lightstation Risk Management (BC) 8,000 1,600   6,542 1,635 1,458
Point Escuminac (NB) 0 0   18,431 4,608 -18,431
Pointe au Baril Lightstation (ON) 100,000 20,000   6,477 1,619 93,523
Pointe de l'Ouest (QC) 240,000 48,000   65,870 16,467 174,130
Pointe Dowker (QC) 12,000 2,400   5,510 1,377 6,490
Pointe du Débarquement, terrain pour héliport (QC) 0 0   5,826 1,456 -5,826
Pointe du Débarquement, terrain pour héliport - 2 (QC) 0 0   5,826 1,456 -5,826
Pointe Heath (QC) 240,000 48,000   3,768 942 236,232
Pointe-Noire (QC) 160,000 32,000   130,443 32,611 29,557
Port Bickerton (NS) 80,000 16,000   16,049 4,012 63,951
Portlock Point (BC) 8,618 1,724   6,542 1,635 2,076
Prim Point (NS) 0 0   164,049 41,012 -164,049
Prim Point (PEI) 64,000 12,800   27,442 6,860 36,558
Prince Rupert - Seal Cove Risk Management (BC) 81,802 16,360   164,298 41,075 -82,496
Prince Rupert Marine Station - Sourdough Bay Risk Management (BC) 81,802 16,360   149,383 37,346 -67,581
Pulteney Point (BC) 8,619 1,724   6,542 1,635 2,077
Quatsino (Kains Island) (BC) 8,619 1,724   6,542 1,635 2,077
Richibucto Head (NB) 0 0   5,874 1,469 -5,874
Rocher aux Oiseaux (QC) 40,000 8,000   43,283 10,821 -3,283
Sainte-Angèle-de-Laval (QC) 16,000 3,200   3,276 819 12,724
Sainte-Marthe-de-Gaspé (QC) 0 0   7,378 1,844 -7,378
Saturna Island Sector (BC) 8,621 1,724   6,542 1,635 2,079
Scarlett Point (BC) 8,619 1,724   6,542 1,635 2,077
Sea Island Hovercraft Base Risk Management (BC) 81,800 16,360   170,924 42,731 -89,124
Sheringham Point (BC) 8,619 1,724   6,542 1,635 2,077
Souris East (NS) 64,000 12,800   89,779 22,445 -25,779
Swallowtail (NB) 8,000 1,600   0 0 8,000
Terence Bay (NS) 0 0   12,634 3,159 -12,634
Trial Islands (BC) 8,619 1,724   6,542 1,635 2,077
Victoria Base Risk Management (BC) 57,798 11,560   35,604 8,901 22,194
West Vancouver Laboratory (BC) 81,800 16,360   124,296 31,074 -42,496
Wood Islands Light (PE) 64,000 12,800   0 0 64,000
Assessment (71 projects) 4,142,400 828,480 1,503,260 b 3,819,994 954,998 2,537,935
      712,269 c      
Total DFO 14,656,584 2,931,317 2,215,529 7,697,967 1,924,472 9,174,146
             
Department of National Defence (DND)            
14 Wing Greenwood NSLZB (NS) 540,000 108,000   808,053 202,013 -268,053
22 Wing Wood Hobby Club Site Remediation (ON) 52,000 10,400   24,127 6,032 27,873
5 Wing Goose Bay (NL) 4,000,000 0   3,315,444 0 684,556
ADMIE OPSEE Remediation (BC) 0 0   396,315 99,079 -396,315
ADMMAT BAF-3 POL Storage Facility (NU) 0 0   52,800 13,200 -52,800
ADMMAT FOX B SRR SUMMIT (S-493) (NU) 0 0   58,402 14,601 -58,402
Ancienne SFC Moisie - site Admin (QC) 420,000 84,000   252,009 63,002 167,991
Assainissement du site de l'ancien puit P-2 (QC) 120,000 24,000   39,200 9,800 80,800
ASU London Highbury Complex (ON) 80,000 16,000   28,981 7,245 51,019
ASU London Wolsley Barracks (ON) 56,000 11,200   30,109 7,527 25,891
BFC Valcartier - Perchlorate - eau souterraine (QC) 80,000 16,000   93,214 23,304 -13,214
Cadet Camp Landfill (ON) 0 0   42,917 10,729 -42,917
CAM-1 Jenny Lind Island DEW Line (NU) 3,136,000 627,200   2,473,850 618,463 662,150
CAM-2 Gladman Point DEW Line (NU) 36,000 3,600   94,316 10,480 -58,316
CAM-3 Shepherd Bay DEW Line (NU) 3,284,936 525,590   4,605,906 917,315 -1,320,970
CAM-4 Pelly Bay DEW Line (NU) 810,000 81,000   503,530 55,948 306,470
CAM-5 Mackar Inlet DEW Line (NU) 5,320,000 1,064,000   3,540,395 885,099 1,779,605
CFAD Bedford Dump Sites (CSites 801, 802, 803 & 820) Risk Mngmt (NS) 50,400 10,080   76,581 19,145 -26,181
CFAD Eastside Peninsula Area (CSite 7402) Remediation (NS) 68,000 13,600   87,881 21,970 -19,881
CFB Esquimalt DY-4 FMF Shops (BC) 800,000 160,000   0 0 800,000
CFB Trenton FFTA - (ON) 64,000 12,800   7,600 1,900 56,400
Colwood Aggregate (BC) 1,600,000 320,000   2,895,982 723,996 -1,295,982
DCD School CSite 909 Remediation (NS) 200,000 40,000   167,002 41,751 32,998
DYE-M Cape Dyer DEW Line (NU) 9,500,000 0   5,135,020 0 4,364,980
Former POL Storage Area, Naval Annex Dockyard (CSite 1107B) Risk (NS) 50,800 10,160   24,617 6,154 26,183
FOX-2 Longstaff Bluff DEW Line - (NU) 64,000 12,800   217,641 54,410 -153,641
FOX-3 Dewar Lakes DEW Line (NU) 200,000 40,000   354,677 88,669 -154,677
FOX-5 Broughton Island DEW Line (NU) 36,000 3,600   223,505 24,834 -187,505
FOX-M Hall Beach DEW Line (NU) 6,300,000 630,000   8,584,748 953,861 -2,284,748
Marlant Bedford Rifle Range (NS) 496,000 99,200   512,478 128,120 -16,478
Marlant Former Firefighter Training Area Site 907, DCD School (NS) 40,000 8,000   36,795 9,199 3,205
Marlant Great Village Former AST Remediation (NS) 40,000 8,000   30,677 7,669 9,323
METC Nicolet Building 5 - (QC) 112,000 22,400   79,686 19,922 32,314
METC Nicolet OP-6 - (QC) 48,000 9,600   14,484 3,621 33,516
NAD 1 - Jr. NCM (BC) 560,000 112,000   848,371 212,093 -288,371
PCB Amended Paint Removal Project (NU) 400,000 80,000   3,034 758 396,966
PIN-2 Cape Young DEW Line (NU) 64,000 12,800   62,860 15,715 1,140
PIN-3 Lady Franklin Point DEW Line (NU) 32,000 6,400   102,113 25,528 -70,113
PIN-4 Byron Bay DEW Line (NU) 3,776,000 755,200   1,979,982 494,995 1,796,018
RDDC Valcartier-Secteurs d'essais et Batiment 307 (QC) 80,000 16,000   332,842 83,211 -252,842
Remediation of PCB contaminated soil at BAF-3, Brevoot Island (NU) 0 0   27,740 6,935 -27,740
Restauration champ de tir 600 verges à St-Bruno (QC) 80,000 16,000   167,012 41,753 -87,012
Restauration du dépotoir à St-Bruno (QC) 60,000 12,000   31,354 7,839 28,646
Saglek Sediments (NL) 120,000 24,000   93,918 23,480 26,082
Shea Heights/Southside Tank Farm (NL) 640,000 128,000   727,251 181,813 -87,251
Shearwater (CSite 207) - Former USTs at Hangar 3 (NS) 4,000 800   4,000 1,000 0
Shearwater (CSite 230)-Buidlings 31,31A,31B,32 (Mobile support) (NS) 4,000 800   4,000 1,000 0
Shirley Road Dump/Landfill (NB) 40,000 8,000   36,802 9,201 3,198
Suffield EPG (AB) 800,000 160,000   328,356 82,089 471,644
Summerside Armoury (PE) 40,000 8,000   45,260 11,315 -5,260
Sydney Underground Storage Tank Removal (NS) 400,000 80,000   118,521 29,630 281,479
TCE Contamination Valcartier (QC) 4,700,000 0   2,915,968 0 1,784,032
YA 2 - Small Boat Float (BC) 1,600,000 320,000   185,957 46,489 1,414,043
Assessments (43 projects) 5,310,337 1,062,067   5,310,337 2,347,114 0
Total DND 56,314,473 6,773,297   48,134,620 8,671,016 8,179,853
             
Environment Canada (EC)            
Hydrometric Stations in BC (BC) 74,400 14,880   81,876 20,468 -7,476
Hydrometric Stations in QC (QC) 100,000 20,000   0 0 100,000
Hydrometric Stations in SK 2007-08 (SK) 144,400 28,880   62,708 15,677 81,692
Lansdowne House (EC) (0N) 77,684 15,537   0 0 77,684
PEC (BC) 4,786,600 574,392   2,523,305 429,908 2,263,295
Pointe-de-l'Est RNF (APEC) (QC) 42,120 8,424   28,465 7,116 13,655
Projet de rehabilitation - Ile de la Providence (QC) 91,941 18,388   0 0 91,941
Sable Island Upper Air Station (NS) 47,064 9,413   0 0 47,064
Assessments (15) 3,976,350 795,270   634,652 158,663 3,341,698
Total EC 9,340,559 1,485,184   3,331,006 631,832 6,009,553
             
Health Canada (HC)            
Kasabonika (ON) 52,800 10,560   41,290 20,443 11,510
Lansdowne House (ON) 52,800 10,560   0 0 52,800
Moose Factory Hospital (ON) 320,000 64,000   144,000 31,833 176,000
Remediation of North Spirit Lake (former) Nursing Station (ON) 104,000 20,800   0 0 104,000
Remediation of Norway House Hospital (MB) 96,000 19,200   103,000 25,750 -7,000
Remediation of Red Sucker Lake Nursing Station (MB) 96,000 19,200   14,769 3,872 81,231
Remediation of Shamattawa Nursing Station (MB) 80,000 16,000   52,676 13,169 27,324
Remediation of Summer Beaver Nursing Station (ON) 96,000 19,200   10,350 16,983 85,650
Remediation of Wapekeka Nursing Station (ON) 53,600 10,720   0 0 53,600
Weagamow Lake (ON) 80,000 16,000   76,500 24,333 3,500
Assessment (10) 136,000 27,200   136,000 262,381 0
Total HC 1,167,200 233,440 143,166 b 578,585 398,764 731,781
             
Indian and Northern Affairs Canada - Indian and Inuit Affairs Business Line (INAC-IIABL)            
1550 Clifford Road (BC) 0 0   113,000 28,250 -113,000
Barrenlands Former DOT Site (MB) 240,000 48,000   88,800 22,200 151,200
Barrenlands/Brochet Frontier School Tankfarm (MB) 68,240 13,648   37,476 9,369 30,764
Big Grassy First Nation (ON) 64,000 12,800   32,200 8,000 31,800
Bob Thomas and IR # 5 (BC) 1,051,600 210,320   136,800 34,200 914,800
Burnt Church - Off old bridge road contaminated site remediation (NB) 0 0   120,000 30,000 -120,000
Former Beren's River Pumphouse Tankfarm (MB) 372,960 74,592   198,880 49,720 174,080
Former God's Lake School Tankfarm (MB) 221,840 44,368   250,560 62,640 -28,720
Former Northlands School Tankfarm (MB) 52,880 10,576   29,104 7,276 23,776
Former Red Sucker Lake School Tankfarm (MB) 1,004,000 200,800   720,720 180,180 283,280
Former School Site "Manto Sipi Cree Nation" (MB) 360,000 72,000   104,400 26,100 255,600
Gitwinksihlkw Front of Village Administration Office (BC) 55,000 11,000   0 0 55,000
Gitxaala Nation Former Power House (BC) 0 0   1,690,913 422,728 -1,690,913
God's Lake Band Tankfarm (MB) 221,840 44,368   250,560 62,640 -28,720
Goodfish Drycleaning Plant Remediation (AB) 0 0   48,954 12,239 -48,954
Heiltsuk Community School (BC) 80,634 16,127   0 0 80,634
Kahnawake - ancien dépotoir Beauvais (QC) 10,400 2,080   6,031 1,508 4,369
Kahnawake - Ancien dépotoir Goodleaf (QC) 10,400 2,080   6,031 1,508 4,369
Kahnawake - Ancien dépotoir Johnson's Point (QC) 10,400 2,080   6,031 1,508 4,369
Kahnawake - Ancien dépotoir Khanata (QC) 10,400 2,080   6,031 1,508 4,369
Kahnawake - Ancien dépotoir Morris (QC) 10,400 2,080   6,031 1,508 4,369
Kahnawake - Ancien dépotoir Patton-Lawrence (QC) 10,400 2,080   6,031 1,508 4,369
Kingfisher Lake Omahama Store (ON) 50,240 10,048   50,240 12,560 0
Kwadacha Powerhouse (BC) 318,200 63,640   43,191 10,798 275,009
Macoah I.R. 1 Generator Site Remediation (BC) 179,136 35,827   285,341 71,335 -106,205
Mathias Colomb Area 5B (MB) 1,249,600 249,920   625,600 156,400 624,000
Mistawasis Bluestone Pit (SK) 64,000 12,800   26,080 6,520 37,920
Nemaska - station service Cree Energy (QC) 8,000 1,600   0 0 8,000
Obedjiwan - Poste de police (QC) 48,000 9,600   0 0 48,000
Red Bridge Spur (BC) 2,000 400   0 0 2,000
Remediation of Former Cutler Acid Site (ON) 200,000 40,000   253,880 63,470 -53,880
Sandy Lake Remediation Project (ON) 960,000 192,000   833,380 208,320 126,620
Squamish Nation Kits Wye Site (BC) 39,144 7,829   0 0 39,144
St. Theresa Point - Former School Tankfarm & Distribution Lines (MB) 320,000 64,000   100,000 25,000 220,000
Tahltan First Nation- Dease Lake band maintenance yard (BC) 174,023 34,805   0 0 174,023
Tsay Keh Dene generator station (BC) 286,900 57,380   41,482 10,371 245,418
Unamen Shipu - Camp des travailleurs (QC) 0 0   9,784 2,446 -9,784
Wapekeka Soil Remediation Project (ON) 1,469,600 293,920   1,480,000 370,000 -10,400
Assessment (47) 3,307,008 661,402 154,995 b 2,310,115 567,679 921,888
      -230,000 c      
Total INAC-IIABL 12,531,245 2,506,249 1,216,238 d 9,917,646 2,469,489 3,829,837
             
Indian and Northern Affairs Canada - Northern Affairs Organization (INAC-NAO)            
Axe Point (NT) 2,944,000 588,800   1,481,313 370,328 1,462,687
BAR D - Atkinson Point (NT) 7,935,512 1,428,392   3,843,779 960,945 4,091,733
Bear Island (NU) 16,000 3,200   455,756 113,939 -439,756
CAM D - Simpson Lake (NU) 96,000 19,200   239,941 59,985 -143,941
CAM F - Sarcpa Lake (NU) 5,630,286 563,029   5,129,352 569,928 500,934
Cape Christian (NU) 2,684,000 536,800   444,958 111,239 2,239,042
Clinton Creek Mine (YT) 298,400 59,680   147,686 36,921 150,714
Colomac Mine (NT) 9,170,534 0   11,730,181 0 -2,559,647
Contact Lake (NT) 619,200 123,840   601,759 150,440 17,441
Discovery Mine (NT) 981,796 196,359   1,021,803 102,922 -40,007
El Bonanza Mine (NT) 669,200 133,840   477,633 119,408 191,567
Faro Mine (YT) 14,620,000 0   15,537,999 0 -917,999
FOX A - Bray Island (NU) 120,000 24,000   9,959 2,490 110,041
FOX C - Ekalugad Fjord (NU) 8,398,574 1,679,715   5,009,951 556,661 3,388,623
Giant Mine (NT) 11,680,000 0   10,752,398 0 927,602
Indore Gold Mine-Beaverlodge Lake (NT) 388,695 77,739   250,165 62,541 138,530
Johnson Pt (NT) 956,000 191,200   382,897 95,724 573,103
Mount Nansen Mine (YT) 1,476,000 295,200   1,062,005 265,501 413,995
North Inca Mine - Remediation (NT) 446,695 89,339   282,006 70,501 164,689
Padloping Island (NU) 296,000 59,200   0 0 296,000
PIN B - Clifton Point (NU) 244,000 48,800   507,306 126,826 -263,306
PIN E - Cape Peel (NU) 16,000 3,200   0 0 16,000
Port Radium Mine (NT) 7,110,328 853,239   4,012,197 179,523 3,098,131
Radio Island (NU) 2,677,150 535,430   2,906,473 726,618 -229,323
Roberts Bay Mine (NU) 1,526,560 305,312   465,374 116,343 1,061,186
Silver Bear Mines (NT) 3,444,800 688,960   1,072,576 268,144 2,372,224
Tundra-Taurcanis Mine (NT) 8,959,500 1,791,900   4,700,244 522,249 4,259,256
United Keno Hill Mine (YT) 3,132,405 313,241   3,043,848 338,205 88,557
Assessment (118) 1,120,000 224,000 439,122 b 898,806 224,706 660,316
Total INAC-NAO 97,657,635 10,833,615 3,133,322 c 76,468,365 6,152,087 24,322,592
             
National Capital Commission (NCC)            
Bayview Remediation (ON) 56,000 11,200   56,000 33,474 0
Ridge Road Landfill (ON) 136,000 27,200   136,000 79,665 0
Assessment (23) 608,800 121,760 870 b 566,633 141,658 43,037
Total NCC 800,800 160,160 870 758,633 254,797 43,037
Natural Resources Canada (NRCan)            
Assessments (4) 128,000 25,600 47,810 b 35,428 8,857 140,382
Total NRCan 128,000 25,600 47,810 35,428 8,857 140,382
Parks Canada Agency (PC)            
Banff National Park Site Remediation (AB) 14,400 2,880   14,400 51,100 0
Cape Breton Highlands NP (NS) 296,451 59,290   613,854 153,463 -317,403
Dégagement chenal (QC) 0 0   0 0 0
Enlèvement haut fonds (QC) -18,400 -3,680   0 0 -18,400
Glacier National Park (BC) 13,200 2,640   19,900 5,600 -6,700
Ingonish Compound Remediation (NS) 184,000 36,800   0 0 184,000
Ivvavik NP, Sheep Creek Fuel Spill (YT) 19,248 3,850   8,548 2,137 10,700
Lachine site 12.2 (QC) 192,000 38,400   48,800 12,200 143,200
Quttinirpaaq NP - Tanquary Fiord (NU) 142,032 28,406   130,675 32,669 11,357
Remediation of Gilman River, Quttinirpaaq National Park (NU) 8,080 1,616   27,437 10,554 -19,357
Riding Mountain NP, Maintenance Compound Garage, Former UST (MB) 13,780 2,756   26,480 6,620 -12,700
Waterton Lakes NP - Stalage Salt Storage remediation (AB) 44,192 8,838   114,680 28,670 -70,488
Assessment (34) 1,176,341 235,268 230,000 d 1,343,122 391,705 63,219
Total PC 2,085,324 417,065 851,873 e 2,347,896 694,718 589,301
             
Public Works and Government Services Canada (PWGSC)            
350 King Edward Monitoring Program (ON) 40,000 8,000   39,605 9,901 395
Alaska Highway - Fireside Maintenance Camp R/RM (BC) 186,160 37,232   129,360 32,340 56,800
Alaska Highway - Fort Nelson Gravel Pit R/RM (BC) 31,200 6,240   36,560 9,140 -5,360
Alaska Highway - Iron Creek Maintenance Camp (YT) 140,514 28,103   102,116 25,529 38,398
Alaska Highway - Liard River Maintenance Camp R/RM (BC) 622,960 124,592   743,009 185,752 -120,049
Alaska Highway - Muncho Lake Maintenance Camp R/RM (BC) 204,880 40,976   122,480 30,620 82,400
Alaska Highway - Sikanni Maintenance Camp R/RM (BC) 101,140 20,228   73,940 18,485 27,200
Alaska Highway - Steamboat Maintenance Camp R/RM (BC) 36,400 7,280   17,760 4,440 18,640
Alaska Highway - Toad Maintenance Camp - R/RM (BC) 528,320 105,664   536,320 134,080 -8,000
Campbell River Federal Building - Risk Management (BC) 20,047 4,009   0 0 20,047
Décontamination des sols Beauceville (QC) 680,000 136,000   26,247 6,561 653,753
Esquimalt Graving Dock Uplands - Risk Management (BC) 14,000 2,800   6,954 1,738 7,046
Esquimalt Graving Dock Waterlot - Risk Management (BC) 267,600 53,520   170,466 42,617 97,134
Former DND Radar Base Restoration (ON) 0 0   0 50,335 0
Kelowna Federal Building - Risk Management (BC) 6,400 1,280   0 0 6,400
Penhold Transmitter Bunker MPES (AB) 137,840 27,568   105,702 26,425 32,138
Remedial Action at Moose Factory (ON) 20,000 4,000   17,184 7,500 2,816
Assessment (11) 958,764 191,753   851,119 350,940 107,645
Total PWGSC 3,996,225 799,245   2,978,822 936,403 1,017,403
             
Royal Canadian Mounted Police (RCMP)            
Coquitlam RCMP Gun Range (BC) 176,000 35,200   345,994 86,498 -169,994
Ft. Providence RCMP Remediation (NT) 40,000 8,000   35,110 8,777 4,890
Haines Junction RCMP Garage (YT) 72,000 14,400   52,569 13,142 19,431
Holman Detachment Remediation (NT) 56,000 11,200   0 0 56,000
Hopedale RCMP Remediation (NL) 48,000 9,600   65,906 16,477 -17,906
Lac Megantic Remediation (QC) 196,000 39,200   0 0 196,000
Nain RCMP Complex (NL) 158,400 31,680   62,423 15,606 95,977
Nelson RCMP District Office (BC) 132,000 26,400   68,934 17,233 63,066
Old Crow RCMP Detachment Compound (YT) 88,800 17,760   0 0 88,800
Old Firing Range, RCMP Depot Training Academy (SK) 940,000 188,000   139,015 34,753 800,985
Rigolet (Former Detachment Location) (NL) 110,400 22,080   12,866 3,217 97,534
Winnipeg Air Services Hangar (MB) 196,000 39,200   129,295 32,324 66,705
Assessment (188) 2,820,000 564,000   2,020,622 519,515 799,378
Total RCMP 5,033,600 1,006,720   2,932,734 747,542 2,100,866
Transport Canada (TC)            
Bonnechere Airport remediation (ON) 188,000 37,600   221,013 55,253 -33,013
Bushell Public Port Facility Remediation (SK) 3,333,920 666,784   2,985,241 746,310 348,679
Coal Harbour Public Port Facility Remediation (BC) 16,560 3,312   16,000 4,000 560
Décontamination – Terrains excédentaires . Villlage de Kuujjuaq (QC) 481,040 96,208   99,533 24,883 381,507
Former Remote Radar Site 59 (NL) 240,000 48,000   102,367 25,592 137,633
Fort Nelson Airport Environmental Remediation (BC) 2,804,050 560,810   2,456,623 614,156 347,427
Nitchequon (QC) 397,920 79,584   254,981 63,745 142,939
Pickering Lands Site PIN 614462 Remediation (ON) 567,504 113,501   589,918 147,480 -22,414
Remediate Helicopter Site (NL) 24,000 4,800   10,270 2,567 13,730
Remediate Marine Fire Training Area (NL) 280,000 56,000   188,000 47,000 92,000
Remediate Soil and Groundwater at FTA (NL) 325,440 65,088   6,148 1,537 319,292
Rock Bay (BC) 1,476,000 147,600   1,341,938 149,104 134,062
Smithers Airport FFTA Remediation (BC) 217,040 43,408   94,116 23,529 122,924
Watson Lake Remediation (YT) 747,634 149,527   0 0 747,634
Williams Lake Airport FFTA Remediation (BC) 449,840 89,968   367,287 91,822 82,553
Assessment (5 projects) 520,000 104,000   111,000 103,000 409,000
Total TC 12,068,948 2,266,190 0 b 8,844,435 2,099,978 3,224,513
Jacques Cartier and Champlain Bridges Incorporated (JCCBI)            
Projet pilote Parcelle 3 (QC) 92,000 18,400   0 0 92,000
Total JCCBI 92,000 18,400   0 0 92,000
Total for remediation/risk management 192,689,953 24,819,953 5,632,568 146,879,259 19,182,048 51,443,262
Total for assessment 25,000,000 5,000,000 2,886,247 18,483,725 6,142,690 9,402,522
GRAND TOTAL 217,689,953 29,819,953 8,518,815 165,362,984 25,324,738 60,845,784

Appendix 4: List of Acronyms

AAFC
Agriculture and Agri-Food Canada
ADM
Assistant Deputy Minister
AST
Above ground storage tanks
BTEX
Benzene Toluene Ethyl-Benzene Xylene
CCME
Canadian Council of Ministers of the Environment
CSC
Correctional Service Canada
CSMP
Contaminated Sites Management Plan
CSMWG
Contaminates Sites Management Working Group
DEW
Distant Early Warning
DFO
Fisheries and Oceans Canada
DNAPL
Dense Non-Aqueous Phase Liquids
DND
National Defence
EC
Environment Canada
ECO Canada
Environmental Careers Organization
ERE
Ecological Risk Evaluations
FCSAAP
Federal Contaminated Sites Accelerated Action Plan
FCSAP
Federal Contaminated Sites Action Plan
FFTA
Fire Fighter Training Area
FY
Fiscal Year
HC
Health Canada
INAC
Indian and Northern Affairs Canada
INAC-IIABL
Indian and Northern Affairs Canada - Indian and Inuit Affairs Business Line
INAC-NAO
Indian and Northern Affairs Canada - Northern Affairs Organization
JCCBI
Jacques Cartier and Champlain Bridges Inc.
NCC
National Capital Commission
NRCan
Natural Resources Canada
PAHs
Polycyclic aromatic hydrocarbons
PCBs
Polychlorinated biphenyls
PCDD/Fs
Polychlorinated dibenzo-p-dioxins and dibenzofurans
PWGSC
Public Works and Government Services Canada
RCMP
Royal Canadian Mounted Police
TBS
Treasury Board Secretariat
TC
Transport Canada

[1] Taking Action on Federal Contaminated Sites: An Environmental and Economic Priority (Environment Canada, July 2005), p. ii.

[2] Public Accounts of Canada 2008, Volume I (PWGSC, 2008), S. 5, p. 5.12.

[3] Taking Action on Federal Contaminated Sites: An Environmental and Economic Priority (EC, July 2005), p. ii

[4] The CCME provides the principal forum among governments in Canada for the joint development of environmental policies and technical guidance for environmental management. The National Classification System for Contaminated Sites is a screening tool for the evaluation of contaminated sites according to their current or potential adverse impacts on human health and the environment. Sites are classified as:

  • Class 1 - High Priority for Action
  • Class 2 - Medium Priority for Action
  • Class 3 - Low Priority for Action
  • Class N - Not a Priority for Action
  • Class INS - Insufficient Information

The National Classification System for Contaminated Sites was updated and a new version was released in 2008. Custodians may also seek remediation / risk management funding for sites classified as Class 1 or 2 using the Federal Contaminated Sites Action Plan Classification System (2005).

[5] Care and maintenance activities are initiated in exceptional circumstances to prevent severe environmental damage or catastrophes from occurring before a site assessment can be completed and/or an action plan can be developed. Short-term activities are undertaken to reduce or prevent the spread of contamination in order to avoid an imminent environmental disaster that would harm human and/or wildlife populations. In past years, care and maintenance have been implemented at several abandoned/idled mines or other large properties with extensive contamination.

[6] In 2007-08, six projects received 100% FCSAP funding: Giant Mine, Faro Mine, Colomac Mine, 5 Wing Goose Bay, TCE Valcartier and DYE-M Cape Dyer DEW Line. Six projects received 90% FCSAP funding: FOX-M Hall Beach DEW Line, United Keno Hill Mine, Rock Bay, CAM-F Sarcpa Lake, FOX-C Ekalugad Fjord, and CAM-2 Gladman Point. Four projects received between 82.5% and 84.9% FCSAP funding: Port Radium Mine (83.8%), CAM-3 Shepherd Bay (84.9%), Tundra-Taurcanis Mine (84.5%) and PEC (82.5%).

[7] The allocated amount presented does not include the FCSAP funds of approximately $8.5M carried forward from 2006-07. Actual available funding for 2007-08 would therefore be $226M.

[8] The actual amount of assessment expenditures by province/territory was not reported in 2007-08. Instead, the national distribution of fuds was estimated using a proportion of each department's reported expenditures and the number of sites that the department worked on in each province/territory. Confirmed assessment expenditures by province/territory are expected to be included within reporting in future years of the Program.

[9] Actual total assessment expenditure reported for 2007-08.

[10] $2,886,247 = Five custodians transferred FCSAP funds from fiscal year 2006-2007 to 2007-2008 in the amount of $47,810 (Natural Resources Canada [NRCan]), $594,117 (Indian and Northern Affairs Canada [INAC] : $154,995 (INAC-IIABL) and $439,122 (INAC-NAO)), $1,503,260 (DFO), $27,921 (Correctional Service of Canada [CSC]), $870 (National Capital Commission [NCC]). One custodian received funds from DFO Expert Support in the amount of $712,269 (DFO).

[11]Ten custodians transferred FCSAP funds from fiscal year 2007-2008 to 2008-2009, in the amount of $1,843,320 (INAC : $660,316 (INAC-NAO) and $1,183,004 (INAC-IIABL)), $790,465 (RCMP), $2,537,935 (DFO), $63,219 (Parks Canada Agency [PC]), $128,000 (NRCan), $1,532,145 (EC), $43,037 (NCC), $27,921 (CSC), $287,600 (AAFC) and $409,000 (TC).

[12] The streamlined process refers to the provision of an NCS or FCSAP score for projects with a total estimated project cost of $50,000 while the regular process refers to the provision of an NCS or FCSAP score as well as the completion of an ecological risk evaluation and a preliminary quantitative risk assessment for the project. Refer to Appendix 1 for details on these processes.

[13] Atlantic Canada includes: New Brunswick, Nova Scotia, Prince Edward Island, and Newfoundland and Labrador.

[14] Four custodians transferred FCSAP funds from fiscal year 2006-2007 to 2007-2008, in the amount of $143,166 (HC), $3,985,443 (INAC : $2,694,200 (NAO) and $1,291,243 (IIABL)), $882,086 (CSC), and $621,873 (PC). In 2006-07 two custodians had identified that they were transferring funds to 2008-09. Of these funds, TC reported that they returned $2,964,000 to the fiscal framework and transferred $5,710,000 originally allocated in 2006-07 to fiscal year 2008-09. This includes assessment funding in the amount of $459,457 that was transferred to 2007-08 with the intention of being spent on remediation / risk management projects. DFO transferred $3,360,000 originally allocated in 2006-07 to fiscal year 2008-09.

[15] Eight custodians transferred FCSAP funds from fiscal year 2007-2008 to 2008-2009, in the amount of $2,532,000 (TC), $19,748,371 (INAC : $17,258,825 (NAO) and $2,489,546 (IIABL)), $526,082 (PC), $6,636,211 (DFO), $1,060,737 (CSC), $731,781 (HC), $1,251,751 (RCMP), and $2,667,855 (EC).

[16] A small percentage of these remediation / risk management projects are found in early steps of the 10-step for a few reasons: unexpected contamination and/or addition of new sites to a project may require stepping back from remediation activities and conduct additional assessment activities at those sites.

[17] Activities under step 8 can be categorized as active, being risk-reducing activities (Steps 8 B (removal of contaminated media off-site) / 8 C (treatment of contaminated media) / 8 D (containment or other risk reduction activities)) and planning activities (Step 8 A). As an example, activity under Step 8 A could include technology evaluation or contractor selection.

[18] The existing definition was intended to ensure that all possible treatment technologies applied to FCSAP sites were identified. However, this initial definition is under review, and, based on consultations within the federal contaminated sites community, it is expected that the term "innovative technology" will be revised in future years of FCSAP. Thus, the annual statistical analysis of innovative technology uptake will not be directly comparable year over year until this definition is finalized.

[19] Public Accounts of Canada 2008, Volume I (PWGSC, 2008), S. 2, pp. 2.10-2.11.

[20] Ibid., S. 5, p. 5.12.

[21] Public Accounts of Canada 2008, Volume I (PWGSC, 2008), S. 5, p. 5.12.

[22] Public Works and Government Services Canada Departmental Performance Report 2007-2008 (PWGSC, 2008), S. IV, Notes to the Consolidated Financial Statements (Unaudited).

[23] Natural Resources Canada 2008-2011 Contaminated Sites Management Plan.

[24] Includes the environmental liability for Port Hope Area Initiative (shared responsibility site which is managed outside of FCSAP).

[25] Includes the environmental liability for Sydney Tar Ponds.

[26] Public Accounts of Canada 2008, Volume I (PWGSC, 2008), S. 5, p. 5.12.

[27] National Classification System for Contaminated Sites, CCME, March 1992.